by SUMATINATH BUILDERS · Nallasopara West, PalgharAlso near Nilemore

Possession date of SHALIBHADRA YASH: 30 November 2029, moved from 31 July 2026 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000008956, and currently active. Its completion date has moved from July 2026 to November 2029: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SHALIBHADRA YASH?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHALIBHADRA YASH has moved

  1. 31 July 2026

    Completion date given when the project was registered

  2. 31 July 2029

    Extended at the builder's request (MahaRERA application EA28072621908)

    Reason the builder gave MahaRERA:
    “We have already constructed 5 Wings (B to F) as per last Approved Plan & Commencement Certificate. Further we have received revised commencement certificate for our last Wing A, as new phase into the same building. So, we request you please…” Read the full reason“We have already constructed 5 Wings (B to F) as per last Approved Plan & Commencement Certificate. Further we have received revised commencement certificate for our last Wing A, as new phase into the same building. So, we request you please extend time for project completion. We also Enclosed Consent of Flat Purchasers. And also Enclosed complete Time Line on Letter Head.”
  3. 30 November 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHALIBHADRA YASH’s extension records on MahaRERA (P99000008956), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHALIBHADRA YASH

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000008956
Status
Registered and active
Builder
SUMATINATH BUILDERS
Location
Nallasopara West, Palghar · 401203
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
July 2026
Latest completion date
November 2029
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
153
Sold or booked
86%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of SHALIBHADRA YASH, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHALIBHADRA YASH- WING A-B-C-D-E-F100%90%89%85%

Commencement certificate (CC), as filed on MahaRERA

  • SHALIBHADRA YASH- WING A-B-C-D-E-F: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHALIBHADRA YASH every month.

SHALIBHADRA YASH: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHALIBHADRA YASH- WING A-B-C-D-E-F (46 floors, 153 units)
  • Land: 5,500 sq m (about 1.4 acres) · sanctioned built-up 5,471 sq m · recreational space 820 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Sumatinath Builders has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, none past the promised date yet. 3 complaints on MahaRERA across 1 project.

Read Google reviews of SHALIBHADRA YASH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHALIBHADRA YASH: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHALIBHADRA YASH

What is the possession date of SHALIBHADRA YASH?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHALIBHADRA YASH in Nallasopara West, Palghar is 30 November 2029 — 36 months later than 31 July 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHALIBHADRA YASH?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHALIBHADRA YASH's builder has filed on MahaRERA, the official one, is 30 November 2029, already 36 months later than the 31 July 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHALIBHADRA YASH extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALIBHADRA YASH's builder applied to MahaRERA to extend the completion date once: to 31 July 2029, giving the reason "We have already constructed 5 Wings (B to F) as per last Approved Plan & Commencement Certificate. Further we have received revised commencement certificate for our last Wing A, as new phase into the same building. So, we request you please extend time for project completion. We also Enclosed Consent of Flat Purchasers. And also Enclosed complete Time Line on Letter Head.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHALIBHADRA YASH?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHALIBHADRA YASH in Nallasopara West, Palghar is P99000008956.

Is SHALIBHADRA YASH registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALIBHADRA YASH is registered as P99000008956 and its status is "Registered and active".

What is the construction status of SHALIBHADRA YASH?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALIBHADRA YASH's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHALIBHADRA YASH- WING A-B-C-D-E-F is 90% done and internal work 89%. GharKundli's full report compares construction progress with the deadline.

Does SHALIBHADRA YASH have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHALIBHADRA YASH safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALIBHADRA YASH is registered on MahaRERA as P99000008956, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHALIBHADRA YASH's possession date changes?

The latest dates are on SHALIBHADRA YASH's MahaRERA page (P99000008956). GharKundli's Kundli Watch sends a free WhatsApp update on SHALIBHADRA YASH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHALIBHADRA YASH have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALIBHADRA YASH has one building filed: SHALIBHADRA YASH- WING A-B-C-D-E-F with 46 floors and 153 units.

How big is the land of SHALIBHADRA YASH?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALIBHADRA YASH stands on 5,500 sq m of land (about 1.4 acres), with 5,471 sq m of sanctioned built-up area and 820 sq m of recreational open space.

What is the track record of SHALIBHADRA YASH's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sumatinath Builders has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, none past the promised date yet. 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHALIBHADRA YASH?

Google Maps has reviews of SHALIBHADRA YASH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHALIBHADRA YASH?

SHALIBHADRA YASH by SUMATINATH BUILDERS is in Nallasopara West, Palghar (pincode 401203), near Nilemore, Maharashtra, and is registered on MahaRERA as P99000008956, per GharKundli's check of MahaRERA records.

How many homes are in SHALIBHADRA YASH?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALIBHADRA YASH has 153 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.

When was SHALIBHADRA YASH registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHALIBHADRA YASH was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHALIBHADRA YASH?

No court cases are listed for SHALIBHADRA YASH on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHALIBHADRA YASH?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SUMATINATH BUILDERS, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2029 in Palghar →

Other projects in pincode 401203

All 162 projects in Nallasopara West (401203) →

Other projects by SUMATINATH BUILDERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.