MAHAVIR RESIDENCY

by MAHAVIR CONSTRUCTIONS · Virar West, Palghar

Possession date of MAHAVIR RESIDENCY: 30 April 2027, moved from 28 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000012246, and currently active. Its completion date has moved from June 2021 to April 2027: 66 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MAHAVIR RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MAHAVIR RESIDENCY has moved

  1. 28 June 2021

    Completion date given when the project was registered

  2. 25 April 2022

    Extended at the builder's request (MahaRERA application EXT99000009414)

    Reason the builder gave MahaRERA: “NOT SUPPLY IN HDIL LAYOUT, WATER SULLY, MSEB METER SUPPLY, ENVIRONMENT, INFRASTRUCTURE, ROAD OR FOOTPATH.”
  3. 23 October 2023

    Extended at the builder's request (MahaRERA application EXT99000012771)

    Reason the builder gave MahaRERA: “MSEB METER SUPPLY, WATER CONNECTION, ENVIRONMENT CLEARANCE, OCCUPATION CERTIFICATE.”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT99000017890)

    Reason the builder gave MahaRERA: “Mseb Meter Connection, Water Supply , Environment Clearance, Occupation Certificate.”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MAHAVIR RESIDENCY’s extension records on MahaRERA (P99000012246), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MAHAVIR RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000012246
Status
Registered and active
Builder
MAHAVIR CONSTRUCTIONS
Location
Virar West, Palghar · 401303
Project type
Others
Registered on
1 Sep 2017
Completion date at registration
June 2021
Latest completion date
April 2027
Delay so far
66 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
58
Sold or booked
98%
Towers
1
Complaints on MahaRERA
4
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of MAHAVIR RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MAHAVIR RESIDENCY BLDG NO 23100%100%100%92%

Commencement certificate (CC), as filed on MahaRERA

  • MAHAVIR RESIDENCY BLDG NO 23: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAHAVIR RESIDENCY every month.

MAHAVIR RESIDENCY: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MAHAVIR RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MAHAVIR RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MAHAVIR RESIDENCY

What is the possession date of MAHAVIR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MAHAVIR RESIDENCY in Virar West, Palghar is 30 April 2027 — 66 months later than 28 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MAHAVIR RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MAHAVIR RESIDENCY's builder has filed on MahaRERA, the official one, is 30 April 2027, already 66 months later than the 28 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MAHAVIR RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHAVIR RESIDENCY's builder applied to MahaRERA to extend the completion date 3 times: to 25 April 2022, giving the reason "NOT SUPPLY IN HDIL LAYOUT, WATER SULLY, MSEB METER SUPPLY, ENVIRONMENT, INFRASTRUCTURE, ROAD OR FOOTPATH."; to 23 October 2023, giving the reason "MSEB METER SUPPLY, WATER CONNECTION, ENVIRONMENT CLEARANCE, OCCUPATION CERTIFICATE."; to 31 December 2026, giving the reason "Mseb Meter Connection, Water Supply , Environment Clearance, Occupation Certificate.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MAHAVIR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MAHAVIR RESIDENCY in Virar West, Palghar is P99000012246.

Is MAHAVIR RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHAVIR RESIDENCY is registered as P99000012246 and its status is "Registered and active".

What is the construction status of MAHAVIR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHAVIR RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MAHAVIR RESIDENCY BLDG NO 23 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does MAHAVIR RESIDENCY have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MAHAVIR RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHAVIR RESIDENCY is registered on MahaRERA as P99000012246, its completion date has moved 66 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MAHAVIR RESIDENCY's possession date changes?

The latest dates are on MAHAVIR RESIDENCY's MahaRERA page (P99000012246). GharKundli's Kundli Watch sends a free WhatsApp update on MAHAVIR RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MAHAVIR RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHAVIR RESIDENCY has one building filed: MAHAVIR RESIDENCY BLDG NO 23 with 17 floors and 65 units.

How big is the land of MAHAVIR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHAVIR RESIDENCY stands on 670 sq m of land (about 0.2 acres), with 4,213 sq m of sanctioned built-up area.

Where can I read reviews of MAHAVIR RESIDENCY?

Google Maps has reviews of MAHAVIR RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MAHAVIR RESIDENCY?

MAHAVIR RESIDENCY by MAHAVIR CONSTRUCTIONS is in Virar West, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000012246, per GharKundli's check of MahaRERA records. Its boundaries filed there include GARDEN.

How many homes are in MAHAVIR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHAVIR RESIDENCY has 58 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.

When was MAHAVIR RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAHAVIR RESIDENCY was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MAHAVIR RESIDENCY?

No court cases are listed for MAHAVIR RESIDENCY on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of MAHAVIR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAHAVIR CONSTRUCTIONS.

All projects with possession due in 2027 in Palghar →

Other projects in pincode 401303

All 187 projects in Virar West (401303) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.