by Swami Developers · Maval, Pune

Possession date of Guruta Nakshatra: 30 April 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100052651, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Guruta Nakshatra?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Guruta Nakshatra has moved

  1. 31 December 2030

    Completion date given when the project was registered

  2. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Guruta Nakshatra’s extension records on MahaRERA (P52100052651), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Guruta Nakshatra

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100052651
Status
Registered and active
Builder
Swami Developers
Location
Maval, Pune · 410506
Project type
Others
Registered on
15 Sep 2023
Completion date at registration
December 2030
Latest completion date
April 2031
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
90
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Guruta Nakshatra, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Guruta Nakshatra100%77%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Guruta Nakshatra: covers Basement Floor, Ground Floor, Typical 1st to 7th Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Guruta Nakshatra every month.

Guruta Nakshatra: buildings, flats and land, as filed on MahaRERA

  • Buildings: Guruta Nakshatra (9 floors, 95 units)
  • Land: 1,428 sq m (about 0.4 acres) · sanctioned built-up 4,711 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Guruta Nakshatra →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Guruta Nakshatra: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Guruta Nakshatra

What is the possession date of Guruta Nakshatra?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Guruta Nakshatra in Maval, Pune is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Guruta Nakshatra?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Guruta Nakshatra's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Guruta Nakshatra?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Guruta Nakshatra in Maval, Pune is P52100052651.

Is Guruta Nakshatra registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Guruta Nakshatra is registered as P52100052651 and its status is "Registered and active".

What is the construction status of Guruta Nakshatra?

According to GharKundli's check of MahaRERA records (updated November 2026), Guruta Nakshatra's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Guruta Nakshatra is 77% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Guruta Nakshatra have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Guruta Nakshatra safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Guruta Nakshatra is registered on MahaRERA as P52100052651, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Guruta Nakshatra's possession date changes?

The latest dates are on Guruta Nakshatra's MahaRERA page (P52100052651). GharKundli's Kundli Watch sends a free WhatsApp update on Guruta Nakshatra every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Guruta Nakshatra have?

According to GharKundli's check of MahaRERA records (updated November 2026), Guruta Nakshatra has one building filed: Guruta Nakshatra with 9 floors and 95 units.

How big is the land of Guruta Nakshatra?

According to GharKundli's check of MahaRERA records (updated November 2026), Guruta Nakshatra stands on 1,428 sq m of land (about 0.4 acres), with 4,711 sq m of sanctioned built-up area.

Where can I read reviews of Guruta Nakshatra?

Google Maps has reviews of Guruta Nakshatra written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Guruta Nakshatra?

Guruta Nakshatra by Swami Developers is in Maval, Pune (pincode 410506), Maharashtra, and is registered on MahaRERA as P52100052651, per GharKundli's check of MahaRERA records.

How many homes are in Guruta Nakshatra?

According to GharKundli's check of MahaRERA records (updated November 2026), Guruta Nakshatra has 90 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Guruta Nakshatra registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Guruta Nakshatra was registered on MahaRERA on 15 September 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Guruta Nakshatra?

No court cases are listed for Guruta Nakshatra on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Guruta Nakshatra?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Swami Developers, which has 1 other project registered on MahaRERA.

All projects with possession due in 2031 in Pune →

Other projects in Mawal

All 104 projects in Talegaon Dabhade (410506) →

Other projects by Swami Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.