Palchin Mango Tree Villa Phase 1

by Palchin Real Estates Private Limited · Shewalewadi, Pune 412307Also near Manjari Budruk, Manjri BkRegistered on MahaRERA as “Mango Tree Villa Phase 1”

What’s in the report? →

Possession date of Palchin Mango Tree Villa Phase 1 (MahaRERA P52100053978): 28 June 2029, moved from 31 July 2026 (31 months later). It has 8 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100053978, and currently active. Its completion date has moved from July 2026 to June 2029: 31 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100053978, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Palchin Mango Tree Villa Phase 1?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Palchin Mango Tree Villa Phase 1 has moved

  1. 31 July 2026

    Completion date given when the project was registered

  2. 28 February 2029

    Extended at the builder's request (MahaRERA application EA09062621283)

    Reason the builder gave MahaRERA: “As per the explanatory note and other documents attached.”
  3. 28 June 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Palchin Mango Tree Villa Phase 1’s extension records on MahaRERA (P52100053978), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Palchin Mango Tree Villa Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the June 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100053978
Status
Registered and active
Builder
Palchin Real Estates Private Limited
Location
Shewalewadi, Pune · 412307
Project type
Residential / Group Housing
Registered on
18 Dec 2023
Completion date at registration
July 2026
Latest completion date
June 2029
Delay so far
31 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
8
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Palchin Mango Tree Villa Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Row House R1 to R80%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Row House R1 to R8: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Palchin Mango Tree Villa Phase 1 every 1–2 months.

Palchin Mango Tree Villa Phase 1: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Palchin Real Estates has 7 projects on MahaRERA since 2023, this one included. Of the 7 GharKundli has checked: 7 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Palchin Mango Tree Villa Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Palchin Mango Tree Villa Phase 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Palchin Mango Tree Villa Phase 1

What is the possession date of Palchin Mango Tree Villa Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Palchin Mango Tree Villa Phase 1 in Shewalewadi, Pune is 28 June 2029 — 31 months later than 31 July 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 31 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Palchin Mango Tree Villa Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Palchin Mango Tree Villa Phase 1's builder has filed on MahaRERA, the official one, is 28 June 2029, already 31 months later than the 31 July 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Palchin Mango Tree Villa Phase 1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 1's builder applied to MahaRERA to extend the completion date once: to 28 February 2029, giving the reason "As per the explanatory note and other documents attached.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Palchin Mango Tree Villa Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Palchin Mango Tree Villa Phase 1 in Shewalewadi, Pune is P52100053978.

Is Palchin Mango Tree Villa Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 1 is registered as P52100053978 and its status is "Registered and active".

What is the current construction status of Palchin Mango Tree Villa Phase 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Row House R1 to R8 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Palchin Mango Tree Villa Phase 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Palchin Mango Tree Villa Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 1 is registered on MahaRERA as P52100053978, its completion date has moved 31 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Palchin Mango Tree Villa Phase 1?

Palchin Mango Tree Villa Phase 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Palchin Mango Tree Villa Phase 1?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Palchin Mango Tree Villa Phase 1: gharkundli.com/tools/property-cost-calculator

Has Palchin Mango Tree Villa Phase 1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 1 is still under construction, with 28 June 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Palchin Mango Tree Villa Phase 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Palchin Mango Tree Villa Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Palchin Mango Tree Villa Phase 1 have other wings or phases?

Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: Mango Tree Villa Phase 2 (P52100053927, possession 30 Oct 2029); Mango Tree Villa Tower 1 (P52100052683, possession 30 Oct 2027); Mango Tree Villa Tower 2 (P52100053177, possession 30 Nov 2027); Mango Tree Villa Tower 3 (P52100054077, possession 30 Jan 2030); Mango Tree Villa Tower 4 (P52100053966, possession 31 Jul 2029). Check that your agreement names the registration of your own wing.

How can I get updates if Palchin Mango Tree Villa Phase 1's possession date changes?

The latest dates are on Palchin Mango Tree Villa Phase 1's MahaRERA page (P52100053978). GharKundli's Kundli Watch sends a free WhatsApp update on Palchin Mango Tree Villa Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Palchin Mango Tree Villa Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 1 has one building filed: Row House R1 to R8 with 2 floors and 8 units.

How much parking does Palchin Mango Tree Villa Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 16 covered and 8 open car parking spaces for Palchin Mango Tree Villa Phase 1.

How big is the land of Palchin Mango Tree Villa Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 1 stands on 45,845 sq m of land (about 11.3 acres), with 2,108 sq m of sanctioned built-up area and 5,763 sq m of recreational open space.

What is the track record of Palchin Mango Tree Villa Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Real Estates has 7 projects on MahaRERA since 2023, this one included. Of the 7 GharKundli has checked: 7 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Palchin Mango Tree Villa Phase 1?

Google Maps has reviews of Palchin Mango Tree Villa Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Palchin Mango Tree Villa Phase 1?

Palchin Mango Tree Villa Phase 1 by Palchin Real Estates Private Limited is in Shewalewadi, Pune, pincode 412307 (near Manjari Budruk, Manjri Bk), Maharashtra, and is registered on MahaRERA as P52100053978, per GharKundli's check of MahaRERA records. GharKundli lists all 136 MahaRERA projects in Manjari Farm (412307).

How many flats are in Palchin Mango Tree Villa Phase 1, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 1 has 8 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Palchin Mango Tree Villa Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 1 was registered on MahaRERA on 18 December 2023. GharKundli did not find a title report on the land on file there.

Does Palchin Mango Tree Villa Phase 1 have any legal issues or court cases?

1 court case is listed for Palchin Mango Tree Villa Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Palchin Mango Tree Villa Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Palchin Real Estates Private Limited, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2029 in Pune →

Other projects in Manjari Farm (412307)

All 136 projects in Manjari Farm (412307) →

Other projects by Palchin Real Estates Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.