Ivory Tathastu

by Ivory Lifespace LLP · Khed, PuneAlso near Chakan

Possession date of Ivory Tathastu: 30 April 2027, moved from 30 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100002274, and currently active. Its completion date has moved from June 2021 to April 2027: 66 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Ivory Tathastu?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Ivory Tathastu has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT52100010666)

    Reason the builder gave MahaRERA:
    “We have registered our project “Ivory Tathastu” as on 31/07/2017. At the time of registration we had given expected date of project completion as 31/12/2020, also we got covid extention to 30/06/21. However we won’t be able to obtain comple…” Read the full reason“We have registered our project “Ivory Tathastu” as on 31/07/2017. At the time of registration we had given expected date of project completion as 31/12/2020, also we got covid extention to 30/06/21. However we won’t be able to obtain completion certificate till that date due to some legal formalities that are taking some time. We request you to grant us the extension of 1 years (i.e. upto 30/06/2022) so that we may complete our project and obtain Completion Certificate.”
  3. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT52100013131)

    Reason the builder gave MahaRERA:
    “There were some delays happened in completion of the project but it was due to ups and downsfor the Indian Real Estate Sector due to corona pandemic. There was liquidity crisis in the market and slowdown in sales since the banks had stricte…” Read the full reason“There were some delays happened in completion of the project but it was due to ups and downsfor the Indian Real Estate Sector due to corona pandemic. There was liquidity crisis in the market and slowdown in sales since the banks had stricter norms for financing the allottees. Due to which the builder also faced huge losses and interest burden on his borrowings.”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT52100018136)

    Reason the builder gave MahaRERA:
    “At the time of previous extension, we had given expected date of project completion as 30.12.2023. However we won’t be able to obtain completion certificate till that date due to some legal formalities that are taking some time, we request…” Read the full reason“At the time of previous extension, we had given expected date of project completion as 30.12.2023. However we won’t be able to obtain completion certificate till that date due to some legal formalities that are taking some time, we request you to grant us the extension upto 31.12.2026 so that we may complete our project and obtain Completion Certificate.”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ivory Tathastu’s extension records on MahaRERA (P52100002274), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ivory Tathastu

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100002274
Status
Registered and active
Builder
Ivory Lifespace LLP
Location
Khed, Pune · 410501
Project type
Mixed
Registered on
31 Jul 2017
Completion date at registration
June 2021
Latest completion date
April 2027
Delay so far
66 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
110
Sold or booked
97%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Ivory Tathastu, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Building100%100%100%100%
B Building0%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • A Building: covers 9 floors
  • B Building: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ivory Tathastu every month.

Ivory Tathastu: buildings, flats and land, as filed on MahaRERA

  • Buildings: A Building (9 floors, 38 units) · B Building (9 floors, 89 units)
  • Car parking: 27 covered
  • Land: 8,400 sq m (about 2.1 acres) · sanctioned built-up 6,298 sq m · recreational space 630 sq m
  • Boundaries filed include: Mahalunge Rahakal Road, Mahalunge Ambethan Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Ivory Tathastu →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ivory Tathastu: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Ivory Tathastu

What is the possession date of Ivory Tathastu?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ivory Tathastu in Khed, Pune is 30 April 2027 — 66 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Ivory Tathastu?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ivory Tathastu's builder has filed on MahaRERA, the official one, is 30 April 2027, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ivory Tathastu extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Ivory Tathastu's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "We have registered our project “Ivory Tathastu” as on 31/07/2017. At the time of registration we had given expected date of project completion as 31/12/2020, also we got covid extention to 30/06/21. However we won’t be able to obtain completion certificate till that date due to some legal formalities that are taking some time. We request you to grant us the extension of 1 years (i.e. upto 30/06/2022) so that we may complete our project and obtain Completion Certificate."; to 30 December 2023, giving the reason "There were some delays happened in completion of the project but it was due to ups and downsfor the Indian Real Estate Sector due to corona pandemic. There was liquidity crisis in the market and slowdown in sales since the banks had stricter norms for financing the allottees. Due to which the builder also faced huge losses and interest burden on his borrowings."; to 31 December 2026, giving the reason "At the time of previous extension, we had given expected date of project completion as 30.12.2023. However we won’t be able to obtain completion certificate till that date due to some legal formalities that are taking some time, we request you to grant us the extension upto 31.12.2026 so that we may complete our project and obtain Completion Certificate.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ivory Tathastu?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ivory Tathastu in Khed, Pune is P52100002274.

Is Ivory Tathastu registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ivory Tathastu is registered as P52100002274 and its status is "Registered and active".

What is the construction status of Ivory Tathastu?

According to GharKundli's check of MahaRERA records (updated November 2026), Ivory Tathastu's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Ivory Tathastu have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Ivory Tathastu safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Ivory Tathastu is registered on MahaRERA as P52100002274, its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Ivory Tathastu's possession date changes?

The latest dates are on Ivory Tathastu's MahaRERA page (P52100002274). GharKundli's Kundli Watch sends a free WhatsApp update on Ivory Tathastu every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ivory Tathastu have?

According to GharKundli's check of MahaRERA records (updated November 2026), Ivory Tathastu has 2 buildings filed: A Building with 9 floors and 38 units; B Building with 9 floors and 89 units.

How much parking does Ivory Tathastu have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 27 covered car parking spaces for Ivory Tathastu.

How big is the land of Ivory Tathastu?

According to GharKundli's check of MahaRERA records (updated November 2026), Ivory Tathastu stands on 8,400 sq m of land (about 2.1 acres), with 6,298 sq m of sanctioned built-up area and 630 sq m of recreational open space.

Where can I read reviews of Ivory Tathastu?

Google Maps has reviews of Ivory Tathastu written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Ivory Tathastu?

Ivory Tathastu by Ivory Lifespace LLP is in Khed, Pune (pincode 410501), near Chakan, Maharashtra, and is registered on MahaRERA as P52100002274, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mahalunge Rahakal Road, Mahalunge Ambethan Road.

How many homes are in Ivory Tathastu?

According to GharKundli's check of MahaRERA records (updated November 2026), Ivory Tathastu has 110 homes in 2 towers registered on MahaRERA, and 97% of them are sold or booked.

When was Ivory Tathastu registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ivory Tathastu was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Ivory Tathastu?

No court cases are listed for Ivory Tathastu on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Ivory Tathastu?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ivory Lifespace LLP.