by Kishor Walhe · Boisar, Palghar

Possession date of DARSHAN COMPLEX: 31 December 2027, moved from 30 December 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000016305, and currently active. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about DARSHAN COMPLEX?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DARSHAN COMPLEX has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA05062621254)

    Reason the builder gave MahaRERA: “Reason”

Source: DARSHAN COMPLEX’s extension records on MahaRERA (P99000016305), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DARSHAN COMPLEX

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000016305
Status
Registered and active
Builder
Kishor Walhe
Location
Boisar, Palghar · 401501
Project type
Others
Registered on
3 May 2018
Completion date at registration
December 2025
Latest completion date
December 2027
Delay so far
24 months
Homes
28
Sold or booked
33%
Towers
2
Complaints on MahaRERA
4
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found

Construction progress of DARSHAN COMPLEX, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building No 2, Wing A to B100%100%0%0%
Building No 2, Wing C100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Building No 2, Wing A to B: covers 3 floors
  • Building No 2, Wing C: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DARSHAN COMPLEX every month.

DARSHAN COMPLEX: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building No 2, Wing A to B (3 floors, 25 units) · Building No 2, Wing C (3 floors, 17 units)
  • Car parking: 40 open
  • Land: 5,000 sq m (about 1.2 acres) · sanctioned built-up 2,866 sq m · recreational space 500 sq m
  • Boundaries filed include: Navapur - Boisar Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of DARSHAN COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DARSHAN COMPLEX: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DARSHAN COMPLEX

What is the possession date of DARSHAN COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DARSHAN COMPLEX in Boisar, Palghar is 31 December 2027 — 24 months later than 30 December 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for DARSHAN COMPLEX?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DARSHAN COMPLEX's builder has filed on MahaRERA, the official one, is 31 December 2027, already 24 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DARSHAN COMPLEX extended?

According to GharKundli's check of MahaRERA records (updated October 2026), DARSHAN COMPLEX's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Reason".

What is the RERA number of DARSHAN COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DARSHAN COMPLEX in Boisar, Palghar is P99000016305.

Is DARSHAN COMPLEX registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DARSHAN COMPLEX is registered as P99000016305 and its status is "Registered and active".

What is the construction status of DARSHAN COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), DARSHAN COMPLEX's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does DARSHAN COMPLEX have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is DARSHAN COMPLEX safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DARSHAN COMPLEX is registered on MahaRERA as P99000016305, its completion date has moved 24 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DARSHAN COMPLEX's possession date changes?

The latest dates are on DARSHAN COMPLEX's MahaRERA page (P99000016305). GharKundli's Kundli Watch sends a free WhatsApp update on DARSHAN COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DARSHAN COMPLEX have?

According to GharKundli's check of MahaRERA records (updated October 2026), DARSHAN COMPLEX has 2 buildings filed: Building No 2, Wing A to B with 3 floors and 25 units; Building No 2, Wing C with 3 floors and 17 units.

How much parking does DARSHAN COMPLEX have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 40 open car parking spaces for DARSHAN COMPLEX.

How big is the land of DARSHAN COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), DARSHAN COMPLEX stands on 5,000 sq m of land (about 1.2 acres), with 2,866 sq m of sanctioned built-up area and 500 sq m of recreational open space.

Where can I read reviews of DARSHAN COMPLEX?

Google Maps has reviews of DARSHAN COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DARSHAN COMPLEX?

DARSHAN COMPLEX by Kishor Walhe is in Boisar, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000016305, per GharKundli's check of MahaRERA records. Its boundaries filed there include Navapur - Boisar Road.

How many homes are in DARSHAN COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), DARSHAN COMPLEX has 28 homes in 2 towers registered on MahaRERA, and 33% of them are sold or booked.

When was DARSHAN COMPLEX registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DARSHAN COMPLEX was registered on MahaRERA on 3 May 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on DARSHAN COMPLEX?

No court cases are listed for DARSHAN COMPLEX on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of DARSHAN COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kishor Walhe.

All projects with possession due in 2027 in Palghar →

Other projects in pincode 401501

All 128 projects in Boisar (401501) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.