Earth Residency

by Earth Builder & Developers · MHADA Lokhandwala Complex, Palghar 401404

What’s in the report? →

Possession: Earth Residency (MahaRERA P99000007170) is marked completed on MahaRERA. It has 72 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000007170. Status: Completed.

Source: MahaRERA website — records for P99000007170, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Earth Residency?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Earth Residency has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 30 March 2020

    Extended at the builder's request (MahaRERA application EXT99000001656)

    Reason the builder gave MahaRERA: “The project is almost complete on all aspects. We are completing the OC formalities thus require extension for completion certificate.”
  3. 30 September 2020

    Revised completion date on MahaRERA

Source: Earth Residency’s extension records on MahaRERA (P99000007170), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Earth Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000007170
Status
Completed
Builder
Earth Builder & Developers
Location
MHADA Lokhandwala Complex, Palghar · 401404
Project type
Others
Registered on
17 Aug 2017
Completion date at registration
March 2019
Latest completion date
September 2020
Delay so far
18 months
Homes
72
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Earth Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Earth Residency100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Earth Residency every 1–2 months.

Earth Residency: buildings, flats and land, as filed on MahaRERA

  • Buildings: Earth Residency (3 floors)
  • Land: 3,005 sq m (about 0.7 acres) · sanctioned built-up 2,66,232 sq m
  • Land, as filed: S N 74 / 1
  • Map: Get directions

The builder’s record and reviews

Earth Builder & Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Earth Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Earth Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Earth Residency

What is the possession date of Earth Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Earth Residency in MHADA Lokhandwala Complex, Palghar is 30 September 2020 — 18 months later than 31 March 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Earth Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Earth Residency's builder has filed on MahaRERA, the official one, is 30 September 2020, already 18 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Earth Residency extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency's builder applied to MahaRERA to extend the completion date once: to 30 March 2020, giving the reason "The project is almost complete on all aspects. We are completing the OC formalities thus require extension for completion certificate.".

What is the RERA number of Earth Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Earth Residency in MHADA Lokhandwala Complex, Palghar is P99000007170.

Is Earth Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency is registered as P99000007170 and its status is "Completed".

What is the current construction status of Earth Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency's status on MahaRERA is "Completed". As filed by the builder, slab work on Earth Residency is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Earth Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Earth Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency is registered on MahaRERA as P99000007170, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Earth Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Earth Residency?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Earth Residency: gharkundli.com/tools/property-cost-calculator

Has Earth Residency received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Earth Residency completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency is marked completed on MahaRERA, and the completion date filed there is 30 September 2020. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Earth Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Earth Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Earth Residency's possession date changes?

The latest dates are on Earth Residency's MahaRERA page (P99000007170). GharKundli's Kundli Watch sends a free WhatsApp update on Earth Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Earth Residency have?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency has one building filed: Earth Residency with 3 floors.

How big is the land of Earth Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency stands on 3,005 sq m of land (about 0.7 acres), with 2,66,232 sq m of sanctioned built-up area.

What is the track record of Earth Residency's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Builder & Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Earth Residency?

Google Maps has reviews of Earth Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Earth Residency?

Earth Residency by Earth Builder & Developers is in MHADA Lokhandwala Complex, Palghar, pincode 401404, Maharashtra, and is registered on MahaRERA as P99000007170, per GharKundli's check of MahaRERA records. Its land is filed as S N 74 / 1. GharKundli lists all 621 MahaRERA projects in Palghar (401404).

How many flats are in Earth Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency has 72 homes in 1 tower registered on MahaRERA.

When was Earth Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Earth Residency was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Does Earth Residency have any legal issues or court cases?

No court cases are listed for Earth Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Earth Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Earth Builder & Developers, which has 1 other project registered on MahaRERA.

Other projects in Palghar

All 621 projects in Palghar (401404) →

Other projects by Earth Builder & Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.