CRYSTAL HOMES
by CRYSTAL CREATIONS · Yamunanagar, Pune
Possession: CRYSTAL HOMES is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100002053. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about CRYSTAL HOMES?
How the possession date of CRYSTAL HOMES has moved
31 December 2019
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT52100005530)
Reason the builder gave MahaRERA: “waiting for PCMC completion certificate”
31 December 2023
Extended at the builder's request (MahaRERA application EXT52100017183)
Reason the builder gave MahaRERA: “Due to the COVID-19 pandemic, the regular flow of work is hampered on account of the unavailability of labour on a regular basis”
Source: CRYSTAL HOMES’s extension records on MahaRERA (P52100002053), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CRYSTAL HOMES
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Crystal Homes Phase - IP52100053027 · possession 30 Apr 2027
- MahaRERA registration
- P52100002053
- Status
- Completed
- Builder
- CRYSTAL CREATIONS
- Location
- Yamunanagar, Pune · 412101
- Project type
- Residential / Group Housing
- Registered on
- 31 Jul 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2023
- Delay so far
- 48 months
- Homes
- 50
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of CRYSTAL HOMES, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C | 100% | 100% | 100% | 100% |
| D | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CRYSTAL HOMES every month.
CRYSTAL HOMES: buildings, flats and land, as filed on MahaRERA
- Buildings: C (9 floors) · D (9 floors)
- Land: 3,100 sq m (about 0.8 acres) · sanctioned built-up 2,368 sq m · recreational space 285 sq m
The builder’s record and reviews
Crystal Creations has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 46 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of CRYSTAL HOMES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CRYSTAL HOMES: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CRYSTAL HOMES
What is the possession date of CRYSTAL HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CRYSTAL HOMES in Yamunanagar, Pune is 31 December 2023 — 48 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for CRYSTAL HOMES?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CRYSTAL HOMES's builder has filed on MahaRERA, the official one, is 31 December 2023, already 48 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CRYSTAL HOMES extended?
According to GharKundli's check of MahaRERA records (updated November 2026), CRYSTAL HOMES's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2020, giving the reason "waiting for PCMC completion certificate"; to 31 December 2023, giving the reason "Due to the COVID-19 pandemic, the regular flow of work is hampered on account of the unavailability of labour on a regular basis".
What is the RERA number of CRYSTAL HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CRYSTAL HOMES in Yamunanagar, Pune is P52100002053.
Is CRYSTAL HOMES registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CRYSTAL HOMES is registered as P52100002053 and its status is "Completed".
What is the construction status of CRYSTAL HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), CRYSTAL HOMES's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does CRYSTAL HOMES have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is CRYSTAL HOMES safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), CRYSTAL HOMES is registered on MahaRERA as P52100002053, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does CRYSTAL HOMES have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Crystal Homes Phase - I (P52100053027, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if CRYSTAL HOMES's possession date changes?
The latest dates are on CRYSTAL HOMES's MahaRERA page (P52100002053). GharKundli's Kundli Watch sends a free WhatsApp update on CRYSTAL HOMES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CRYSTAL HOMES have?
According to GharKundli's check of MahaRERA records (updated November 2026), CRYSTAL HOMES has 2 buildings filed: C with 9 floors; D with 9 floors.
How big is the land of CRYSTAL HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), CRYSTAL HOMES stands on 3,100 sq m of land (about 0.8 acres), with 2,368 sq m of sanctioned built-up area and 285 sq m of recreational open space.
What is the track record of CRYSTAL HOMES's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Crystal Creations has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 46 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of CRYSTAL HOMES?
Google Maps has reviews of CRYSTAL HOMES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CRYSTAL HOMES?
CRYSTAL HOMES by CRYSTAL CREATIONS is in Yamunanagar, Pune (pincode 412101), Maharashtra, and is registered on MahaRERA as P52100002053, per GharKundli's check of MahaRERA records.
How many homes are in CRYSTAL HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), CRYSTAL HOMES has 50 homes in 2 towers registered on MahaRERA.
When was CRYSTAL HOMES registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CRYSTAL HOMES was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on CRYSTAL HOMES?
No court cases are listed for CRYSTAL HOMES on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of CRYSTAL HOMES?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is CRYSTAL CREATIONS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of CRYSTAL HOMES
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Haveli
- QUE 101 PHASE I
- MADHUGHAT
- CULLINAN
- SIDDHI AURUM
- ATS - THE CONDOMINIUMS
- DYNAMIC SOLITAIRE – PHASE II
- BALWANT EMPIRE
- SnehKunj
Other projects by CRYSTAL CREATIONS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.