Skip to content
GharKundli

Aps Grand

by APS DEVELOPERS · Near Mokashi Bunglow, Pune 410401

What’s in the report? →

Possession: Aps Grand (MahaRERA P52100006373) is marked completed on MahaRERA. It has 76 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100006373. Status: Completed.

Source: MahaRERA website — records for P52100006373, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Aps Grand?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Aps Grand has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT52100000812)

    Reason the builder gave MahaRERA:
    “FOURTH FLOOR PERMISSION RECEIVED FROM LONAVALA MUNICIPAL COUNCIL ON 27.08.2018 VIDE REVISED COMMENCEMENT CERTIFICATE LETTER NO.ENG/BP/60/1495 ON 27.08.2018. THEREAFTER WE HAVE STARTED WORK ABOVE 3RD FLOOR HENCE WORK IS DELAYED. HENCE WE REQ…” Read the full reason“FOURTH FLOOR PERMISSION RECEIVED FROM LONAVALA MUNICIPAL COUNCIL ON 27.08.2018 VIDE REVISED COMMENCEMENT CERTIFICATE LETTER NO.ENG/BP/60/1495 ON 27.08.2018. THEREAFTER WE HAVE STARTED WORK ABOVE 3RD FLOOR HENCE WORK IS DELAYED. HENCE WE REQUIRED ADDITIONAL 4 MONTHS PERIOD TO COMPLETE THE PROJECT IN ALL RESPECT. PRESENTLY ALL RCC WORK & BRICK WORK IS COMPLETED WITH COUNSILED PLUMBING & ELECTRICAL WORKS. INSIDE PLASTER UP-TO 3RD FLOOR IS COMPLETED AND OUTSIDE PLASTER AND 4TH FLOOR INSIDE PLASTER IS IN PROGRESS. UNDER GROUND & OVERHEAD WATER TANKS ARE COMPLETED.”

Source: Aps Grand’s extension records on MahaRERA (P52100006373), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aps Grand

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100006373
Status
Completed
Builder
APS DEVELOPERS
Location
Near Mokashi Bunglow, Pune · 410401
Project type
Others
Registered on
14 Aug 2017
Completion date at registration
December 2018
Latest completion date
December 2019
Delay so far
12 months
Homes
76
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Aps Grand, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
APS GRAND100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aps Grand every 1–2 months.

Aps Grand: buildings, flats and land, as filed on MahaRERA

  • Buildings: APS GRAND (5 floors)
  • Land: 3,153 sq m (about 0.8 acres) · sanctioned built-up 2,678 sq m · recreational space 1,571 sq m
  • Land, as filed: 188, 54
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Aps Grand →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aps Grand: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aps Grand

What is the possession date of Aps Grand?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aps Grand in Near Mokashi Bunglow, Pune is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Aps Grand?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aps Grand's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Aps Grand extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "FOURTH FLOOR PERMISSION RECEIVED FROM LONAVALA MUNICIPAL COUNCIL ON 27.08.2018 VIDE REVISED COMMENCEMENT CERTIFICATE LETTER NO.ENG/BP/60/1495 ON 27.08.2018. THEREAFTER WE HAVE STARTED WORK ABOVE 3RD FLOOR HENCE WORK IS DELAYED. HENCE WE REQUIRED ADDITIONAL 4 MONTHS PERIOD TO COMPLETE THE PROJECT IN ALL RESPECT. PRESENTLY ALL RCC WORK & BRICK WORK IS COMPLETED WITH COUNSILED PLUMBING & ELECTRICAL WORKS. INSIDE PLASTER UP-TO 3RD FLOOR IS COMPLETED AND OUTSIDE PLASTER AND 4TH FLOOR INSIDE PLASTER IS IN PROGRESS. UNDER GROUND & OVERHEAD WATER TANKS ARE COMPLETED.".

What is the RERA number of Aps Grand?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aps Grand in Near Mokashi Bunglow, Pune is P52100006373.

Is Aps Grand registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand is registered as P52100006373 and its status is "Completed".

What is the current construction status of Aps Grand? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand's status on MahaRERA is "Completed". As filed by the builder, slab work on APS GRAND is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Aps Grand have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Aps Grand safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand is registered on MahaRERA as P52100006373, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aps Grand?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Aps Grand?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aps Grand: gharkundli.com/tools/property-cost-calculator

Has Aps Grand received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Aps Grand completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand is marked completed on MahaRERA, and the completion date filed there is 31 December 2019. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Aps Grand uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Aps Grand was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aps Grand's possession date changes?

The latest dates are on Aps Grand's MahaRERA page (P52100006373). GharKundli's Kundli Watch sends a free WhatsApp update on Aps Grand every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aps Grand have?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand has one building filed: APS GRAND with 5 floors.

How big is the land of Aps Grand?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand stands on 3,153 sq m of land (about 0.8 acres), with 2,678 sq m of sanctioned built-up area and 1,571 sq m of recreational open space.

What are the reviews of Aps Grand?

Google Maps has reviews of Aps Grand written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aps Grand?

Aps Grand by APS DEVELOPERS is in Near Mokashi Bunglow, Pune, pincode 410401, Maharashtra, and is registered on MahaRERA as P52100006373, per GharKundli's check of MahaRERA records. Its land is filed as 188, 54. GharKundli lists all 76 MahaRERA projects in Lonavala (410401).

How many flats are in Aps Grand?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand has 76 homes in 1 tower registered on MahaRERA.

When was Aps Grand registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aps Grand was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Does Aps Grand have any legal issues or court cases?

No court cases are listed for Aps Grand on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Aps Grand?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is APS DEVELOPERS, which has 1 other project registered on MahaRERA.

Other projects in Mawal

All 76 projects in Lonavala (410401) →

Other projects by APS DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.