SOMANI CENTRE
by SOMANI DEVELOPERS · Chinchwadgaon, Pune
Possession date of SOMANI CENTRE: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100052857, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SOMANI CENTRE?
How the possession date of SOMANI CENTRE has moved
30 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SOMANI CENTRE’s extension records on MahaRERA (P52100052857), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SOMANI CENTRE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100052857
- Status
- Registered and active
- Builder
- SOMANI DEVELOPERS
- Location
- Chinchwadgaon, Pune · 411033
- Project type
- Commercial
- Registered on
- 5 Oct 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 130
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SOMANI CENTRE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SOMANI CENTRE | 100% | 39% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SOMANI CENTRE every month.
SOMANI CENTRE: buildings, flats and land, as filed on MahaRERA
- Buildings: SOMANI CENTRE (3 floors)
- Land: 5,097 sq m (about 1.3 acres) · sanctioned built-up 488 sq m
The builder’s record and reviews
Fast Realty (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of SOMANI CENTRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SOMANI CENTRE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SOMANI CENTRE
What is the possession date of SOMANI CENTRE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SOMANI CENTRE in Chinchwadgaon, Pune is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SOMANI CENTRE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SOMANI CENTRE's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SOMANI CENTRE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SOMANI CENTRE in Chinchwadgaon, Pune is P52100052857.
Is SOMANI CENTRE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SOMANI CENTRE is registered as P52100052857 and its status is "Registered and active".
What is the construction status of SOMANI CENTRE?
According to GharKundli's check of MahaRERA records (updated November 2026), SOMANI CENTRE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SOMANI CENTRE is 39% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SOMANI CENTRE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SOMANI CENTRE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SOMANI CENTRE is registered on MahaRERA as P52100052857, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SOMANI CENTRE's possession date changes?
The latest dates are on SOMANI CENTRE's MahaRERA page (P52100052857). GharKundli's Kundli Watch sends a free WhatsApp update on SOMANI CENTRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SOMANI CENTRE have?
According to GharKundli's check of MahaRERA records (updated November 2026), SOMANI CENTRE has one building filed: SOMANI CENTRE with 3 floors.
How big is the land of SOMANI CENTRE?
According to GharKundli's check of MahaRERA records (updated November 2026), SOMANI CENTRE stands on 5,097 sq m of land (about 1.3 acres), with 488 sq m of sanctioned built-up area.
What is the track record of SOMANI CENTRE's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Fast Realty (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SOMANI CENTRE?
Google Maps has reviews of SOMANI CENTRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SOMANI CENTRE?
SOMANI CENTRE by SOMANI DEVELOPERS is in Chinchwadgaon, Pune (pincode 411033), Maharashtra, and is registered on MahaRERA as P52100052857, per GharKundli's check of MahaRERA records.
How many homes are in SOMANI CENTRE?
According to GharKundli's check of MahaRERA records (updated November 2026), SOMANI CENTRE has 130 homes in 1 tower registered on MahaRERA.
When was SOMANI CENTRE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SOMANI CENTRE was registered on MahaRERA on 5 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SOMANI CENTRE?
No court cases are listed for SOMANI CENTRE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SOMANI CENTRE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SOMANI DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of SOMANI CENTRE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in pincode 411033
- GANGA AMBER PH II
- AISHWARYAM INSIGNIA
- RAMAN STELLAR
- Nirman Serenopolis
- ROHAN HARITA PHASE 4
- Millennium Samriddhi
- KOHINOOR UPTOWN AVENUE
- West World
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.