Swastik Epitome Building 2 Phase II 8 to 14 floors

by Hemant Ramesh Mhatre · Behind D Mart, PalgharAlso near Virar

Possession date of Swastik Epitome Building 2 Phase II 8 to 14 floors: 30 April 2027, moved from 30 December 2020 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000012158, and currently active. Its completion date has moved from December 2020 to April 2027: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Swastik Epitome Building 2 Phase II 8 to 14 floors?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Swastik Epitome Building 2 Phase II 8 to 14 floors has moved

  1. 30 December 2020

    Completion date given when the project was registered

  2. 31 May 2021

    Extended at the builder's request (MahaRERA application EXT99000006356)

    Reason the builder gave MahaRERA: “Due to delay in receiving the permission and approvals for the said project from the respective competent authority.”
  3. 31 August 2022

    Extended at the builder's request (MahaRERA application EXT99000011075)

    Reason the builder gave MahaRERA: “Project has been delayed due to the pandemic which has led to lack of availability of resources, labour and finance.”
  4. 31 August 2023

    Extended at the builder's request (MahaRERA application EXT99000012583)

    Reason the builder gave MahaRERA: “The project is delayed due to worldwide Pandemic situation which led to financial crisis. Also, due to the unforeseen circumstances i.e. non- availability of labour, materials and lack of customer demand occurred during the Pandemic period.”
  5. 31 October 2024

    Extended at the builder's request (MahaRERA application EXT99000018656)

    Reason the builder gave MahaRERA:
    “We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has also led to financial crisis hindering the completion of the projec…” Read the full reason“We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has also led to financial crisis hindering the completion of the project.”
  6. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT99000025036)

    Reason the builder gave MahaRERA: “We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has led to the completion of the project.”
  7. 31 December 2026

    Extended at the builder's request (MahaRERA application EA20052621037)

    Reason the builder gave MahaRERA:
    “We hereby notify that the project is duly completed except the external amenities which are already in process. Also, we are awaiting for the occupation certificate to be issued from the competent authority. Hence we request you to kindly p…” Read the full reason“We hereby notify that the project is duly completed except the external amenities which are already in process. Also, we are awaiting for the occupation certificate to be issued from the competent authority. Hence we request you to kindly provide extension for the project as we expecting the certificate at the earliest.”
  8. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Swastik Epitome Building 2 Phase II 8 to 14 floors’s extension records on MahaRERA (P99000012158), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Swastik Epitome Building 2 Phase II 8 to 14 floors

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000012158
Status
Registered and active
Builder
Hemant Ramesh Mhatre
Location
Behind D Mart, Palghar · 401305
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
December 2020
Latest completion date
April 2027
Delay so far
72 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
172
Sold or booked
76%
Towers
5
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Swastik Epitome Building 2 Phase II 8 to 14 floors, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C WING0%100%90%90%
D WING0%100%90%90%
E WING0%100%90%90%
F WING0%100%90%90%
G WING0%100%90%90%

Commencement certificate (CC), as filed on MahaRERA

  • C WING: covers 21 floors
  • D WING: covers 21 floors
  • E WING: covers 21 floors
  • F WING: covers 21 floors
  • G WING: covers 21 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Swastik Epitome Building 2 Phase II 8 to 14 floors every month.

Swastik Epitome Building 2 Phase II 8 to 14 floors: buildings, flats and land, as filed on MahaRERA

  • Buildings: C WING (9 floors, 26 units) · D WING (9 floors, 40 units) · E WING (9 floors, 26 units) · F WING (9 floors, 40 units) · G WING (9 floors, 40 units)
  • Land: 3,421 sq m (about 0.8 acres) · recreational space 2,827 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Hemant Ramesh Mhatre has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 69 months late). 3 complaints on MahaRERA across 2 projects.

