by Ashiana Housing Limited · Infotech Park (Hinjawadi), Pune

Possession date of Ashiana Malhar Phase II: 30 September 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100052593, and currently active. Its completion date is now September 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Ashiana Malhar Phase II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Ashiana Malhar Phase II has moved

  1. 31 May 2027

    Completion date given when the project was registered

  2. 30 September 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ashiana Malhar Phase II’s extension records on MahaRERA (P52100052593), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ashiana Malhar Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100052593
Status
Registered and active
Builder
Ashiana Housing Limited
Location
Infotech Park (Hinjawadi), Pune · 411057
Project type
Residential / Group Housing
Registered on
11 Sep 2023
Completion date at registration
May 2027
Latest completion date
September 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
220
Sold or booked
96%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of Ashiana Malhar Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
T- 8100%100%100%85%
T - 9100%100%100%85%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ashiana Malhar Phase II every month.

Ashiana Malhar Phase II: buildings, flats and land, as filed on MahaRERA

  • Buildings: T- 8 (15 floors, 110 units) · T - 9 (15 floors, 110 units)
  • Car parking: 16 covered, 195 open
  • Land: 9,735 sq m (about 2.4 acres) · sanctioned built-up 19,333 sq m

The builder’s record and reviews

Ashiana Housing has 8 projects on MahaRERA since 2022, this one included. Of the 8 GharKundli has checked: 8 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Ashiana Malhar Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ashiana Malhar Phase II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Ashiana Malhar Phase II

What is the possession date of Ashiana Malhar Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ashiana Malhar Phase II in Infotech Park (Hinjawadi), Pune is 30 September 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Ashiana Malhar Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ashiana Malhar Phase II's builder has filed on MahaRERA, the official one, is 30 September 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Ashiana Malhar Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ashiana Malhar Phase II in Infotech Park (Hinjawadi), Pune is P52100052593.

Is Ashiana Malhar Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ashiana Malhar Phase II is registered as P52100052593 and its status is "Registered and active".

What is the construction status of Ashiana Malhar Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Ashiana Malhar Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Ashiana Malhar Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Ashiana Malhar Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Ashiana Malhar Phase II is registered on MahaRERA as P52100052593, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Ashiana Malhar Phase II have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Ashiana Malhar Phase 4 (PR1260002501981, possession 30 Jan 2030); ASHIANA MALHAR PHASE III (P52100076601, possession 31 Jul 2028). Check that your agreement names the registration of your own wing.

How can I get updates if Ashiana Malhar Phase II's possession date changes?

The latest dates are on Ashiana Malhar Phase II's MahaRERA page (P52100052593). GharKundli's Kundli Watch sends a free WhatsApp update on Ashiana Malhar Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ashiana Malhar Phase II have?

According to GharKundli's check of MahaRERA records (updated November 2026), Ashiana Malhar Phase II has 2 buildings filed: T- 8 with 15 floors and 110 units; T - 9 with 15 floors and 110 units.

How much parking does Ashiana Malhar Phase II have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 16 covered and 195 open car parking spaces for Ashiana Malhar Phase II.

How big is the land of Ashiana Malhar Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Ashiana Malhar Phase II stands on 9,735 sq m of land (about 2.4 acres), with 19,333 sq m of sanctioned built-up area.

What is the track record of Ashiana Malhar Phase II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Ashiana Housing has 8 projects on MahaRERA since 2022, this one included. Of the 8 GharKundli has checked: 8 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Ashiana Malhar Phase II?

Google Maps has reviews of Ashiana Malhar Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Ashiana Malhar Phase II?

Ashiana Malhar Phase II by Ashiana Housing Limited is in Infotech Park (Hinjawadi), Pune (pincode 411057), Maharashtra, and is registered on MahaRERA as P52100052593, per GharKundli's check of MahaRERA records.

How many homes are in Ashiana Malhar Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Ashiana Malhar Phase II has 220 homes in 2 towers registered on MahaRERA, and 96% of them are sold or booked.

When was Ashiana Malhar Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ashiana Malhar Phase II was registered on MahaRERA on 11 September 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Ashiana Malhar Phase II?

No court cases are listed for Ashiana Malhar Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Ashiana Malhar Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ashiana Housing Limited, which has 7 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Other projects in pincode 411057

All 430 projects in Wakad (411057) →

Other projects by Ashiana Housing Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.