GOKUL NAGAR

by FIVESTAR REALTORS · Virar, Palghar

Possession date of GOKUL NAGAR: 30 April 2027, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000009505, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about GOKUL NAGAR?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GOKUL NAGAR has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT99000028045)

    Reason the builder gave MahaRERA:
    “Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a s…” Read the full reason“Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these mat…”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GOKUL NAGAR’s extension records on MahaRERA (P99000009505), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GOKUL NAGAR

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000009505
Status
Registered and active
Builder
FIVESTAR REALTORS
Location
Virar, Palghar · 401501
Project type
Mixed
Registered on
22 Aug 2017
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
70
Towers
4
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of GOKUL NAGAR, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 3 A AND B WING100%100%90%50%
BUILDING NO 2 A WING100%100%45%20%
BUILDING NO 1 A WING10%0%0%0%
BUILDING NO 1 A WING10%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOKUL NAGAR every month.

GOKUL NAGAR: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 3 A AND B WING (5 floors) · BUILDING NO 2 A WING (5 floors) · BUILDING NO 1 A WING (5 floors) · BUILDING NO 1 A WING (5 floors)
  • Land: 6,180 sq m (about 1.5 acres) · sanctioned built-up 5,005 sq m · recreational space 4,755 sq m
  • Boundaries filed include: BOISAR TARAPUR MAIN ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GOKUL NAGAR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GOKUL NAGAR: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GOKUL NAGAR

What is the possession date of GOKUL NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GOKUL NAGAR in Virar, Palghar is 30 April 2027 — 24 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GOKUL NAGAR?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GOKUL NAGAR's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GOKUL NAGAR extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GOKUL NAGAR's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these mat…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of GOKUL NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GOKUL NAGAR in Virar, Palghar is P99000009505.

Is GOKUL NAGAR registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOKUL NAGAR is registered as P99000009505 and its status is "Registered and active".

What is the construction status of GOKUL NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), GOKUL NAGAR's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does GOKUL NAGAR have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is GOKUL NAGAR safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GOKUL NAGAR is registered on MahaRERA as P99000009505, its completion date has moved 24 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GOKUL NAGAR's possession date changes?

The latest dates are on GOKUL NAGAR's MahaRERA page (P99000009505). GharKundli's Kundli Watch sends a free WhatsApp update on GOKUL NAGAR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GOKUL NAGAR have?

According to GharKundli's check of MahaRERA records (updated October 2026), GOKUL NAGAR has 4 buildings filed: BUILDING NO 3 A AND B WING with 5 floors; BUILDING NO 2 A WING with 5 floors; BUILDING NO 1 A WING with 5 floors; BUILDING NO 1 A WING with 5 floors.

How big is the land of GOKUL NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), GOKUL NAGAR stands on 6,180 sq m of land (about 1.5 acres), with 5,005 sq m of sanctioned built-up area and 4,755 sq m of recreational open space.

Where can I read reviews of GOKUL NAGAR?

Google Maps has reviews of GOKUL NAGAR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GOKUL NAGAR?

GOKUL NAGAR by FIVESTAR REALTORS is in Virar, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000009505, per GharKundli's check of MahaRERA records. Its boundaries filed there include BOISAR TARAPUR MAIN ROAD.

How many homes are in GOKUL NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), GOKUL NAGAR has 70 homes in 4 towers registered on MahaRERA.

When was GOKUL NAGAR registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOKUL NAGAR was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on GOKUL NAGAR?

No court cases are listed for GOKUL NAGAR on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of GOKUL NAGAR?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is FIVESTAR REALTORS.

All projects with possession due in 2027 in Palghar →

Other projects in Virar

All 127 projects in Boisar (401501) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.