Lakshya Paradise

by LAKSHYA PARADISE · Pimple Saudagar, Pune 411045Also near Baner, Balewadi, Pashan

What’s in the report? →

Possession date of Lakshya Paradise (MahaRERA P52100006265): 29 December 2020, moved from 30 June 2019 (18 months later), and it has already passed. It has 16 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100006265. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100006265, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2020) has passed.

What do you want to know about Lakshya Paradise?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Lakshya Paradise has moved

  1. 30 June 2019

    Completion date given when the project was registered

  2. 29 June 2020

    Extended at the builder's request (MahaRERA application EXT52100003719)

    Reason the builder gave MahaRERA: “TDR loading pending”
  3. 29 December 2020

    Revised completion date on MahaRERA

Source: Lakshya Paradise’s extension records on MahaRERA (P52100006265), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Lakshya Paradise

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100006265
Status
Lapsed (registration period ended)
Builder
LAKSHYA PARADISE
Location
Pimple Saudagar, Pune · 411045
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
June 2019
Latest completion date
December 2020
Delay so far
18 months
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Lakshya Paradise, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LAKSHYA PARADISE100%100%80%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lakshya Paradise every 1–2 months.

Lakshya Paradise: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Lakshya Paradise →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lakshya Paradise: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Lakshya Paradise

What is the possession date of Lakshya Paradise?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Lakshya Paradise in Pimple Saudagar, Pune is 29 December 2020 — 18 months later than 30 June 2019, the date given at registration. That date has already passed.

The date has already moved 18 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Lakshya Paradise?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lakshya Paradise's builder has filed on MahaRERA, the official one, is 29 December 2020, already 18 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Lakshya Paradise extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise's builder applied to MahaRERA to extend the completion date once: to 29 June 2020, giving the reason "TDR loading pending".

What is the RERA number of Lakshya Paradise?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Lakshya Paradise in Pimple Saudagar, Pune is P52100006265.

Is Lakshya Paradise registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise is registered as P52100006265 and its status is "Lapsed (registration period ended)".

What is the current construction status of Lakshya Paradise? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on LAKSHYA PARADISE is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Lakshya Paradise have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Lakshya Paradise safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise is registered on MahaRERA as P52100006265, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Lakshya Paradise?

Lakshya Paradise isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Lakshya Paradise?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Lakshya Paradise: gharkundli.com/tools/property-cost-calculator

Has Lakshya Paradise received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 29 December 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Lakshya Paradise?

According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (29 December 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Lakshya Paradise uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Lakshya Paradise was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Lakshya Paradise's possession date changes?

The latest dates are on Lakshya Paradise's MahaRERA page (P52100006265). GharKundli's Kundli Watch sends a free WhatsApp update on Lakshya Paradise every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lakshya Paradise have?

According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise has one building filed: LAKSHYA PARADISE with 4 floors.

How big is the land of Lakshya Paradise?

According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise stands on 500 sq m of land (about 0.1 acres), with 375 sq m of sanctioned built-up area.

What are the reviews of Lakshya Paradise?

Google Maps has reviews of Lakshya Paradise written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Lakshya Paradise?

Lakshya Paradise by LAKSHYA PARADISE is in Pimple Saudagar, Pune, pincode 411045 (near Baner, Balewadi, Pashan), Maharashtra, and is registered on MahaRERA as P52100006265, per GharKundli's check of MahaRERA records. Its land is filed as SR NO 105. GharKundli lists all 713 MahaRERA projects in Baner (411045).

How many flats are in Lakshya Paradise?

According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise has 16 homes in 1 tower registered on MahaRERA.

When was Lakshya Paradise registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Lakshya Paradise was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Does Lakshya Paradise have any legal issues or court cases?

No court cases are listed for Lakshya Paradise on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Lakshya Paradise?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is LAKSHYA PARADISE.

Other projects in Baner (411045)

All 713 projects in Baner (411045) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.