by Prathmesh Developers · Virar, Palghar 401303Also near Bolinj, HDIL Layout, Sitabuldi
What’s in the report? →Possession date of Prathmesh Dreams (MahaRERA P99000007940): 30 June 2024, moved from 31 December 2019 (54 months later), and it has already passed. It has 79 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000007940. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P99000007940, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2024) has passed.
What do you want to know about Prathmesh Dreams?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Prathmesh Dreams has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT99000003776)
Reason the builder gave MahaRERA:
“OUR PROJECT DELAY REASON IS THAT WE HAVE SUBMITTED ALL REQUIRED PAPERS IN VASAI VIRAR MUNICIPAL CORPORATION FOR OCCUPATION CERTIFICATE BUT SINCE WE HAVE STILL NOT RECEIVED THE OCCUPATION CERTIFICATE FROM CORPORATION WE ARE HENCEFORTH REQUES…” Read the full reason
“OUR PROJECT DELAY REASON IS THAT WE HAVE SUBMITTED ALL REQUIRED PAPERS IN VASAI VIRAR MUNICIPAL CORPORATION FOR OCCUPATION CERTIFICATE BUT SINCE WE HAVE STILL NOT RECEIVED THE OCCUPATION CERTIFICATE FROM CORPORATION WE ARE HENCEFORTH REQUESTING FOR THE EXTENSION.”31 December 2023
Extended at the builder's request (MahaRERA application EXT99000009895)
Reason the builder gave MahaRERA:
“WE HAVE ALREADY APPLIED FOR THE OCCUPANCY CERTIFICATE TO VASAI VIRAR CITY MUNICIPAL CORPORATION ON 22/07/2019 BUT STILL IT IS NOT RECEIVED AND AWAITED DUE TO THE COVID PANADEMIC SITUATION AND WE ALSO HAVE GOT FORM 4 AND APPLICATION COPY OF…” Read the full reason
“WE HAVE ALREADY APPLIED FOR THE OCCUPANCY CERTIFICATE TO VASAI VIRAR CITY MUNICIPAL CORPORATION ON 22/07/2019 BUT STILL IT IS NOT RECEIVED AND AWAITED DUE TO THE COVID PANADEMIC SITUATION AND WE ALSO HAVE GOT FORM 4 AND APPLICATION COPY OF OCCUPANCY CERTIFICATE WHICH WE HAVE ATTACHED SO WE WOULD LIKE TO REQUEST YOU TO GRANT FOR EXTENSION OF PROJECT TILL 31/12/2023”30 June 2024
Revised completion date on MahaRERA
Source: Prathmesh Dreams’s extension records on MahaRERA (P99000007940), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Prathmesh Dreams
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000007940
- Status
- Lapsed (registration period ended)
- Builder
- Prathmesh Developers
- Location
- Virar, Palghar · 401303
- Project type
- Others
- Registered on
- 18 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- June 2024
- Delay so far
- 54 months
- Homes
- 79
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Prathmesh Dreams, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Prathmesh Dreams | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prathmesh Dreams every 1–2 months.
Prathmesh Dreams: buildings, flats and land, as filed on MahaRERA
- Buildings: Prathmesh Dreams (14 floors)
- Land: 1,289 sq m (about 0.3 acres) · sanctioned built-up 3,043 sq m · recreational space 844 sq m
- Boundaries filed include: Garden
- Land, as filed: 66/169 Hissa No 1 , 69/172 Hissa No 5
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Prathmesh Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 lapsed. No complaints on MahaRERA.
Read Google reviews of Prathmesh Dreams →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Prathmesh Dreams: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Prathmesh Dreams
What is the possession date of Prathmesh Dreams?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Prathmesh Dreams in Virar, Palghar is 30 June 2024 — 54 months later than 31 December 2019, the date given at registration. That date has already passed.
The date has already moved 54 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Prathmesh Dreams?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Prathmesh Dreams's builder has filed on MahaRERA, the official one, is 30 June 2024, already 54 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Prathmesh Dreams extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "OUR PROJECT DELAY REASON IS THAT WE HAVE SUBMITTED ALL REQUIRED PAPERS IN VASAI VIRAR MUNICIPAL CORPORATION FOR OCCUPATION CERTIFICATE BUT SINCE WE HAVE STILL NOT RECEIVED THE OCCUPATION CERTIFICATE FROM CORPORATION WE ARE HENCEFORTH REQUESTING FOR THE EXTENSION."; to 31 December 2023, giving the reason "WE HAVE ALREADY APPLIED FOR THE OCCUPANCY CERTIFICATE TO VASAI VIRAR CITY MUNICIPAL CORPORATION ON 22/07/2019 BUT STILL IT IS NOT RECEIVED AND AWAITED DUE TO THE COVID PANADEMIC SITUATION AND WE ALSO HAVE GOT FORM 4 AND APPLICATION COPY OF OCCUPANCY CERTIFICATE WHICH WE HAVE ATTACHED SO WE WOULD LIKE TO REQUEST YOU TO GRANT FOR EXTENSION OF PROJECT TILL 31/12/2023".
What is the RERA number of Prathmesh Dreams?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Prathmesh Dreams in Virar, Palghar is P99000007940.
Is Prathmesh Dreams registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams is registered as P99000007940 and its status is "Lapsed (registration period ended)".
What is the current construction status of Prathmesh Dreams? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Prathmesh Dreams is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Prathmesh Dreams have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Prathmesh Dreams safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams is registered on MahaRERA as P99000007940, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Prathmesh Dreams?
Prathmesh Dreams isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Prathmesh Dreams?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Prathmesh Dreams: gharkundli.com/tools/property-cost-calculator
Has Prathmesh Dreams received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Prathmesh Dreams?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Prathmesh Dreams uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Prathmesh Dreams was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Prathmesh Dreams's possession date changes?
The latest dates are on Prathmesh Dreams's MahaRERA page (P99000007940). GharKundli's Kundli Watch sends a free WhatsApp update on Prathmesh Dreams every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Prathmesh Dreams have?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams has one building filed: Prathmesh Dreams with 14 floors.
How big is the land of Prathmesh Dreams?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams stands on 1,289 sq m of land (about 0.3 acres), with 3,043 sq m of sanctioned built-up area and 844 sq m of recreational open space.
What is the track record of Prathmesh Dreams's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Prathmesh Dreams?
Google Maps has reviews of Prathmesh Dreams written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Prathmesh Dreams?
Prathmesh Dreams by Prathmesh Developers is in Virar, Palghar, pincode 401303 (near Bolinj, HDIL Layout, Sitabuldi), Maharashtra, and is registered on MahaRERA as P99000007940, per GharKundli's check of MahaRERA records. Its boundaries filed there include Garden. Its land is filed as 66/169 Hissa No 1 , 69/172 Hissa No 5. GharKundli lists all 298 MahaRERA projects in Virar West (401303).
How many flats are in Prathmesh Dreams?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams has 79 homes in 1 tower registered on MahaRERA.
When was Prathmesh Dreams registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Prathmesh Dreams was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Does Prathmesh Dreams have any legal issues or court cases?
No court cases are listed for Prathmesh Dreams on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Prathmesh Dreams?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Prathmesh Developers, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Prathmesh Dreams
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Virar West (401303)
- Super Homez-harmony Phase III
- S M Tower
- Viva City - A5
- Viva City - A3
- Bhakti Greens
- VIMALNATH Building no-2
- Valencia CHS
- Belle Vue 9
Other projects by Prathmesh Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.