HARIDHAM

by V M HOUSING · Virar, Palghar

Possession date of HARIDHAM: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000055379, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about HARIDHAM?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HARIDHAM has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: HARIDHAM’s extension records on MahaRERA (P99000055379), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HARIDHAM

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000055379
Status
Registered and active
Builder
V M HOUSING
Location
Virar, Palghar · 401303
Project type
Residential / Group Housing
Registered on
22 Mar 2024
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
170
Sold or booked
72%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of HARIDHAM, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HARIDHAM100%100%75%75%

Commencement certificate (CC), as filed on MahaRERA

  • HARIDHAM: covers 17 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HARIDHAM every month.

HARIDHAM: buildings, flats and land, as filed on MahaRERA

  • Buildings: HARIDHAM (18 floors, 170 units)
  • Land: 2,301 sq m (about 0.6 acres) · sanctioned built-up 9,776 sq m

The builder’s record and reviews

V Housing (a group of 6 linked companies) has 7 projects on MahaRERA since 2024, this one included. Of the 7 GharKundli has checked: 7 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of HARIDHAM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HARIDHAM: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HARIDHAM

What is the possession date of HARIDHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HARIDHAM in Virar, Palghar is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for HARIDHAM?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HARIDHAM's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of HARIDHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HARIDHAM in Virar, Palghar is P99000055379.

Is HARIDHAM registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HARIDHAM is registered as P99000055379 and its status is "Registered and active".

What is the construction status of HARIDHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), HARIDHAM's status on MahaRERA is "Registered and active". As filed by the builder, slab work on HARIDHAM is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does HARIDHAM have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is HARIDHAM safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), HARIDHAM is registered on MahaRERA as P99000055379, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HARIDHAM's possession date changes?

The latest dates are on HARIDHAM's MahaRERA page (P99000055379). GharKundli's Kundli Watch sends a free WhatsApp update on HARIDHAM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HARIDHAM have?

According to GharKundli's check of MahaRERA records (updated October 2026), HARIDHAM has one building filed: HARIDHAM with 18 floors and 170 units.

How big is the land of HARIDHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), HARIDHAM stands on 2,301 sq m of land (about 0.6 acres), with 9,776 sq m of sanctioned built-up area.

What is the track record of HARIDHAM's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), V Housing (a group of 6 linked companies) has 7 projects on MahaRERA since 2024, this one included. Of the 7 GharKundli has checked: 7 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of HARIDHAM?

Google Maps has reviews of HARIDHAM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HARIDHAM?

HARIDHAM by V M HOUSING is in Virar, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000055379, per GharKundli's check of MahaRERA records.

How many homes are in HARIDHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), HARIDHAM has 170 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.

When was HARIDHAM registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HARIDHAM was registered on MahaRERA on 22 March 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on HARIDHAM?

No court cases are listed for HARIDHAM on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of HARIDHAM?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is V M HOUSING.

All projects with possession due in 2028 in Palghar →

Other projects in pincode 401303

All 210 projects in Virar West (401303) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.