NIRMITI HEIGHTS

by SHREE NIRMITI DEVELOPERS · Chikhali, PuneAlso near Rupeenagar, Chinchwad East, Akurdi

Possession date of NIRMITI HEIGHTS: 31 March 2024, moved from 10 May 2022 (22 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100018140. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2024) has passed.

What do you want to know about NIRMITI HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NIRMITI HEIGHTS has moved

  1. 10 May 2022

    Completion date given when the project was registered

  2. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52100013672)

    Reason the builder gave MahaRERA:
    “Contractor Issue We as promoter/ developer provide information, that the initially we appointed a particular contractor for the work of RCC work, Brick work, Plaster work and Water proofing (i.e. Whole work has been given to single contract…” Read the full reason“Contractor Issue We as promoter/ developer provide information, that the initially we appointed a particular contractor for the work of RCC work, Brick work, Plaster work and Water proofing (i.e. Whole work has been given to single contractor) and same has been verified through their initial agreement. During the course of RCC work, we found that the said contractor has not followed the guidelines such as follows. • Quality of Works was not in line of as expected • Safety Norms were not followed • Strength of Labour Force were inadequate to the work due to which time duration has been exten…”

Source: NIRMITI HEIGHTS’s extension records on MahaRERA (P52100018140), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NIRMITI HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100018140
Status
Lapsed (registration period ended)
Builder
SHREE NIRMITI DEVELOPERS
Location
Chikhali, Pune · 411062
Project type
Residential / Group Housing
Registered on
11 Oct 2018
Completion date at registration
May 2022
Latest completion date
March 2024
Delay so far
22 months
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of NIRMITI HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NIRMITI HEIGHTS0%20%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRMITI HEIGHTS every month.

NIRMITI HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: NIRMITI HEIGHTS (6 floors)
  • Land: 498 sq m (about 0.1 acres) · sanctioned built-up 423 sq m
  • Boundaries filed include: 9 M GOVT ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NIRMITI HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NIRMITI HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NIRMITI HEIGHTS

What is the possession date of NIRMITI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NIRMITI HEIGHTS in Chikhali, Pune is 31 March 2024 — 22 months later than 10 May 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for NIRMITI HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRMITI HEIGHTS's builder has filed on MahaRERA, the official one, is 31 March 2024, already 22 months later than the 10 May 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NIRMITI HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 March 2024, giving the reason "Contractor Issue We as promoter/ developer provide information, that the initially we appointed a particular contractor for the work of RCC work, Brick work, Plaster work and Water proofing (i.e. Whole work has been given to single contractor) and same has been verified through their initial agreement. During the course of RCC work, we found that the said contractor has not followed the guidelines such as follows. • Quality of Works was not in line of as expected • Safety Norms were not followed • Strength of Labour Force were inadequate to the work due to which time duration has been exten…".

What is the RERA number of NIRMITI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NIRMITI HEIGHTS in Chikhali, Pune is P52100018140.

Is NIRMITI HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI HEIGHTS is registered as P52100018140 and its status is "Lapsed (registration period ended)".

What is the construction status of NIRMITI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI HEIGHTS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NIRMITI HEIGHTS is 20% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does NIRMITI HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is NIRMITI HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI HEIGHTS is registered on MahaRERA as P52100018140, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 22 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NIRMITI HEIGHTS's possession date changes?

The latest dates are on NIRMITI HEIGHTS's MahaRERA page (P52100018140). GharKundli's Kundli Watch sends a free WhatsApp update on NIRMITI HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NIRMITI HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI HEIGHTS has one building filed: NIRMITI HEIGHTS with 6 floors.

How big is the land of NIRMITI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI HEIGHTS stands on 498 sq m of land (about 0.1 acres), with 423 sq m of sanctioned built-up area.

Where can I read reviews of NIRMITI HEIGHTS?

Google Maps has reviews of NIRMITI HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NIRMITI HEIGHTS?

NIRMITI HEIGHTS by SHREE NIRMITI DEVELOPERS is in Chikhali, Pune (pincode 411062), near Rupeenagar, Chinchwad East, Akurdi, Maharashtra, and is registered on MahaRERA as P52100018140, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 M GOVT ROAD.

How many homes are in NIRMITI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI HEIGHTS has 12 homes in 1 tower registered on MahaRERA.

When was NIRMITI HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI HEIGHTS was registered on MahaRERA on 11 October 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on NIRMITI HEIGHTS?

No court cases are listed for NIRMITI HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NIRMITI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE NIRMITI DEVELOPERS.

Other projects in pincode 411062

All 114 projects in Chikhali (411062) →