Read Google reviews of Swastik Epitome Building 2 Phase II 8 to 14 floors →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Swastik Epitome Building 2 Phase II 8 to 14 floors: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Swastik Epitome Building 2 Phase II 8 to 14 floors

What is the possession date of Swastik Epitome Building 2 Phase II 8 to 14 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Swastik Epitome Building 2 Phase II 8 to 14 floors in Behind D Mart, Palghar is 30 April 2027 — 72 months later than 30 December 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Swastik Epitome Building 2 Phase II 8 to 14 floors?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Swastik Epitome Building 2 Phase II 8 to 14 floors's builder has filed on MahaRERA, the official one, is 30 April 2027, already 72 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Swastik Epitome Building 2 Phase II 8 to 14 floors extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase II 8 to 14 floors's builder applied to MahaRERA to extend the completion date 6 times: to 31 May 2021, giving the reason "Due to delay in receiving the permission and approvals for the said project from the respective competent authority."; to 31 August 2022, giving the reason "Project has been delayed due to the pandemic which has led to lack of availability of resources, labour and finance."; to 31 August 2023, giving the reason "The project is delayed due to worldwide Pandemic situation which led to financial crisis. Also, due to the unforeseen circumstances i.e. non- availability of labour, materials and lack of customer demand occurred during the Pandemic period."; to 31 October 2024, giving the reason "We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has also led to financial crisis hindering the completion of the project."; to 31 December 2025, giving the reason "We hereby notify that there has been a delay in completion of the project due to non-availability of labour, materials and lack of customer demand during Covid 19 which has led to the completion of the project."; to 31 December 2026, giving the reason "We hereby notify that the project is duly completed except the external amenities which are already in process. Also, we are awaiting for the occupation certificate to be issued from the competent authority. Hence we request you to kindly provide extension for the project as we expecting the certificate at the earliest.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Swastik Epitome Building 2 Phase II 8 to 14 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Swastik Epitome Building 2 Phase II 8 to 14 floors in Behind D Mart, Palghar is P99000012158.

Is Swastik Epitome Building 2 Phase II 8 to 14 floors registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase II 8 to 14 floors is registered as P99000012158 and its status is "Registered and active".

What is the construction status of Swastik Epitome Building 2 Phase II 8 to 14 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase II 8 to 14 floors's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does Swastik Epitome Building 2 Phase II 8 to 14 floors have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Swastik Epitome Building 2 Phase II 8 to 14 floors safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase II 8 to 14 floors is registered on MahaRERA as P99000012158, its completion date has moved 72 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Swastik Epitome Building 2 Phase II 8 to 14 floors's possession date changes?

The latest dates are on Swastik Epitome Building 2 Phase II 8 to 14 floors's MahaRERA page (P99000012158). GharKundli's Kundli Watch sends a free WhatsApp update on Swastik Epitome Building 2 Phase II 8 to 14 floors every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Swastik Epitome Building 2 Phase II 8 to 14 floors have?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase II 8 to 14 floors has 5 buildings filed: C WING with 9 floors and 26 units; D WING with 9 floors and 40 units; E WING with 9 floors and 26 units; F WING with 9 floors and 40 units; G WING with 9 floors and 40 units.

How big is the land of Swastik Epitome Building 2 Phase II 8 to 14 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase II 8 to 14 floors stands on 3,421 sq m of land (about 0.8 acres) and 2,827 sq m of recreational open space.

What is the track record of Swastik Epitome Building 2 Phase II 8 to 14 floors's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Hemant Ramesh Mhatre has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 69 months late). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Swastik Epitome Building 2 Phase II 8 to 14 floors?

Google Maps has reviews of Swastik Epitome Building 2 Phase II 8 to 14 floors written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Swastik Epitome Building 2 Phase II 8 to 14 floors?

Swastik Epitome Building 2 Phase II 8 to 14 floors by Hemant Ramesh Mhatre is in Behind D Mart, Palghar (pincode 401305), near Virar, Maharashtra, and is registered on MahaRERA as P99000012158, per GharKundli's check of MahaRERA records.

How many homes are in Swastik Epitome Building 2 Phase II 8 to 14 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase II 8 to 14 floors has 172 homes in 5 towers registered on MahaRERA, and 76% of them are sold or booked.

When was Swastik Epitome Building 2 Phase II 8 to 14 floors registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Epitome Building 2 Phase II 8 to 14 floors was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Swastik Epitome Building 2 Phase II 8 to 14 floors?

1 court case is listed for Swastik Epitome Building 2 Phase II 8 to 14 floors on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Swastik Epitome Building 2 Phase II 8 to 14 floors?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Hemant Ramesh Mhatre, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in Vasai

All 88 projects in Virar East (401305) →

Other projects by Hemant Ramesh Mhatre

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.