SIGNATURE 28
by Jagrutsara Structures LLP (Sara) · Chakan, Pune
Possession: SIGNATURE 28 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100015061. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SIGNATURE 28?
How the possession date of SIGNATURE 28 has moved
30 December 2020
Completion date given when the project was registered
30 December 2021
Extended at the builder's request (MahaRERA application EXT52100006152)
Reason the builder gave MahaRERA: “Due to COVID 2019 Situation we will not able to complete said project in Given timeline, so we are requesting 12 months Extension for the said project”
31 May 2023
Extended at the builder's request (MahaRERA application EXT52100012643)
Reason the builder gave MahaRERA: “The Project near to completion we also have applied for Completion Certificate/ Occupation certificate... due to some technical issues.. it is getting delayed so we required extension till 31 may 2023. resolution also attached”
Source: SIGNATURE 28’s extension records on MahaRERA (P52100015061), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SIGNATURE 28
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100015061
- Status
- Completed
- Builder
- Jagrutsara Structures LLP
- Location
- Chakan, Pune · 410501
- Project type
- Residential / Group Housing
- Registered on
- 22 Jan 2018
- Completion date at registration
- December 2020
- Latest completion date
- May 2023
- Delay so far
- 29 months
- Homes
- 31
- Towers
- 6
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 24
Construction progress of SIGNATURE 28, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING 1 | 100% | 100% | 100% | 100% |
| BUILDING 2 | 100% | 100% | 100% | 100% |
| BUILDING 3 | 100% | 100% | 100% | 100% |
| BUILDING 4 | 100% | 100% | 100% | 100% |
| BUILDING 5 | 100% | 100% | 100% | 100% |
| BUILDING 6 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIGNATURE 28 every month.
SIGNATURE 28: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING 1 (2 floors) · BUILDING 2 (2 floors) · BUILDING 3 (2 floors) · BUILDING 4 (2 floors) · BUILDING 5 (2 floors) · BUILDING 6 (2 floors)
- Land: 5,220 sq m (about 1.3 acres) · sanctioned built-up 2,959 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sara Properties (a group of 9 linked companies) has 50 projects on MahaRERA since 2018, this one included. Of the 28 GharKundli has checked: 10 finished, 7 within the promised date and 3 needed more time (typically 11 months); 17 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of SIGNATURE 28 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SIGNATURE 28: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SIGNATURE 28
What is the possession date of SIGNATURE 28?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SIGNATURE 28 in Chakan, Pune is 31 May 2023 — 29 months later than 30 December 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SIGNATURE 28?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SIGNATURE 28's builder has filed on MahaRERA, the official one, is 31 May 2023, already 29 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SIGNATURE 28 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SIGNATURE 28's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2021, giving the reason "Due to COVID 2019 Situation we will not able to complete said project in Given timeline, so we are requesting 12 months Extension for the said project"; to 31 May 2023, giving the reason "The Project near to completion we also have applied for Completion Certificate/ Occupation certificate... due to some technical issues.. it is getting delayed so we required extension till 31 may 2023. resolution also attached".
What is the RERA number of SIGNATURE 28?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SIGNATURE 28 in Chakan, Pune is P52100015061.
Is SIGNATURE 28 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SIGNATURE 28 is registered as P52100015061 and its status is "Completed".
What is the construction status of SIGNATURE 28?
According to GharKundli's check of MahaRERA records (updated November 2026), SIGNATURE 28's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does SIGNATURE 28 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SIGNATURE 28 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SIGNATURE 28 is registered on MahaRERA as P52100015061, its MahaRERA status is "Completed", its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SIGNATURE 28's possession date changes?
The latest dates are on SIGNATURE 28's MahaRERA page (P52100015061). GharKundli's Kundli Watch sends a free WhatsApp update on SIGNATURE 28 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SIGNATURE 28 have?
According to GharKundli's check of MahaRERA records (updated November 2026), SIGNATURE 28 has 6 buildings filed: BUILDING 1 with 2 floors; BUILDING 2 with 2 floors; BUILDING 3 with 2 floors; BUILDING 4 with 2 floors; BUILDING 5 with 2 floors; BUILDING 6 with 2 floors.
How big is the land of SIGNATURE 28?
According to GharKundli's check of MahaRERA records (updated November 2026), SIGNATURE 28 stands on 5,220 sq m of land (about 1.3 acres), with 2,959 sq m of sanctioned built-up area.
What is the track record of SIGNATURE 28's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sara Properties (a group of 9 linked companies) has 50 projects on MahaRERA since 2018, this one included. Of the 28 GharKundli has checked: 10 finished, 7 within the promised date and 3 needed more time (typically 11 months); 17 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SIGNATURE 28?
Google Maps has reviews of SIGNATURE 28 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SIGNATURE 28?
SIGNATURE 28 by Jagrutsara Structures LLP (Sara) is in Chakan, Pune (pincode 410501), Maharashtra, and is registered on MahaRERA as P52100015061, per GharKundli's check of MahaRERA records.
How many homes are in SIGNATURE 28?
According to GharKundli's check of MahaRERA records (updated November 2026), SIGNATURE 28 has 31 homes in 6 towers registered on MahaRERA.
When was SIGNATURE 28 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SIGNATURE 28 was registered on MahaRERA on 22 January 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on SIGNATURE 28?
No court cases are listed for SIGNATURE 28 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SIGNATURE 28?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Jagrutsara Structures LLP, the company Sara files this project under, which has 24 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SIGNATURE 28
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 410501
- SIDDHIVINAYAK DREAM HOMES C,D WING
- Mungase Towers
- SARA CITY PLOT E 1
- SARA NILAAY
- Vighnaharta
- Imperial Plaza
- RAJ APOORVAM
- Tathastu Homes
Other projects by Jagrutsara Structures LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.