Jupiter Complex
by M/s. JEM Developers · Betegoan, Palghar
Possession date of Jupiter Complex: 30 April 2027, moved from 31 May 2019 (91 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000013313, and currently active. Its completion date has moved from May 2019 to April 2027: 91 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Jupiter Complex?
How the possession date of Jupiter Complex has moved
31 May 2019
Completion date given when the project was registered
30 May 2020
Extended at the builder's request (MahaRERA application EXT99000001756)
Reason the builder gave MahaRERA: “DUE TO CHANGE IN ENVIRONMENTAL NORMS BY COMPETENT AUTHORITY.”
30 May 2022
Extended at the builder's request (MahaRERA application EXT99000006137)
Reason the builder gave MahaRERA:
“Dear Sir, We the undersigned elected member of Association of Allottees of the Project upon the request received by M/s Jem Developers, Promoter of the Project – Jupiter Complex having MahaRERA No. P99000013313 situated at S.No./Plot bearin…” Read the full reason
“Dear Sir, We the undersigned elected member of Association of Allottees of the Project upon the request received by M/s Jem Developers, Promoter of the Project – Jupiter Complex having MahaRERA No. P99000013313 situated at S.No./Plot bearing No. 11,51,16,118 at betegoan, Palghar, PIN:401501 request your kind office the fact that: 1. The Project-Jupiter Complex has two buildings- building No 1 and Building No. 2. As per the Architect Certificate received by us Building No. 2 is physically 100% Completed and applied for Fire and other related NOC. And the work of Building No. 1 is going on bu…”30 September 2024
Extended at the builder's request (MahaRERA application EXT99000012729)
Reason the builder gave MahaRERA: “Dear Sir, Due to Corona virus pandemic, the project work has been affected and therefore extra time till 30-09-2024 is required to complete the project.”
31 December 2026
Extended at the builder's request (MahaRERA application EXT99000024641)
Reason the builder gave MahaRERA:
“DEAR SIR, CIVIL WORK OF BOTH BUILDING HAS BEEN COMPLETED AS PER ARCHITET'S LETTER ATTACHED. DUE TO SOME NORMS CHANGES AND CHANGE IN LAYOUT WE ARE GETTING DELAY IN OBTAINING O.C. DETAILED REASON AND WORK STATUS HAS BEEN ATTACHED IN OTHER TAB…” Read the full reason
“DEAR SIR, CIVIL WORK OF BOTH BUILDING HAS BEEN COMPLETED AS PER ARCHITET'S LETTER ATTACHED. DUE TO SOME NORMS CHANGES AND CHANGE IN LAYOUT WE ARE GETTING DELAY IN OBTAINING O.C. DETAILED REASON AND WORK STATUS HAS BEEN ATTACHED IN OTHER TAB. KINDLY CONSIDER OUR APPLICATION AND ALLOW FURTHER EXTENSION TILL 31-12-2026. THANKING YOU YOURS FAITHFULLY,”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Jupiter Complex’s extension records on MahaRERA (P99000013313), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Jupiter Complex
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000013313
- Status
- Registered and active
- Builder
- M/s. JEM Developers
- Location
- Betegoan, Palghar · 401501
- Project type
- Residential / Group Housing
- Registered on
- 22 Sep 2017
- Completion date at registration
- May 2019
- Latest completion date
- April 2027
- Delay so far
- 91 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 174
- Towers
- 2
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Jupiter Complex, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Jupiter Complex Bldg No 1 | 100% | 100% | 100% | 80% |
| Jupiter Complex Bldg No 2 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jupiter Complex every month.
Jupiter Complex: buildings, flats and land, as filed on MahaRERA
- Buildings: Jupiter Complex Bldg No 1 (5 floors) · Jupiter Complex Bldg No 2 (6 floors)
- Land: 4,103 sq m (about 1.0 acres) · sanctioned built-up 7,814 sq m · recreational space 410 sq m
The builder’s record and reviews
JEM Developeres AND Builderes (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 85 months late). 2 complaints on MahaRERA across 1 project.
