by SAPTGIRI DEVELOPERS · Yamunanagar, Pune 412114Also near Chikhali, Jadhavwadi, AkurdiRegistered on MahaRERA as “CRYSTAL CORNER”
What’s in the report? →Possession: Saptgiri Crystal Corner (MahaRERA P52100004065) is marked completed on MahaRERA. It has 105 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100004065. Status: Completed.
Source: MahaRERA website — records for P52100004065, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Saptgiri Crystal Corner?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Saptgiri Crystal Corner has moved
31 March 2018
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT52100000544)
Reason the builder gave MahaRERA: “WE ARE APPLIED FOR FINAL (COMPLITION)NO OBJECTION CERTIFICATE FORM WATER DIVISION , GARDEN NOC, DRAINAGE NOC, AND FIRE NOC. AFTER RECEIVING OF ALL NOC WE CAN APPLIED FOR CC.”
30 April 2020
Extended at the builder's request (MahaRERA application EXT52100002314)
Reason the builder gave MahaRERA: “PROJECT COMPLETION CERTIFICATE RECEIVED FROM pcmc AND POSSESSION GIVEN TO ALL FLAT PURCHASERS, SO PLEASE WE ARE REQUESTING YOU CLOSE OUR RERA NO.”
30 October 2020
Revised completion date on MahaRERA
Source: Saptgiri Crystal Corner’s extension records on MahaRERA (P52100004065), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Saptgiri Crystal Corner
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100004065
- Status
- Completed
- Builder
- SAPTGIRI DEVELOPERS
- Location
- Yamunanagar, Pune · 412114
- Project type
- Residential / Group Housing
- Registered on
- 7 Aug 2017
- Completion date at registration
- March 2018
- Latest completion date
- October 2020
- Delay so far
- 31 months
- Homes
- 105
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Saptgiri Crystal Corner, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 0% | 100% | 80% | 100% |
| B | 0% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Saptgiri Crystal Corner every 1–2 months.
Saptgiri Crystal Corner: buildings, flats and land, as filed on MahaRERA
- Buildings: A (9 floors) · B (9 floors)
- Land: 3,813 sq m (about 0.9 acres) · sanctioned built-up 4,738 sq m · recreational space 379 sq m
- Land, as filed: GAT NO 1585,DHARMARAJNAGAR CHIKHALI
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Saptgiri Crystal Corner →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Saptgiri Crystal Corner: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Saptgiri Crystal Corner
What is the possession date of Saptgiri Crystal Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Saptgiri Crystal Corner in Yamunanagar, Pune is 30 October 2020 — 31 months later than 31 March 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Saptgiri Crystal Corner?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Saptgiri Crystal Corner's builder has filed on MahaRERA, the official one, is 30 October 2020, already 31 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Saptgiri Crystal Corner extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2020, giving the reason "WE ARE APPLIED FOR FINAL (COMPLITION)NO OBJECTION CERTIFICATE FORM WATER DIVISION , GARDEN NOC, DRAINAGE NOC, AND FIRE NOC. AFTER RECEIVING OF ALL NOC WE CAN APPLIED FOR CC."; to 30 April 2020, giving the reason "PROJECT COMPLETION CERTIFICATE RECEIVED FROM pcmc AND POSSESSION GIVEN TO ALL FLAT PURCHASERS, SO PLEASE WE ARE REQUESTING YOU CLOSE OUR RERA NO.".
What is the RERA number of Saptgiri Crystal Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Saptgiri Crystal Corner in Yamunanagar, Pune is P52100004065.
Is Saptgiri Crystal Corner registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner is registered as P52100004065 and its status is "Completed".
What is the current construction status of Saptgiri Crystal Corner? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Saptgiri Crystal Corner have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Saptgiri Crystal Corner safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner is registered on MahaRERA as P52100004065, its MahaRERA status is "Completed", its completion date has moved 31 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Saptgiri Crystal Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Saptgiri Crystal Corner?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Saptgiri Crystal Corner: gharkundli.com/tools/property-cost-calculator
Has Saptgiri Crystal Corner received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Saptgiri Crystal Corner completed?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner is marked completed on MahaRERA, and the completion date filed there is 30 October 2020. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Saptgiri Crystal Corner uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Saptgiri Crystal Corner was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Saptgiri Crystal Corner's possession date changes?
The latest dates are on Saptgiri Crystal Corner's MahaRERA page (P52100004065). GharKundli's Kundli Watch sends a free WhatsApp update on Saptgiri Crystal Corner every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Saptgiri Crystal Corner have?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner has 2 buildings filed: A with 9 floors; B with 9 floors.
How big is the land of Saptgiri Crystal Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner stands on 3,813 sq m of land (about 0.9 acres), with 4,738 sq m of sanctioned built-up area and 379 sq m of recreational open space.
What are the reviews of Saptgiri Crystal Corner?
Google Maps has reviews of Saptgiri Crystal Corner written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Saptgiri Crystal Corner?
Saptgiri Crystal Corner by SAPTGIRI DEVELOPERS is in Yamunanagar, Pune, pincode 412114 (near Chikhali, Jadhavwadi, Akurdi), Maharashtra, and is registered on MahaRERA as P52100004065, per GharKundli's check of MahaRERA records. Its land is filed as GAT NO 1585,DHARMARAJNAGAR CHIKHALI.
How many flats are in Saptgiri Crystal Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner has 105 homes in 2 towers registered on MahaRERA.
When was Saptgiri Crystal Corner registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Saptgiri Crystal Corner was registered on MahaRERA on 7 August 2017. GharKundli did not find a title report on the land on file there.
Does Saptgiri Crystal Corner have any legal issues or court cases?
No court cases are listed for Saptgiri Crystal Corner on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Saptgiri Crystal Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAPTGIRI DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Saptgiri Crystal Corner
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Haveli
All Pune projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.