Swastik Epitome Building 2 Phase I Ground to 7 floors

by Hemant Ramesh Mhatre · Behind D Mart, PalgharAlso near Virar West, Virar East

Possession date of Swastik Epitome Building 2 Phase I Ground to 7 floors: 30 April 2027, moved from 31 December 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000006718, and currently active. Its completion date has moved from December 2019 to April 2027: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Swastik Epitome Building 2 Phase I Ground to 7 floors?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Swastik Epitome Building 2 Phase I Ground to 7 floors has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT99000003834)

    Reason the builder gave MahaRERA: “Delay in receiving CC/RDP for above floors (phase - 2). Work could not be completed due to the delay of higher floors”
  3. 31 March 2022

    Extended at the builder's request (MahaRERA application EXT99000011209)

    Reason the builder gave MahaRERA: “Due to delay in receiving permission and approvals to the said project from the respective competent authority.”
  4. 30 September 2022

    Extended at the builder's request (MahaRERA application EXT99000011676)

    Reason the builder gave MahaRERA: “The project is delayed due to worldwide Pandemic situation and unforeseen circumstances i.e. non-availability of labour, materials and lack of customer demand occurred”
  5. 31 August 2024

    Extended at the builder's request (MahaRERA application EXT99000017823)

    Reason the builder gave MahaRERA:
    “We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has also led to financial crisis hindering the completion of the projec…” Read the full reason“We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has also led to financial crisis hindering the completion of the project.”
  6. 31 October 2025

    Extended at the builder's request (MahaRERA application EXT99000024904)

    Reason the builder gave MahaRERA: “We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has also led to hindering the completion of the project.”
  7. 31 December 2026

    Extended at the builder's request (MahaRERA application EA08042620578)

    Reason the builder gave MahaRERA:
    “We hereby notify that the project is duly completed except the external amenities which are already in process. Also, we are awaiting for the occupation certificate to be issued from the competent authority. Hence we request you to kindly p…” Read the full reason“We hereby notify that the project is duly completed except the external amenities which are already in process. Also, we are awaiting for the occupation certificate to be issued from the competent authority. Hence we request you to kindly provide extension for the project as we expecting the certificate at the earliest.”
  8. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Swastik Epitome Building 2 Phase I Ground to 7 floors’s extension records on MahaRERA (P99000006718), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Swastik Epitome Building 2 Phase I Ground to 7 floors

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 1 court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000006718
Status
Registered and active
Builder
Hemant Ramesh Mhatre
Location
Behind D Mart, Palghar · 401305
Project type
Residential / Group Housing
Registered on
16 Aug 2017
Completion date at registration
December 2019
Latest completion date
April 2027
Delay so far
84 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
182
Sold or booked
90%
Towers
5
Complaints on MahaRERA
2
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Swastik Epitome Building 2 Phase I Ground to 7 floors, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C WING100%100%95%90%
D WING100%100%95%90%
E WING100%100%95%90%
F WING100%100%95%90%
G WING100%100%95%90%

Commencement certificate (CC), as filed on MahaRERA

  • C WING: covers 21 floors
  • D WING: covers 21 floors
  • E WING: covers 21 floors
  • F WING: covers 21 floors
  • G WING: covers 21 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Swastik Epitome Building 2 Phase I Ground to 7 floors every month.

Swastik Epitome Building 2 Phase I Ground to 7 floors: buildings, flats and land, as filed on MahaRERA

  • Buildings: C WING (10 floors, 28 units) · D WING (10 floors, 42 units) · E WING (10 floors, 28 units) · F WING (10 floors, 42 units) · G WING (10 floors, 42 units)
  • Car parking: 50 covered, 7 open
  • Land: 3,421 sq m (about 0.8 acres) · sanctioned built-up 7,957 sq m · recreational space 2,827 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Hemant Ramesh Mhatre has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 69 months late). 3 complaints on MahaRERA across 2 projects.

