by FRIENDS CONSTRUCTION · Virar East, Palghar 401303Also near Virar West, Bolinj, HDIL Layout

What’s in the report? →

Possession date of Friends Park (MahaRERA P99000012133): 31 July 2024, moved from 1 January 2020 (54 months later), and it has already passed. It has 106 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000012133. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P99000012133, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2024) has passed.

What do you want to know about Friends Park?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Friends Park has moved

  1. 1 January 2020

    Completion date given when the project was registered

  2. 31 January 2024

    Extended at the builder's request (MahaRERA application EXT99000008540)

    Reason the builder gave MahaRERA: “BLDG NO 1 CONSISTS OF A,B,C WINGS. O.C. OF B,C AND BLDG. NO. 2 RECEIVED. HOWEVER, WORK OF A WING RECENTLY STARTED FOR WHICH EXTENSION SOUGHT”
  3. 31 July 2024

    Revised completion date on MahaRERA

Source: Friends Park’s extension records on MahaRERA (P99000012133), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Friends Park

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000012133
Status
Lapsed (registration period ended)
Builder
FRIENDS CONSTRUCTION
Location
Virar East, Palghar · 401303
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
January 2020
Latest completion date
July 2024
Delay so far
54 months
Homes
106
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Friends Park, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NILKANTH100%100%100%100%
KESHAV100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Friends Park every 1–2 months.

Friends Park: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Friends Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Friends Park: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Friends Park

What is the possession date of Friends Park?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Friends Park in Virar East, Palghar is 31 July 2024 — 54 months later than 1 January 2020, the date given at registration. That date has already passed.

The date has already moved 54 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Friends Park?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Friends Park's builder has filed on MahaRERA, the official one, is 31 July 2024, already 54 months later than the 1 January 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Friends Park extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park's builder applied to MahaRERA to extend the completion date once: to 31 January 2024, giving the reason "BLDG NO 1 CONSISTS OF A,B,C WINGS. O.C. OF B,C AND BLDG. NO. 2 RECEIVED. HOWEVER, WORK OF A WING RECENTLY STARTED FOR WHICH EXTENSION SOUGHT".

What is the RERA number of Friends Park?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Friends Park in Virar East, Palghar is P99000012133.

Is Friends Park registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park is registered as P99000012133 and its status is "Lapsed (registration period ended)".

What is the current construction status of Friends Park? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Friends Park have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Friends Park safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park is registered on MahaRERA as P99000012133, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Friends Park?

Friends Park isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Friends Park?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Friends Park: gharkundli.com/tools/property-cost-calculator

Has Friends Park received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Friends Park?

According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Friends Park uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Friends Park was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Friends Park's possession date changes?

The latest dates are on Friends Park's MahaRERA page (P99000012133). GharKundli's Kundli Watch sends a free WhatsApp update on Friends Park every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Friends Park have?

According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park has 2 buildings filed: NILKANTH with 7 floors; KESHAV with 7 floors.

How big is the land of Friends Park?

According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park stands on 6,312 sq m of land (about 1.6 acres), with 3,896 sq m of sanctioned built-up area and 701 sq m of recreational open space.

What are the reviews of Friends Park?

Google Maps has reviews of Friends Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Friends Park?

Friends Park by FRIENDS CONSTRUCTION is in Virar East, Palghar, pincode 401303 (near Virar West, Bolinj, HDIL Layout), Maharashtra, and is registered on MahaRERA as P99000012133, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 115, H. NO. 36. GharKundli lists all 298 MahaRERA projects in Virar West (401303).

How many flats are in Friends Park?

According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park has 106 homes in 2 towers registered on MahaRERA.

When was Friends Park registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Friends Park was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Does Friends Park have any legal issues or court cases?

No court cases are listed for Friends Park on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Friends Park?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is FRIENDS CONSTRUCTION.