GAURAV HEIGHTS

by MAHAVIR DEVELOPERS · Nallasopara West, Palghar

Possession date of GAURAV HEIGHTS: 31 July 2027, moved from 1 June 2019 (93 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000009792, and currently active. Its completion date has moved from June 2019 to July 2027: 93 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about GAURAV HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GAURAV HEIGHTS has moved

  1. 1 June 2019

    Completion date given when the project was registered

  2. 31 May 2020

    Extended at the builder's request (MahaRERA application EXT99000005857)

    Reason the builder gave MahaRERA:
    “Project Gaurav Heights is completed Appx. 97% as per Architect` Certificate dated 01-03-2019 , copy of teh same is already uploaded on Maharera Site & Developer has applied to VVCMC - Town Planning Authority for regularization of additional…” Read the full reason“Project Gaurav Heights is completed Appx. 97% as per Architect` Certificate dated 01-03-2019 , copy of teh same is already uploaded on Maharera Site & Developer has applied to VVCMC - Town Planning Authority for regularization of additional construction by using TDR as per MRTP Act, 1966 on 16-05-2017 & have also applied again on 21-02-2019 copy of the same is enclosed herewith . The sadi Project is under Revise Sanction pending from VVCMC & Applicant has no control over thisa situation & applicant is waiting for the regularization of addtional built up area and proposed area of constructio…”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT99000008520)

    Reason the builder gave MahaRERA: “Consent Resolution is attached”
  4. 31 March 2027

    Extended at the builder's request (MahaRERA application EXT99000019395)

    Reason the builder gave MahaRERA: “WE HAVE NOT RECEIVED OC YET.”
  5. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GAURAV HEIGHTS’s extension records on MahaRERA (P99000009792), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GAURAV HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000009792
Status
Registered and active
Builder
MAHAVIR DEVELOPERS
Location
Nallasopara West, Palghar · 401203
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
June 2019
Latest completion date
July 2027
Delay so far
93 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
135
Towers
3
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of GAURAV HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING100%100%100%100%
B WING100%100%100%100%
A AND B WING PROPOSED0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAURAV HEIGHTS every month.

GAURAV HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING (12 floors) · B WING (12 floors) · A AND B WING PROPOSED (4 floors)
  • Land: 2,605 sq m (about 0.6 acres) · sanctioned built-up 2,602 sq m · recreational space 200 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GAURAV HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GAURAV HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GAURAV HEIGHTS

What is the possession date of GAURAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GAURAV HEIGHTS in Nallasopara West, Palghar is 31 July 2027 — 93 months later than 1 June 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GAURAV HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GAURAV HEIGHTS's builder has filed on MahaRERA, the official one, is 31 July 2027, already 93 months later than the 1 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GAURAV HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 31 May 2020, giving the reason "Project Gaurav Heights is completed Appx. 97% as per Architect` Certificate dated 01-03-2019 , copy of teh same is already uploaded on Maharera Site & Developer has applied to VVCMC - Town Planning Authority for regularization of additional construction by using TDR as per MRTP Act, 1966 on 16-05-2017 & have also applied again on 21-02-2019 copy of the same is enclosed herewith . The sadi Project is under Revise Sanction pending from VVCMC & Applicant has no control over thisa situation & applicant is waiting for the regularization of addtional built up area and proposed area of constructio…"; to 31 December 2023, giving the reason "Consent Resolution is attached"; to 31 March 2027, giving the reason "WE HAVE NOT RECEIVED OC YET.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of GAURAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GAURAV HEIGHTS in Nallasopara West, Palghar is P99000009792.

Is GAURAV HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV HEIGHTS is registered as P99000009792 and its status is "Registered and active".

What is the construction status of GAURAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does GAURAV HEIGHTS have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is GAURAV HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV HEIGHTS is registered on MahaRERA as P99000009792, its completion date has moved 93 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GAURAV HEIGHTS's possession date changes?

The latest dates are on GAURAV HEIGHTS's MahaRERA page (P99000009792). GharKundli's Kundli Watch sends a free WhatsApp update on GAURAV HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GAURAV HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV HEIGHTS has 3 buildings filed: A WING with 12 floors; B WING with 12 floors; A AND B WING PROPOSED with 4 floors.

How big is the land of GAURAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV HEIGHTS stands on 2,605 sq m of land (about 0.6 acres), with 2,602 sq m of sanctioned built-up area and 200 sq m of recreational open space.

Where can I read reviews of GAURAV HEIGHTS?

Google Maps has reviews of GAURAV HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GAURAV HEIGHTS?

GAURAV HEIGHTS by MAHAVIR DEVELOPERS is in Nallasopara West, Palghar (pincode 401203), Maharashtra, and is registered on MahaRERA as P99000009792, per GharKundli's check of MahaRERA records.

How many homes are in GAURAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV HEIGHTS has 135 homes in 3 towers registered on MahaRERA.

When was GAURAV HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURAV HEIGHTS was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on GAURAV HEIGHTS?

1 court case is listed for GAURAV HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of GAURAV HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAHAVIR DEVELOPERS, which has 8 other projects registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in pincode 401203

All 167 projects in Nallasopara West (401203) →

Other projects by MAHAVIR DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.