ESSENCIA HEIGHTS

by Sanskruti & Aditya Associates · Balewadi Stadium, PuneAlso near Baner, Mahalunge, N.I.A

Possession: ESSENCIA HEIGHTS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100007045. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about ESSENCIA HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ESSENCIA HEIGHTS has moved

  1. 1 February 2021

    Completion date given when the project was registered

  2. 31 January 2022

    Extended at the builder's request (MahaRERA application EXT52100009014)

    Reason the builder gave MahaRERA:
    “We had submitted the proposal for revised sanctioning in PMRDA. The file was put-up in the office of PMRDA in the month of February 2019. however, the same was sanctioned on the 06 th March 2020 which resulted in the delay out of the develo…” Read the full reason“We had submitted the proposal for revised sanctioning in PMRDA. The file was put-up in the office of PMRDA in the month of February 2019. however, the same was sanctioned on the 06 th March 2020 which resulted in the delay out of the developer’s hand. Due to Covid 19 (Corona Virus) pandemic, reverse migration of labourers to their native places and the construction activities of the said projects was highly impacted and break in supply chain of construction material and the said project facing problem of material shortage /unavailability.”
  3. 31 July 2023

    Extended at the builder's request (MahaRERA application EXT52100012359)

    Reason the builder gave MahaRERA:
    “We have already received part occupation certificate upto 8th floor bearing no 1586/18-19 dated 08/11/2021 File has already been submitted with PMRDA for obtaining occupation certificate for the 9th & 10th floor and now awaited for its cert…” Read the full reason“We have already received part occupation certificate upto 8th floor bearing no 1586/18-19 dated 08/11/2021 File has already been submitted with PMRDA for obtaining occupation certificate for the 9th & 10th floor and now awaited for its certificate. Considering the time required for obtaining Occupation certificate, we hereby requesting the MAHARERA Authority to please allow the extension of project completion Date till 31/07/2023.”
  4. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52100018073)

    Reason the builder gave MahaRERA:
    “The Project was completed within the timeframe of the extended date of completion along with the procurement of the occupancy certificate up to 8th Floor out of 10 Floors dated 08/11/2021 which is uploaded on the RERA website. Occupancy Cer…” Read the full reason“The Project was completed within the timeframe of the extended date of completion along with the procurement of the occupancy certificate up to 8th Floor out of 10 Floors dated 08/11/2021 which is uploaded on the RERA website. Occupancy Certificate for the 9th & 10th Floors was pending due to the MOD Noc which was also obtained on 04/10/2023 & the same has been uploaded on the RERA website. we request you to grant us the extension as we have completed our project alongwith the procurement of occupancy certificate from the concerned authority. Also, Form 4 on completion from architect has be…”

Source: ESSENCIA HEIGHTS’s extension records on MahaRERA (P52100007045), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ESSENCIA HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100007045
Status
Completed
Builder
Sanskruti & Aditya Associates
Location
Balewadi Stadium, Pune · 411045
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
February 2021
Latest completion date
December 2023
Delay so far
34 months
Homes
88
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of ESSENCIA HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ESSENCIA HEIGHTS every month.

ESSENCIA HEIGHTS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ESSENCIA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ESSENCIA HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ESSENCIA HEIGHTS

What is the possession date of ESSENCIA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ESSENCIA HEIGHTS in Balewadi Stadium, Pune is 31 December 2023 — 34 months later than 1 February 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for ESSENCIA HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ESSENCIA HEIGHTS's builder has filed on MahaRERA, the official one, is 31 December 2023, already 34 months later than the 1 February 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ESSENCIA HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), ESSENCIA HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 31 January 2022, giving the reason "We had submitted the proposal for revised sanctioning in PMRDA. The file was put-up in the office of PMRDA in the month of February 2019. however, the same was sanctioned on the 06 th March 2020 which resulted in the delay out of the developer’s hand. Due to Covid 19 (Corona Virus) pandemic, reverse migration of labourers to their native places and the construction activities of the said projects was highly impacted and break in supply chain of construction material and the said project facing problem of material shortage /unavailability."; to 31 July 2023, giving the reason "We have already received part occupation certificate upto 8th floor bearing no 1586/18-19 dated 08/11/2021 File has already been submitted with PMRDA for obtaining occupation certificate for the 9th & 10th floor and now awaited for its certificate. Considering the time required for obtaining Occupation certificate, we hereby requesting the MAHARERA Authority to please allow the extension of project completion Date till 31/07/2023."; to 31 December 2023, giving the reason "The Project was completed within the timeframe of the extended date of completion along with the procurement of the occupancy certificate up to 8th Floor out of 10 Floors dated 08/11/2021 which is uploaded on the RERA website. Occupancy Certificate for the 9th & 10th Floors was pending due to the MOD Noc which was also obtained on 04/10/2023 & the same has been uploaded on the RERA website. we request you to grant us the extension as we have completed our project alongwith the procurement of occupancy certificate from the concerned authority. Also, Form 4 on completion from architect has be…".

What is the RERA number of ESSENCIA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ESSENCIA HEIGHTS in Balewadi Stadium, Pune is P52100007045.

Is ESSENCIA HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ESSENCIA HEIGHTS is registered as P52100007045 and its status is "Completed".

What is the construction status of ESSENCIA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), ESSENCIA HEIGHTS's status on MahaRERA is "Completed". As filed by the builder, slab work on C is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does ESSENCIA HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is ESSENCIA HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ESSENCIA HEIGHTS is registered on MahaRERA as P52100007045, its MahaRERA status is "Completed", its completion date has moved 34 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ESSENCIA HEIGHTS's possession date changes?

The latest dates are on ESSENCIA HEIGHTS's MahaRERA page (P52100007045). GharKundli's Kundli Watch sends a free WhatsApp update on ESSENCIA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ESSENCIA HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), ESSENCIA HEIGHTS has one building filed: C with 11 floors.

How big is the land of ESSENCIA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), ESSENCIA HEIGHTS stands on 1,800 sq m of land (about 0.4 acres), with 5,032 sq m of sanctioned built-up area and 1,020 sq m of recreational open space.

Where can I read reviews of ESSENCIA HEIGHTS?

Google Maps has reviews of ESSENCIA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ESSENCIA HEIGHTS?

ESSENCIA HEIGHTS by Sanskruti & Aditya Associates is in Balewadi Stadium, Pune (pincode 411045), near Baner, Mahalunge, N.I.A, Maharashtra, and is registered on MahaRERA as P52100007045, per GharKundli's check of MahaRERA records. Its boundaries filed there include GAYRAN ROAD.

How many homes are in ESSENCIA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), ESSENCIA HEIGHTS has 88 homes in 1 tower registered on MahaRERA.

When was ESSENCIA HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ESSENCIA HEIGHTS was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ESSENCIA HEIGHTS?

No court cases are listed for ESSENCIA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of ESSENCIA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sanskruti & Aditya Associates.

Other projects in Mulshi

All 425 projects in Baner (411045) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.