Triaa Hillome

by TRIAA DEVELOPMENTS · Sangamwadi, Pune 411001Also near Panchavati, Pune city, Pune Station

What’s in the report? →

Possession date of Triaa Hillome (MahaRERA P52100005561): 30 December 2020, moved from 30 December 2019 (12 months later), and it has already passed. It has 107 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100005561. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100005561, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2020) has passed.

What do you want to know about Triaa Hillome?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Triaa Hillome has moved

  1. 30 December 2019

    Completion date given when the project was registered

  2. 30 June 2020

    Extended at the builder's request (MahaRERA application EXT52100005344)

    Reason the builder gave MahaRERA: “Waiting for Completion Certificate from The Competent Authority”
  3. 30 December 2020

    Revised completion date on MahaRERA

Source: Triaa Hillome’s extension records on MahaRERA (P52100005561), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Triaa Hillome

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100005561
Status
Lapsed (registration period ended)
Builder
TRIAA DEVELOPMENTS
Location
Sangamwadi, Pune · 411001
Project type
Others
Registered on
11 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2020
Delay so far
12 months
Homes
107
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Triaa Hillome, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TRIAA HILLOME WING B100%100%90%50%
TRIAA HILLOME WING A100%40%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Triaa Hillome every 1–2 months.

Triaa Hillome: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Triaa Lifespaces (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 still being built, 1 past the promised date (typically 1 months late); 3 lapsed. 3 complaints on MahaRERA across 2 projects.

Read Google reviews of Triaa Hillome →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Triaa Hillome: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Triaa Hillome

What is the possession date of Triaa Hillome?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Triaa Hillome in Sangamwadi, Pune is 30 December 2020 — 12 months later than 30 December 2019, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Triaa Hillome?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Triaa Hillome's builder has filed on MahaRERA, the official one, is 30 December 2020, already 12 months later than the 30 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Triaa Hillome extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome's builder applied to MahaRERA to extend the completion date once: to 30 June 2020, giving the reason "Waiting for Completion Certificate from The Competent Authority".

What is the RERA number of Triaa Hillome?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Triaa Hillome in Sangamwadi, Pune is P52100005561.

Is Triaa Hillome registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome is registered as P52100005561 and its status is "Lapsed (registration period ended)".

What is the current construction status of Triaa Hillome? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 40% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Triaa Hillome have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Triaa Hillome safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome is registered on MahaRERA as P52100005561, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Triaa Hillome?

Triaa Hillome isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Triaa Hillome?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Triaa Hillome: gharkundli.com/tools/property-cost-calculator

Has Triaa Hillome received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Triaa Hillome?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Triaa Hillome uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Triaa Hillome was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Triaa Hillome's possession date changes?

The latest dates are on Triaa Hillome's MahaRERA page (P52100005561). GharKundli's Kundli Watch sends a free WhatsApp update on Triaa Hillome every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Triaa Hillome have?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome has 2 buildings filed: TRIAA HILLOME WING B with 10 floors; TRIAA HILLOME WING A with 13 floors.

How big is the land of Triaa Hillome?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome stands on 4,000 sq m of land (about 1.0 acres), with 4,262 sq m of sanctioned built-up area and 400 sq m of recreational open space.

What is the track record of Triaa Hillome's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Lifespaces (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 still being built, 1 past the promised date (typically 1 months late); 3 lapsed. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Triaa Hillome?

Google Maps has reviews of Triaa Hillome written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Triaa Hillome?

Triaa Hillome by TRIAA DEVELOPMENTS is in Sangamwadi, Pune, pincode 411001 (near Panchavati, Pune city, Pune Station), Maharashtra, and is registered on MahaRERA as P52100005561, per GharKundli's check of MahaRERA records. Its land is filed as 284/4. GharKundli lists all 103 MahaRERA projects in Pune (411001).

How many flats are in Triaa Hillome?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome has 107 homes in 2 towers registered on MahaRERA.

When was Triaa Hillome registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Hillome was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Does Triaa Hillome have any legal issues or court cases?

No court cases are listed for Triaa Hillome on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Triaa Hillome?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is TRIAA DEVELOPMENTS.