SAI YASHODHAN BLDG NO. 2

by deepak sadanand hanchate · parasnath nagari, Palghar

Possession: SAI YASHODHAN BLDG NO. 2 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000005416. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAI YASHODHAN BLDG NO. 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI YASHODHAN BLDG NO. 2 has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT99000001855)

    Reason the builder gave MahaRERA: “due non availability of building material sand”
  3. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT99000005368)

    Reason the builder gave MahaRERA: “non availability of material and delayed in getting permission for upper floors from collector”
  4. 29 December 2025

    Extended at the builder's request (MahaRERA application EXT99000018739)

    Reason the builder gave MahaRERA: “As there was delay in receiving N.A order of proposed pending upper floors from the component Authority”
  5. 30 December 2027

    Extended at the builder's request (MahaRERA application EA18012619490)

    Reason the builder gave MahaRERA: “we have completed the project have applied for OC hence required extension”

Source: SAI YASHODHAN BLDG NO. 2’s extension records on MahaRERA (P99000005416), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI YASHODHAN BLDG NO. 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000005416
Status
Completed
Builder
deepak sadanand hanchate
Location
parasnath nagari, Palghar · 401404
Project type
Residential / Group Housing
Registered on
11 Aug 2017
Completion date at registration
December 2018
Latest completion date
December 2027
Delay so far
108 months
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SAI YASHODHAN BLDG NO. 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%100%100%100%
WING B100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI YASHODHAN BLDG NO. 2 every month.

SAI YASHODHAN BLDG NO. 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A (5 floors) · WING B (5 floors)
  • Car parking: 1 covered
  • Land: 1,722 sq m (about 0.4 acres) · sanctioned built-up 2,838 sq m

The builder’s record and reviews

Deepak Sadanand Hanchate has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 107 months); 1 still being built, 1 past the promised date (typically 99 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of SAI YASHODHAN BLDG NO. 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI YASHODHAN BLDG NO. 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI YASHODHAN BLDG NO. 2

What is the possession date of SAI YASHODHAN BLDG NO. 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI YASHODHAN BLDG NO. 2 in parasnath nagari, Palghar is 30 December 2027 — 108 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAI YASHODHAN BLDG NO. 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI YASHODHAN BLDG NO. 2's builder has filed on MahaRERA, the official one, is 30 December 2027, already 108 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI YASHODHAN BLDG NO. 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI YASHODHAN BLDG NO. 2's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2022, giving the reason "due non availability of building material sand"; to 31 December 2022, giving the reason "non availability of material and delayed in getting permission for upper floors from collector"; to 29 December 2025, giving the reason "As there was delay in receiving N.A order of proposed pending upper floors from the component Authority"; to 30 December 2027, giving the reason "we have completed the project have applied for OC hence required extension".

What is the RERA number of SAI YASHODHAN BLDG NO. 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI YASHODHAN BLDG NO. 2 in parasnath nagari, Palghar is P99000005416.

Is SAI YASHODHAN BLDG NO. 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI YASHODHAN BLDG NO. 2 is registered as P99000005416 and its status is "Completed".

What is the construction status of SAI YASHODHAN BLDG NO. 2?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI YASHODHAN BLDG NO. 2's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does SAI YASHODHAN BLDG NO. 2 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAI YASHODHAN BLDG NO. 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI YASHODHAN BLDG NO. 2 is registered on MahaRERA as P99000005416, its MahaRERA status is "Completed", its completion date has moved 108 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does SAI YASHODHAN BLDG NO. 2 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SAI YASHODHAN BLDG NO.1 (P99000009983, possession 29 Apr 2027). Check that your agreement names the registration of your own wing.

How can I get updates if SAI YASHODHAN BLDG NO. 2's possession date changes?

The latest dates are on SAI YASHODHAN BLDG NO. 2's MahaRERA page (P99000005416). GharKundli's Kundli Watch sends a free WhatsApp update on SAI YASHODHAN BLDG NO. 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI YASHODHAN BLDG NO. 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI YASHODHAN BLDG NO. 2 has 2 buildings filed: WING A with 5 floors; WING B with 5 floors.

How much parking does SAI YASHODHAN BLDG NO. 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for SAI YASHODHAN BLDG NO. 2.

How big is the land of SAI YASHODHAN BLDG NO. 2?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI YASHODHAN BLDG NO. 2 stands on 1,722 sq m of land (about 0.4 acres), with 2,838 sq m of sanctioned built-up area.

What is the track record of SAI YASHODHAN BLDG NO. 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Deepak Sadanand Hanchate has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 107 months); 1 still being built, 1 past the promised date (typically 99 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAI YASHODHAN BLDG NO. 2?

Google Maps has reviews of SAI YASHODHAN BLDG NO. 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI YASHODHAN BLDG NO. 2?

SAI YASHODHAN BLDG NO. 2 by deepak sadanand hanchate is in parasnath nagari, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000005416, per GharKundli's check of MahaRERA records.

When was SAI YASHODHAN BLDG NO. 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI YASHODHAN BLDG NO. 2 was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI YASHODHAN BLDG NO. 2?

No court cases are listed for SAI YASHODHAN BLDG NO. 2 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SAI YASHODHAN BLDG NO. 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is deepak sadanand hanchate, which has 1 other project registered on MahaRERA.

Other projects in Palghar

All 366 projects in Palghar (401404) →

Other projects by deepak sadanand hanchate

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.