FRENY AVENUE
by SUMITRA REALTORS · Vasai Nallasopara Link Road, PalgharAlso near Nallosapare E
Possession date of FRENY AVENUE: 30 August 2028, moved from 28 August 2026 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000022110, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about FRENY AVENUE?
How the possession date of FRENY AVENUE has moved
28 August 2026
Completion date given when the project was registered
30 August 2028
Extended at the builder's request (MahaRERA application EA20082622270)
Reason the builder gave MahaRERA: “DUE TO SOME UNAVOIDABLE REASONS THE PROJECT CANNOT BE COMPLETED BEFORE TIME.”
Source: FRENY AVENUE’s extension records on MahaRERA (P99000022110), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on FRENY AVENUE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the August 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000022110
- Status
- Registered and active
- Builder
- SUMITRA REALTORS
- Location
- Vasai Nallasopara Link Road, Palghar · 401209
- Project type
- Others
- Registered on
- 27 Aug 2019
- Completion date at registration
- August 2026
- Latest completion date
- August 2028
- Delay so far
- 24 months
- Homes
- 114
- Sold or booked
- 10%
- Towers
- 3
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of FRENY AVENUE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| FRENY AVENUE WING A | 100% | 80% | 10% | 0% |
| FRENY AVENUE WING B | 100% | 38% | 8% | 0% |
| BUILDING NO 1 WING-A TYPE-B2 | 100% | 38% | 8% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- FRENY AVENUE WING A: covers 17 floors
- FRENY AVENUE WING B: covers 0 floors
- BUILDING NO 1 WING-A TYPE-B2: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on FRENY AVENUE every month.
FRENY AVENUE: buildings, flats and land, as filed on MahaRERA
- Buildings: FRENY AVENUE WING A (17 floors, 126 units) · FRENY AVENUE WING B (7 floors) · BUILDING NO 1 WING-A TYPE-B2 (5 floors)
- Land: 1,470 sq m (about 0.4 acres) · sanctioned built-up 1,279 sq m · recreational space 147 sq m
- Boundaries filed include: SHIV KRUPA COMPLEX, ACHOLE LINK ROAD, MARTIN COMPLEX
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of FRENY AVENUE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
FRENY AVENUE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about FRENY AVENUE
What is the possession date of FRENY AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for FRENY AVENUE in Vasai Nallasopara Link Road, Palghar is 30 August 2028 — 24 months later than 28 August 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for FRENY AVENUE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date FRENY AVENUE's builder has filed on MahaRERA, the official one, is 30 August 2028, already 24 months later than the 28 August 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of FRENY AVENUE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), FRENY AVENUE's builder applied to MahaRERA to extend the completion date once: to 30 August 2028, giving the reason "DUE TO SOME UNAVOIDABLE REASONS THE PROJECT CANNOT BE COMPLETED BEFORE TIME.".
What is the RERA number of FRENY AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of FRENY AVENUE in Vasai Nallasopara Link Road, Palghar is P99000022110.
Is FRENY AVENUE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), FRENY AVENUE is registered as P99000022110 and its status is "Registered and active".
What is the construction status of FRENY AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), FRENY AVENUE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 38% to 80% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does FRENY AVENUE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is FRENY AVENUE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), FRENY AVENUE is registered on MahaRERA as P99000022110, its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if FRENY AVENUE's possession date changes?
The latest dates are on FRENY AVENUE's MahaRERA page (P99000022110). GharKundli's Kundli Watch sends a free WhatsApp update on FRENY AVENUE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does FRENY AVENUE have?
According to GharKundli's check of MahaRERA records (updated October 2026), FRENY AVENUE has 3 buildings filed: FRENY AVENUE WING A with 17 floors and 126 units; FRENY AVENUE WING B with 7 floors; BUILDING NO 1 WING-A TYPE-B2 with 5 floors.
How big is the land of FRENY AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), FRENY AVENUE stands on 1,470 sq m of land (about 0.4 acres), with 1,279 sq m of sanctioned built-up area and 147 sq m of recreational open space.
Where can I read reviews of FRENY AVENUE?
Google Maps has reviews of FRENY AVENUE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is FRENY AVENUE?
FRENY AVENUE by SUMITRA REALTORS is in Vasai Nallasopara Link Road, Palghar (pincode 401209), near Nallosapare E, Maharashtra, and is registered on MahaRERA as P99000022110, per GharKundli's check of MahaRERA records. Its boundaries filed there include SHIV KRUPA COMPLEX, ACHOLE LINK ROAD, MARTIN COMPLEX.
How many homes are in FRENY AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), FRENY AVENUE has 114 homes in 3 towers registered on MahaRERA, and 10% of them are sold or booked.
When was FRENY AVENUE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), FRENY AVENUE was registered on MahaRERA on 27 August 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on FRENY AVENUE?
No court cases are listed for FRENY AVENUE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of FRENY AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUMITRA REALTORS.
Check it yourself on MahaRERA
- How to check the possession date of FRENY AVENUE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Palghar →
Other projects in Vasai
- VIMALNATH Building no-2
- STAR LEGACY
- Acciano Bianca
- COMFORT AARADHYA
- DHANANJAY ICON
- GULMOHAR HERITAGE BUILDING NO 3 WING E PHASE I
- SHIVNERI
- Carpentry Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.