Possession date of AAKASH COMPLEX: 30 March 2027, moved from 1 July 2023 (40 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000006053, and currently active. Its completion date has moved from July 2023 to March 2027: 40 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AAKASH COMPLEX?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AAKASH COMPLEX has moved

  1. 1 July 2023

    Completion date given when the project was registered

  2. 30 November 2026

    Extended at the builder's request (MahaRERA application EXT99000025358)

    Reason the builder gave MahaRERA:
    “The government has increased the FSI, and we are required to utilize and construct according to the new regulations. However, due to the unfavorable market conditions caused by COVID-19, it was not feasible to complete the project within th…” Read the full reason“The government has increased the FSI, and we are required to utilize and construct according to the new regulations. However, due to the unfavorable market conditions caused by COVID-19, it was not feasible to complete the project within the originally scheduled timeline.”
  3. 30 March 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: AAKASH COMPLEX’s extension records on MahaRERA (P99000006053), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AAKASH COMPLEX

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000006053
Status
Registered and active
Builder
LXMI INFRA
Location
Kurgaon, Palghar · 401502
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
July 2023
Latest completion date
March 2027
Delay so far
40 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
96
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of AAKASH COMPLEX, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AAKASH COMPLEX100%87%83%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AAKASH COMPLEX every month.

AAKASH COMPLEX: buildings, flats and land, as filed on MahaRERA

  • Buildings: AAKASH COMPLEX (5 floors)
  • Land: 5,896 sq m (about 1.5 acres) · sanctioned built-up 5,895 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AAKASH COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AAKASH COMPLEX: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AAKASH COMPLEX

What is the possession date of AAKASH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AAKASH COMPLEX in Kurgaon, Palghar is 30 March 2027 — 40 months later than 1 July 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for AAKASH COMPLEX?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AAKASH COMPLEX's builder has filed on MahaRERA, the official one, is 30 March 2027, already 40 months later than the 1 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AAKASH COMPLEX extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AAKASH COMPLEX's builder applied to MahaRERA to extend the completion date once: to 30 November 2026, giving the reason "The government has increased the FSI, and we are required to utilize and construct according to the new regulations. However, due to the unfavorable market conditions caused by COVID-19, it was not feasible to complete the project within the originally scheduled timeline.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of AAKASH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AAKASH COMPLEX in Kurgaon, Palghar is P99000006053.

Is AAKASH COMPLEX registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AAKASH COMPLEX is registered as P99000006053 and its status is "Registered and active".

What is the construction status of AAKASH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), AAKASH COMPLEX's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AAKASH COMPLEX is 87% done and internal work 83%. GharKundli's full report compares construction progress with the deadline.

Does AAKASH COMPLEX have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AAKASH COMPLEX safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AAKASH COMPLEX is registered on MahaRERA as P99000006053, its completion date has moved 40 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AAKASH COMPLEX's possession date changes?

The latest dates are on AAKASH COMPLEX's MahaRERA page (P99000006053). GharKundli's Kundli Watch sends a free WhatsApp update on AAKASH COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AAKASH COMPLEX have?

According to GharKundli's check of MahaRERA records (updated October 2026), AAKASH COMPLEX has one building filed: AAKASH COMPLEX with 5 floors.

How big is the land of AAKASH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), AAKASH COMPLEX stands on 5,896 sq m of land (about 1.5 acres), with 5,895 sq m of sanctioned built-up area.

Where can I read reviews of AAKASH COMPLEX?

Google Maps has reviews of AAKASH COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AAKASH COMPLEX?

AAKASH COMPLEX by LXMI INFRA is in Kurgaon, Palghar (pincode 401502), Maharashtra, and is registered on MahaRERA as P99000006053, per GharKundli's check of MahaRERA records.

How many homes are in AAKASH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), AAKASH COMPLEX has 96 homes in 1 tower registered on MahaRERA.

When was AAKASH COMPLEX registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AAKASH COMPLEX was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AAKASH COMPLEX?

No court cases are listed for AAKASH COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AAKASH COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LXMI INFRA.

All projects with possession due in 2027 in Palghar →

Other projects in Palghar

All 9 projects in Kurgaon (401502) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.