BHAVANI VIEW

by Bhavani Construction · Virar West, Palghar

Possession date of BHAVANI VIEW: 30 October 2026, moved from 31 December 2019 (78 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P99000007598. Status: Lapsed (registration period ended). Its completion date has moved from December 2019 to October 2026: 78 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about BHAVANI VIEW?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BHAVANI VIEW has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT99000003988)

    Reason the builder gave MahaRERA:
    “As per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.12.2019 as the project completion date. We have completed the construction work and we had applied for Occupancy Certificat…” Read the full reason“As per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.12.2019 as the project completion date. We have completed the construction work and we had applied for Occupancy Certificate to the Vasai-Virar Municipal Corporation on 13.08.2019 and awaiting since then. Hence we need an extension up to one year to obtain the same.”
  3. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT99000010037)

    Reason the builder gave MahaRERA:
    “WE HAVE SUBMITTED OUR FILE FOR OCCUPANCY CERTIFICATE TO VASAI VIRAR MUNICIPAL CORPORATION ON 13/08/2019 BUT STILL THE OCCUPANCY CERTIFICATE HAS NOT BEEN RECEIVED AND WE ARE AWAITING FOR THE SAME AND DUE TO COVID PANADEMIC SITUATION IT IS GE…” Read the full reason“WE HAVE SUBMITTED OUR FILE FOR OCCUPANCY CERTIFICATE TO VASAI VIRAR MUNICIPAL CORPORATION ON 13/08/2019 BUT STILL THE OCCUPANCY CERTIFICATE HAS NOT BEEN RECEIVED AND WE ARE AWAITING FOR THE SAME AND DUE TO COVID PANADEMIC SITUATION IT IS GETTING DELAYED SO PLEASE KINDLY WE REQUEST YOU TO GRANT THE EXTENTION UNTIL 30/06/2023”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT99000013832)

    Reason the builder gave MahaRERA: “The registered project is complete and awaiting Occupancy Certificate from the Planning Authority. We are attaching copies of Application for Extention alongwith reason of delay and requisite documents.”
  5. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: BHAVANI VIEW’s extension records on MahaRERA (P99000007598), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BHAVANI VIEW

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000007598
Status
Lapsed (registration period ended)
Builder
Bhavani Construction
Location
Virar West, Palghar · 401303
Project type
Others
Registered on
17 Aug 2017
Completion date at registration
December 2019
Latest completion date
October 2026
Delay so far
78 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of BHAVANI VIEW, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BHAVANI VIEW100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BHAVANI VIEW every month.

BHAVANI VIEW: buildings, flats and land, as filed on MahaRERA

  • Buildings: BHAVANI VIEW (17 floors)
  • Land: 1,401 sq m (about 0.3 acres) · sanctioned built-up 4,759 sq m · recreational space 1,174 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of BHAVANI VIEW →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BHAVANI VIEW: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BHAVANI VIEW

What is the possession date of BHAVANI VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BHAVANI VIEW in Virar West, Palghar is 30 October 2026 — 78 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for BHAVANI VIEW?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BHAVANI VIEW's builder has filed on MahaRERA, the official one, is 30 October 2026, already 78 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of BHAVANI VIEW extended?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANI VIEW's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "As per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.12.2019 as the project completion date. We have completed the construction work and we had applied for Occupancy Certificate to the Vasai-Virar Municipal Corporation on 13.08.2019 and awaiting since then. Hence we need an extension up to one year to obtain the same."; to 30 June 2022, giving the reason "WE HAVE SUBMITTED OUR FILE FOR OCCUPANCY CERTIFICATE TO VASAI VIRAR MUNICIPAL CORPORATION ON 13/08/2019 BUT STILL THE OCCUPANCY CERTIFICATE HAS NOT BEEN RECEIVED AND WE ARE AWAITING FOR THE SAME AND DUE TO COVID PANADEMIC SITUATION IT IS GETTING DELAYED SO PLEASE KINDLY WE REQUEST YOU TO GRANT THE EXTENTION UNTIL 30/06/2023"; to 30 June 2026, giving the reason "The registered project is complete and awaiting Occupancy Certificate from the Planning Authority. We are attaching copies of Application for Extention alongwith reason of delay and requisite documents.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of BHAVANI VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BHAVANI VIEW in Virar West, Palghar is P99000007598.

Is BHAVANI VIEW registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANI VIEW is registered as P99000007598 and its status is "Lapsed (registration period ended)".

What is the construction status of BHAVANI VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANI VIEW's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on BHAVANI VIEW is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does BHAVANI VIEW have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is BHAVANI VIEW safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANI VIEW is registered on MahaRERA as P99000007598, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 78 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BHAVANI VIEW's possession date changes?

The latest dates are on BHAVANI VIEW's MahaRERA page (P99000007598). GharKundli's Kundli Watch sends a free WhatsApp update on BHAVANI VIEW every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BHAVANI VIEW have?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANI VIEW has one building filed: BHAVANI VIEW with 17 floors.

How big is the land of BHAVANI VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANI VIEW stands on 1,401 sq m of land (about 0.3 acres), with 4,759 sq m of sanctioned built-up area and 1,174 sq m of recreational open space.

Where can I read reviews of BHAVANI VIEW?

Google Maps has reviews of BHAVANI VIEW written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BHAVANI VIEW?

BHAVANI VIEW by Bhavani Construction is in Virar West, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000007598, per GharKundli's check of MahaRERA records.

When was BHAVANI VIEW registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANI VIEW was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on BHAVANI VIEW?

No court cases are listed for BHAVANI VIEW on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of BHAVANI VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Bhavani Construction, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Palghar →

Other projects in pincode 401303

All 187 projects in Virar West (401303) →

Other projects by Bhavani Construction

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.