Read Google reviews of Jupiter Complex →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Jupiter Complex: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Jupiter Complex
What is the possession date of Jupiter Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Jupiter Complex in Betegoan, Palghar is 30 April 2027 — 91 months later than 31 May 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Jupiter Complex?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Jupiter Complex's builder has filed on MahaRERA, the official one, is 30 April 2027, already 91 months later than the 31 May 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Jupiter Complex extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Jupiter Complex's builder applied to MahaRERA to extend the completion date 4 times: to 30 May 2020, giving the reason "DUE TO CHANGE IN ENVIRONMENTAL NORMS BY COMPETENT AUTHORITY."; to 30 May 2022, giving the reason "Dear Sir, We the undersigned elected member of Association of Allottees of the Project upon the request received by M/s Jem Developers, Promoter of the Project – Jupiter Complex having MahaRERA No. P99000013313 situated at S.No./Plot bearing No. 11,51,16,118 at betegoan, Palghar, PIN:401501 request your kind office the fact that: 1. The Project-Jupiter Complex has two buildings- building No 1 and Building No. 2. As per the Architect Certificate received by us Building No. 2 is physically 100% Completed and applied for Fire and other related NOC. And the work of Building No. 1 is going on bu…"; to 30 September 2024, giving the reason "Dear Sir, Due to Corona virus pandemic, the project work has been affected and therefore extra time till 30-09-2024 is required to complete the project."; to 31 December 2026, giving the reason "DEAR SIR, CIVIL WORK OF BOTH BUILDING HAS BEEN COMPLETED AS PER ARCHITET'S LETTER ATTACHED. DUE TO SOME NORMS CHANGES AND CHANGE IN LAYOUT WE ARE GETTING DELAY IN OBTAINING O.C. DETAILED REASON AND WORK STATUS HAS BEEN ATTACHED IN OTHER TAB. KINDLY CONSIDER OUR APPLICATION AND ALLOW FURTHER EXTENSION TILL 31-12-2026. THANKING YOU YOURS FAITHFULLY,". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Jupiter Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Jupiter Complex in Betegoan, Palghar is P99000013313.
Is Jupiter Complex registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Jupiter Complex is registered as P99000013313 and its status is "Registered and active".
What is the construction status of Jupiter Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), Jupiter Complex's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Jupiter Complex have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Jupiter Complex safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Jupiter Complex is registered on MahaRERA as P99000013313, its completion date has moved 91 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Jupiter Complex's possession date changes?
The latest dates are on Jupiter Complex's MahaRERA page (P99000013313). GharKundli's Kundli Watch sends a free WhatsApp update on Jupiter Complex every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Jupiter Complex have?
According to GharKundli's check of MahaRERA records (updated October 2026), Jupiter Complex has 2 buildings filed: Jupiter Complex Bldg No 1 with 5 floors; Jupiter Complex Bldg No 2 with 6 floors.
How big is the land of Jupiter Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), Jupiter Complex stands on 4,103 sq m of land (about 1.0 acres), with 7,814 sq m of sanctioned built-up area and 410 sq m of recreational open space.
What is the track record of Jupiter Complex's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), JEM Developeres AND Builderes (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 85 months late). 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Jupiter Complex?
Google Maps has reviews of Jupiter Complex written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Jupiter Complex?
Jupiter Complex by M/s. JEM Developers is in Betegoan, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000013313, per GharKundli's check of MahaRERA records.
How many homes are in Jupiter Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), Jupiter Complex has 174 homes in 2 towers registered on MahaRERA.
When was Jupiter Complex registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Jupiter Complex was registered on MahaRERA on 22 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Jupiter Complex?
No court cases are listed for Jupiter Complex on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Jupiter Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/s. JEM Developers.
Check it yourself on MahaRERA
- How to check the possession date of Jupiter Complex
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Palghar
- Sunshine Complex
- Elite Residency
- Rubicon Shinde Heritage
- V SQUARE ARCADE
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.