by FUTURE BUILD R CON · Nallasopara East, Palghar 401209Also near Nallasopara West, Achole, Borivali East

What’s in the report? →

Possession date of Valmiki Heights (MahaRERA P99000012263): 10 August 2022, moved from 14 February 2021 (18 months later), and it has already passed. It has 40 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000012263. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P99000012263, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (August 2022) has passed.

What do you want to know about Valmiki Heights?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Valmiki Heights has moved

  1. 14 February 2021

    Completion date given when the project was registered

  2. 10 February 2022

    Extended at the builder's request (MahaRERA application EXT99000009242)

    Reason the builder gave MahaRERA: “Because of covid our project is not completed that's why extend our project period”
  3. 10 August 2022

    Revised completion date on MahaRERA

Source: Valmiki Heights’s extension records on MahaRERA (P99000012263), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Valmiki Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000012263
Status
Lapsed (registration period ended)
Builder
FUTURE BUILD R CON
Location
Nallasopara East, Palghar · 401209
Project type
Others
Registered on
1 Sep 2017
Completion date at registration
February 2021
Latest completion date
August 2022
Delay so far
18 months
Homes
40
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Valmiki Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VALMIKI HEIGHTS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Valmiki Heights every 1–2 months.

Valmiki Heights: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Future Build Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Valmiki Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Valmiki Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Valmiki Heights

What is the possession date of Valmiki Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Valmiki Heights in Nallasopara East, Palghar is 10 August 2022 — 18 months later than 14 February 2021, the date given at registration. That date has already passed.

The date has already moved 18 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Valmiki Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Valmiki Heights's builder has filed on MahaRERA, the official one, is 10 August 2022, already 18 months later than the 14 February 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Valmiki Heights extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights's builder applied to MahaRERA to extend the completion date once: to 10 February 2022, giving the reason "Because of covid our project is not completed that's why extend our project period".

What is the RERA number of Valmiki Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Valmiki Heights in Nallasopara East, Palghar is P99000012263.

Is Valmiki Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights is registered as P99000012263 and its status is "Lapsed (registration period ended)".

What is the current construction status of Valmiki Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on VALMIKI HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Valmiki Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Valmiki Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights is registered on MahaRERA as P99000012263, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Valmiki Heights?

Valmiki Heights isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Valmiki Heights?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Valmiki Heights: gharkundli.com/tools/property-cost-calculator

Has Valmiki Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 10 August 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Valmiki Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (10 August 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Valmiki Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Valmiki Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Valmiki Heights's possession date changes?

The latest dates are on Valmiki Heights's MahaRERA page (P99000012263). GharKundli's Kundli Watch sends a free WhatsApp update on Valmiki Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Valmiki Heights have?

According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights has one building filed: VALMIKI HEIGHTS with 9 floors.

How big is the land of Valmiki Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights stands on 898 sq m of land (about 0.2 acres), with 1,770 sq m of sanctioned built-up area and 24,793 sq m of recreational open space.

What is the track record of Valmiki Heights's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Future Build Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Valmiki Heights?

Google Maps has reviews of Valmiki Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Valmiki Heights?

Valmiki Heights by FUTURE BUILD R CON is in Nallasopara East, Palghar, pincode 401209 (near Nallasopara West, Achole, Borivali East), Maharashtra, and is registered on MahaRERA as P99000012263, per GharKundli's check of MahaRERA records. Its land is filed as 50,51. GharKundli lists all 152 MahaRERA projects in Nallasopara East (401209).

How many flats are in Valmiki Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights has 40 homes in 1 tower registered on MahaRERA.

When was Valmiki Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Valmiki Heights was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Does Valmiki Heights have any legal issues or court cases?

No court cases are listed for Valmiki Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Valmiki Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is FUTURE BUILD R CON.

Other projects in Nallasopara East (401209)

All 152 projects in Nallasopara East (401209) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.