Palchin Mango Tree Villa Phase 2
by Palchin Real Estates Private Limited · Shewalwadi, Pune 412307Also near Manjari Budruk, Manjri BkRegistered on MahaRERA as “Mango Tree Villa Phase 2”
What’s in the report? →Possession date of Palchin Mango Tree Villa Phase 2 (MahaRERA P52100053927): 30 October 2029, moved from 30 April 2027 (26 months later). It has 5 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100053927, and currently active. Its completion date has moved from April 2027 to October 2029: 26 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100053927, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Palchin Mango Tree Villa Phase 2?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Palchin Mango Tree Villa Phase 2 has moved
30 April 2027
Completion date given when the project was registered
30 June 2029
Extended at the builder's request (MahaRERA application EA02072621654)
Reason the builder gave MahaRERA: “As per reasons of delay and other documents enclosed.”
30 October 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Palchin Mango Tree Villa Phase 2’s extension records on MahaRERA (P52100053927), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Palchin Mango Tree Villa Phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the October 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Mango Tree Villa Phase 1P52100053978 · possession 28 Jun 2029
- Mango Tree Villa Tower 1P52100052683 · possession 30 Oct 2027
- Mango Tree Villa Tower 2P52100053177 · possession 30 Nov 2027
- Mango Tree Villa Tower 3P52100054077 · possession 30 Jan 2030
- Mango Tree Villa Tower 4P52100053966 · possession 31 Jul 2029
- MahaRERA registration
- P52100053927
- Status
- Registered and active
- Builder
- Palchin Real Estates Private Limited
- Location
- Shewalwadi, Pune · 412307
- Project type
- Residential / Group Housing
- Registered on
- 11 Dec 2023
- Completion date at registration
- April 2027
- Latest completion date
- October 2029
- Delay so far
- 26 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 5
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of Palchin Mango Tree Villa Phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Row House R9 to R13 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Row House R9 to R13: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Palchin Mango Tree Villa Phase 2 every 1–2 months.
Palchin Mango Tree Villa Phase 2: buildings, flats and land, as filed on MahaRERA
- Buildings: Row House R9 to R13 (2 floors, 5 units)
- Car parking: 15 covered
- Land: 1,463 sq m (about 0.4 acres) · sanctioned built-up 1,318 sq m · recreational space 5,763 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Palchin Real Estates has 7 projects on MahaRERA since 2023, this one included. Of the 7 GharKundli has checked: 7 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Palchin Mango Tree Villa Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Palchin Mango Tree Villa Phase 2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Palchin Mango Tree Villa Phase 2
What is the possession date of Palchin Mango Tree Villa Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Palchin Mango Tree Villa Phase 2 in Shewalwadi, Pune is 30 October 2029 — 26 months later than 30 April 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 26 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Palchin Mango Tree Villa Phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Palchin Mango Tree Villa Phase 2's builder has filed on MahaRERA, the official one, is 30 October 2029, already 26 months later than the 30 April 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Palchin Mango Tree Villa Phase 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 2's builder applied to MahaRERA to extend the completion date once: to 30 June 2029, giving the reason "As per reasons of delay and other documents enclosed.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Palchin Mango Tree Villa Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Palchin Mango Tree Villa Phase 2 in Shewalwadi, Pune is P52100053927.
Is Palchin Mango Tree Villa Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 2 is registered as P52100053927 and its status is "Registered and active".
What is the current construction status of Palchin Mango Tree Villa Phase 2? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Row House R9 to R13 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Palchin Mango Tree Villa Phase 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Palchin Mango Tree Villa Phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 2 is registered on MahaRERA as P52100053927, its completion date has moved 26 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Palchin Mango Tree Villa Phase 2?
Palchin Mango Tree Villa Phase 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Palchin Mango Tree Villa Phase 2?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Palchin Mango Tree Villa Phase 2: gharkundli.com/tools/property-cost-calculator
Has Palchin Mango Tree Villa Phase 2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 2 is still under construction, with 30 October 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Palchin Mango Tree Villa Phase 2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Palchin Mango Tree Villa Phase 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Palchin Mango Tree Villa Phase 2 have other wings or phases?
Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: Mango Tree Villa Phase 1 (P52100053978, possession 28 Jun 2029); Mango Tree Villa Tower 1 (P52100052683, possession 30 Oct 2027); Mango Tree Villa Tower 2 (P52100053177, possession 30 Nov 2027); Mango Tree Villa Tower 3 (P52100054077, possession 30 Jan 2030); Mango Tree Villa Tower 4 (P52100053966, possession 31 Jul 2029). Check that your agreement names the registration of your own wing.
How can I get updates if Palchin Mango Tree Villa Phase 2's possession date changes?
The latest dates are on Palchin Mango Tree Villa Phase 2's MahaRERA page (P52100053927). GharKundli's Kundli Watch sends a free WhatsApp update on Palchin Mango Tree Villa Phase 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Palchin Mango Tree Villa Phase 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 2 has one building filed: Row House R9 to R13 with 2 floors and 5 units.
How much parking does Palchin Mango Tree Villa Phase 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered car parking spaces for Palchin Mango Tree Villa Phase 2.
How big is the land of Palchin Mango Tree Villa Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 2 stands on 1,463 sq m of land (about 0.4 acres), with 1,318 sq m of sanctioned built-up area and 5,763 sq m of recreational open space.
What is the track record of Palchin Mango Tree Villa Phase 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Real Estates has 7 projects on MahaRERA since 2023, this one included. Of the 7 GharKundli has checked: 7 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Palchin Mango Tree Villa Phase 2?
Google Maps has reviews of Palchin Mango Tree Villa Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Palchin Mango Tree Villa Phase 2?
Palchin Mango Tree Villa Phase 2 by Palchin Real Estates Private Limited is in Shewalwadi, Pune, pincode 412307 (near Manjari Budruk, Manjri Bk), Maharashtra, and is registered on MahaRERA as P52100053927, per GharKundli's check of MahaRERA records. GharKundli lists all 136 MahaRERA projects in Manjari Farm (412307).
How many flats are in Palchin Mango Tree Villa Phase 2, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 2 has 5 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Palchin Mango Tree Villa Phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Palchin Mango Tree Villa Phase 2 was registered on MahaRERA on 11 December 2023. GharKundli did not find a title report on the land on file there.
Does Palchin Mango Tree Villa Phase 2 have any legal issues or court cases?
1 court case is listed for Palchin Mango Tree Villa Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Palchin Mango Tree Villa Phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Palchin Real Estates Private Limited, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Palchin Mango Tree Villa Phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Pune →
Other projects in Manjari Farm (412307)
- Mango Tree Villa Villament Block 1
- Joyville Celestia Phase 1
- Joyville Celestia Phase 2
- Joyville Celestia Phase 3
- Joyville Celestia Phase 5
- Joyville Hadapsar Annexe Phase 17
- Joyville Hadapsar Annexe Retail
- Ews Building - Wing B
Other projects by Palchin Real Estates Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.