Read Google reviews of Swastik Epitome Building 2 Phase I Ground to 7 floors →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Swastik Epitome Building 2 Phase I Ground to 7 floors: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Swastik Epitome Building 2 Phase I Ground to 7 floors

What is the possession date of Swastik Epitome Building 2 Phase I Ground to 7 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Swastik Epitome Building 2 Phase I Ground to 7 floors in Behind D Mart, Palghar is 30 April 2027 — 84 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Swastik Epitome Building 2 Phase I Ground to 7 floors?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Swastik Epitome Building 2 Phase I Ground to 7 floors's builder has filed on MahaRERA, the official one, is 30 April 2027, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Swastik Epitome Building 2 Phase I Ground to 7 floors extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase I Ground to 7 floors's builder applied to MahaRERA to extend the completion date 6 times: to 30 December 2020, giving the reason "Delay in receiving CC/RDP for above floors (phase - 2). Work could not be completed due to the delay of higher floors"; to 31 March 2022, giving the reason "Due to delay in receiving permission and approvals to the said project from the respective competent authority."; to 30 September 2022, giving the reason "The project is delayed due to worldwide Pandemic situation and unforeseen circumstances i.e. non-availability of labour, materials and lack of customer demand occurred"; to 31 August 2024, giving the reason "We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has also led to financial crisis hindering the completion of the project."; to 31 October 2025, giving the reason "We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has also led to hindering the completion of the project."; to 31 December 2026, giving the reason "We hereby notify that the project is duly completed except the external amenities which are already in process. Also, we are awaiting for the occupation certificate to be issued from the competent authority. Hence we request you to kindly provide extension for the project as we expecting the certificate at the earliest.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Swastik Epitome Building 2 Phase I Ground to 7 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Swastik Epitome Building 2 Phase I Ground to 7 floors in Behind D Mart, Palghar is P99000006718.

Is Swastik Epitome Building 2 Phase I Ground to 7 floors registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase I Ground to 7 floors is registered as P99000006718 and its status is "Registered and active".

What is the construction status of Swastik Epitome Building 2 Phase I Ground to 7 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase I Ground to 7 floors's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does Swastik Epitome Building 2 Phase I Ground to 7 floors have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Swastik Epitome Building 2 Phase I Ground to 7 floors safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase I Ground to 7 floors is registered on MahaRERA as P99000006718, its completion date has moved 84 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Swastik Epitome Building 2 Phase I Ground to 7 floors's possession date changes?

The latest dates are on Swastik Epitome Building 2 Phase I Ground to 7 floors's MahaRERA page (P99000006718). GharKundli's Kundli Watch sends a free WhatsApp update on Swastik Epitome Building 2 Phase I Ground to 7 floors every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Swastik Epitome Building 2 Phase I Ground to 7 floors have?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase I Ground to 7 floors has 5 buildings filed: C WING with 10 floors and 28 units; D WING with 10 floors and 42 units; E WING with 10 floors and 28 units; F WING with 10 floors and 42 units; G WING with 10 floors and 42 units.

How much parking does Swastik Epitome Building 2 Phase I Ground to 7 floors have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 50 covered and 7 open car parking spaces for Swastik Epitome Building 2 Phase I Ground to 7 floors.

How big is the land of Swastik Epitome Building 2 Phase I Ground to 7 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase I Ground to 7 floors stands on 3,421 sq m of land (about 0.8 acres), with 7,957 sq m of sanctioned built-up area and 2,827 sq m of recreational open space.

What is the track record of Swastik Epitome Building 2 Phase I Ground to 7 floors's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Hemant Ramesh Mhatre has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 69 months late). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Swastik Epitome Building 2 Phase I Ground to 7 floors?

Google Maps has reviews of Swastik Epitome Building 2 Phase I Ground to 7 floors written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Swastik Epitome Building 2 Phase I Ground to 7 floors?

Swastik Epitome Building 2 Phase I Ground to 7 floors by Hemant Ramesh Mhatre is in Behind D Mart, Palghar (pincode 401305), near Virar West, Virar East, Maharashtra, and is registered on MahaRERA as P99000006718, per GharKundli's check of MahaRERA records.

How many homes are in Swastik Epitome Building 2 Phase I Ground to 7 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase I Ground to 7 floors has 182 homes in 5 towers registered on MahaRERA, and 90% of them are sold or booked.

When was Swastik Epitome Building 2 Phase I Ground to 7 floors registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase I Ground to 7 floors was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Swastik Epitome Building 2 Phase I Ground to 7 floors?

1 court case is listed for Swastik Epitome Building 2 Phase I Ground to 7 floors on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Swastik Epitome Building 2 Phase I Ground to 7 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Hemant Ramesh Mhatre, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in Vasai

All 88 projects in Virar East (401305) →

Other projects by Hemant Ramesh Mhatre

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.