What’s in the report? →Possession date of Punyavaastu (MahaRERA P52100011322): 30 October 2020, moved from 31 July 2018 (27 months later), and it has already passed. It has 86 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100011322. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100011322, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2020) has passed.
What do you want to know about Punyavaastu?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Punyavaastu has moved
31 July 2018
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT52100000566)
Reason the builder gave MahaRERA: “We have submitted the file for part completion of the project. We have to utilise the TDR”
30 April 2020
Extended at the builder's request (MahaRERA application EXT52100005405)
Reason the builder gave MahaRERA: “WE HAVE RECEIVED THE COMPLETION CERTIFICATE OF THE RESIDENTIAL UNIT (78 OUT OF 78). WE ARE WAITING FOR THE COMPLETION CERTIFICATE OF COMMERCIAL. NOT SOLD ANY UNIT OF COMMERCIAL”
30 October 2020
Revised completion date on MahaRERA
Source: Punyavaastu’s extension records on MahaRERA (P52100011322), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Punyavaastu
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100011322
- Status
- Lapsed (registration period ended)
- Builder
- URBAN CREATION
- Location
- Sangamwadi, Pune · 412105
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- July 2018
- Latest completion date
- October 2020
- Delay so far
- 27 months
- Homes
- 86
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Punyavaastu, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RESIDENTIAL | 100% | 100% | 100% | 100% |
| COMMERCIAL | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Punyavaastu every 1–2 months.
Punyavaastu: buildings, flats and land, as filed on MahaRERA
- Buildings: RESIDENTIAL (13 floors) · COMMERCIAL (2 floors)
- Land: 3,469 sq m (about 0.9 acres) · sanctioned built-up 3,468 sq m · recreational space 312 sq m
- Land, as filed: 103/1/2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Punyavaastu →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Punyavaastu: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Punyavaastu
What is the possession date of Punyavaastu?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Punyavaastu in Sangamwadi, Pune is 30 October 2020 — 27 months later than 31 July 2018, the date given at registration. That date has already passed.
The date has already moved 27 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Punyavaastu?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Punyavaastu's builder has filed on MahaRERA, the official one, is 30 October 2020, already 27 months later than the 31 July 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Punyavaastu extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2020, giving the reason "We have submitted the file for part completion of the project. We have to utilise the TDR"; to 30 April 2020, giving the reason "WE HAVE RECEIVED THE COMPLETION CERTIFICATE OF THE RESIDENTIAL UNIT (78 OUT OF 78). WE ARE WAITING FOR THE COMPLETION CERTIFICATE OF COMMERCIAL. NOT SOLD ANY UNIT OF COMMERCIAL".
What is the RERA number of Punyavaastu?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Punyavaastu in Sangamwadi, Pune is P52100011322.
Is Punyavaastu registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu is registered as P52100011322 and its status is "Lapsed (registration period ended)".
What is the current construction status of Punyavaastu? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Punyavaastu have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Punyavaastu safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu is registered on MahaRERA as P52100011322, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Punyavaastu?
Punyavaastu isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Punyavaastu?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Punyavaastu: gharkundli.com/tools/property-cost-calculator
Has Punyavaastu received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 October 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Punyavaastu?
According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 October 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Punyavaastu uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Punyavaastu was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Punyavaastu's possession date changes?
The latest dates are on Punyavaastu's MahaRERA page (P52100011322). GharKundli's Kundli Watch sends a free WhatsApp update on Punyavaastu every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Punyavaastu have?
According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu has 2 buildings filed: RESIDENTIAL with 13 floors; COMMERCIAL with 2 floors.
How big is the land of Punyavaastu?
According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu stands on 3,469 sq m of land (about 0.9 acres), with 3,468 sq m of sanctioned built-up area and 312 sq m of recreational open space.
What are the reviews of Punyavaastu?
Google Maps has reviews of Punyavaastu written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Punyavaastu?
Punyavaastu by URBAN CREATION is in Sangamwadi, Pune, pincode 412105, Maharashtra, and is registered on MahaRERA as P52100011322, per GharKundli's check of MahaRERA records. Its land is filed as 103/1/2. GharKundli lists all 885 MahaRERA projects in Alandi Devachi (412105).
How many flats are in Punyavaastu?
According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu has 86 homes in 2 towers registered on MahaRERA.
When was Punyavaastu registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Punyavaastu was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Punyavaastu have any legal issues or court cases?
No court cases are listed for Punyavaastu on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Punyavaastu?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is URBAN CREATION.
Check it yourself on MahaRERA
- How to check the possession date of Punyavaastu
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Alandi Devachi (412105)
All 885 projects in Alandi Devachi (412105) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.