PLATINUM
by BRIGHT DEVELOPERS · Chikhali, Pune
Possession date of PLATINUM: 30 September 2024, moved from 30 September 2022 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100012147. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (September 2024) has passed.
What do you want to know about PLATINUM?
How the possession date of PLATINUM has moved
30 September 2022
Completion date given when the project was registered
30 September 2024
Extended at the builder's request (MahaRERA application EXT52100013117)
Reason the builder gave MahaRERA:
“The original proposed date of completion was 30/09/2021, but we could not complete our project on time, because of Covid -19 and lockdown situation in the entire city, which was going on and off for 2 years in a row. The construction sector…” Read the full reason
“The original proposed date of completion was 30/09/2021, but we could not complete our project on time, because of Covid -19 and lockdown situation in the entire city, which was going on and off for 2 years in a row. The construction sector had been heavily hampered due to such situation. Lack of workers and due to shortage of supply of materials we could not complete our project on time. We hereby request you to kindly extend out project registration for a minimum period of 2 year.”
Source: PLATINUM’s extension records on MahaRERA (P52100012147), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PLATINUM
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100012147
- Status
- Lapsed (registration period ended)
- Builder
- BRIGHT DEVELOPERS
- Location
- Chikhali, Pune · 411062
- Project type
- Others
- Registered on
- 1 Sep 2017
- Completion date at registration
- September 2022
- Latest completion date
- September 2024
- Delay so far
- 24 months
- Homes
- 59
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of PLATINUM, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PLATINUM B | 100% | 100% | 70% | 0% |
| PLATINUM A | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PLATINUM every month.
PLATINUM: buildings, flats and land, as filed on MahaRERA
- Buildings: PLATINUM B (16 floors) · PLATINUM A (6 floors)
- Land: 3,400 sq m (about 0.8 acres) · sanctioned built-up 2,702 sq m · recreational space 343 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PLATINUM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PLATINUM: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PLATINUM
What is the possession date of PLATINUM?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PLATINUM in Chikhali, Pune is 30 September 2024 — 24 months later than 30 September 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for PLATINUM?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PLATINUM's builder has filed on MahaRERA, the official one, is 30 September 2024, already 24 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PLATINUM extended?
According to GharKundli's check of MahaRERA records (updated November 2026), PLATINUM's builder applied to MahaRERA to extend the completion date once: to 30 September 2024, giving the reason "The original proposed date of completion was 30/09/2021, but we could not complete our project on time, because of Covid -19 and lockdown situation in the entire city, which was going on and off for 2 years in a row. The construction sector had been heavily hampered due to such situation. Lack of workers and due to shortage of supply of materials we could not complete our project on time. We hereby request you to kindly extend out project registration for a minimum period of 2 year.".
What is the RERA number of PLATINUM?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PLATINUM in Chikhali, Pune is P52100012147.
Is PLATINUM registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PLATINUM is registered as P52100012147 and its status is "Lapsed (registration period ended)".
What is the construction status of PLATINUM?
According to GharKundli's check of MahaRERA records (updated November 2026), PLATINUM's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does PLATINUM have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is PLATINUM safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PLATINUM is registered on MahaRERA as P52100012147, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PLATINUM's possession date changes?
The latest dates are on PLATINUM's MahaRERA page (P52100012147). GharKundli's Kundli Watch sends a free WhatsApp update on PLATINUM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PLATINUM have?
According to GharKundli's check of MahaRERA records (updated November 2026), PLATINUM has 2 buildings filed: PLATINUM B with 16 floors; PLATINUM A with 6 floors.
How big is the land of PLATINUM?
According to GharKundli's check of MahaRERA records (updated November 2026), PLATINUM stands on 3,400 sq m of land (about 0.8 acres), with 2,702 sq m of sanctioned built-up area and 343 sq m of recreational open space.
Where can I read reviews of PLATINUM?
Google Maps has reviews of PLATINUM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PLATINUM?
PLATINUM by BRIGHT DEVELOPERS is in Chikhali, Pune (pincode 411062), Maharashtra, and is registered on MahaRERA as P52100012147, per GharKundli's check of MahaRERA records.
How many homes are in PLATINUM?
According to GharKundli's check of MahaRERA records (updated November 2026), PLATINUM has 59 homes in 2 towers registered on MahaRERA.
When was PLATINUM registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PLATINUM was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on PLATINUM?
No court cases are listed for PLATINUM on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of PLATINUM?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BRIGHT DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PLATINUM
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 411062
- SIDDHI NEST A1 A2
- VSG LEGACY ONE
- SAI SUVARNA
- Abhiman Vishwa
- RAGHAV RESERVE
- Mahadev Park
- AKSHA VRUNDAVAN II
- 24KG GOLD RESIDENCY
Other projects by BRIGHT DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.