Sun-Srushti Greens

by SRUSHTI DEVELOPERS · Kiwale, PuneAlso near Dehu Road Cantt

Possession: Sun-Srushti Greens is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100009844. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Sun-Srushti Greens?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sun-Srushti Greens has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT52100008470)

    Reason the builder gave MahaRERA: “NATURAL CALAMITIES”
  3. 1 August 2024

    Extended at the builder's request (MahaRERA application EXT52100012492)

    Reason the builder gave MahaRERA: “Non availability of raw material and labor due to covid 19 pandemic”

Source: Sun-Srushti Greens’s extension records on MahaRERA (P52100009844), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sun-Srushti Greens

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100009844
Status
Completed
Builder
SRUSHTI DEVELOPERS
Location
Kiwale, Pune · 412101
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
December 2019
Latest completion date
August 2024
Delay so far
56 months
Homes
21
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of Sun-Srushti Greens, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SUN-SRUSHTI GREENS100%80%80%80%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sun-Srushti Greens every month.

Sun-Srushti Greens: buildings, flats and land, as filed on MahaRERA

  • Buildings: SUN-SRUSHTI GREENS (5 floors)
  • Land: 797 sq m (about 0.2 acres) · sanctioned built-up 1,545 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sun-Srushti Greens →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sun-Srushti Greens: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sun-Srushti Greens

What is the possession date of Sun-Srushti Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sun-Srushti Greens in Kiwale, Pune is 1 August 2024 — 56 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Sun-Srushti Greens?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sun-Srushti Greens's builder has filed on MahaRERA, the official one, is 1 August 2024, already 56 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sun-Srushti Greens extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Srushti Greens's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "NATURAL CALAMITIES"; to 1 August 2024, giving the reason "Non availability of raw material and labor due to covid 19 pandemic".

What is the RERA number of Sun-Srushti Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sun-Srushti Greens in Kiwale, Pune is P52100009844.

Is Sun-Srushti Greens registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Srushti Greens is registered as P52100009844 and its status is "Completed".

What is the construction status of Sun-Srushti Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Srushti Greens's status on MahaRERA is "Completed". As filed by the builder, slab work on SUN-SRUSHTI GREENS is 80% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Sun-Srushti Greens have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Sun-Srushti Greens safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Srushti Greens is registered on MahaRERA as P52100009844, its MahaRERA status is "Completed", its completion date has moved 56 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sun-Srushti Greens's possession date changes?

The latest dates are on Sun-Srushti Greens's MahaRERA page (P52100009844). GharKundli's Kundli Watch sends a free WhatsApp update on Sun-Srushti Greens every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sun-Srushti Greens have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Srushti Greens has one building filed: SUN-SRUSHTI GREENS with 5 floors.

How big is the land of Sun-Srushti Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Srushti Greens stands on 797 sq m of land (about 0.2 acres), with 1,545 sq m of sanctioned built-up area.

Where can I read reviews of Sun-Srushti Greens?

Google Maps has reviews of Sun-Srushti Greens written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sun-Srushti Greens?

Sun-Srushti Greens by SRUSHTI DEVELOPERS is in Kiwale, Pune (pincode 412101), near Dehu Road Cantt, Maharashtra, and is registered on MahaRERA as P52100009844, per GharKundli's check of MahaRERA records.

How many homes are in Sun-Srushti Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Srushti Greens has 21 homes in 1 tower registered on MahaRERA.

When was Sun-Srushti Greens registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Srushti Greens was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Sun-Srushti Greens?

No court cases are listed for Sun-Srushti Greens on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sun-Srushti Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SRUSHTI DEVELOPERS, which has 8 other projects registered on MahaRERA.