by SHREYA BUILDERS · bhusari colony, PuneAlso near Wakad, Baner, Kiwale

Possession: silver hills is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100020917. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about silver hills?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of silver hills has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52100010998)

    Reason the builder gave MahaRERA:
    “I Promoter of the project "Silver Hills" do hereby declare that we have completed and sold 1st 4 floors of project "Silver hills" before RERA came into force. We received further sanctions for the 5th, 6th, and 7th floors from the concerned…” Read the full reason“I Promoter of the project "Silver Hills" do hereby declare that we have completed and sold 1st 4 floors of project "Silver hills" before RERA came into force. We received further sanctions for the 5th, 6th, and 7th floors from the concerned municipal corporation on 27.12.2018 vide cc no cc/2991/18. Post which, we registered the project under RERA in the year 2019 for building upper floors (5th, 6th, and 7th). However, we were not able to start the construction in the year 2019 as the Issuance of AVIATION NOC was delayed by the concerned authority and which is mandatory for the project. The…”

Source: silver hills’s extension records on MahaRERA (P52100020917), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on silver hills

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100020917
Status
Completed
Builder
SHREYA BUILDERS
Location
bhusari colony, Pune · 411038
Project type
Residential / Group Housing
Registered on
23 May 2019
Completion date at registration
December 2021
Latest completion date
December 2024
Delay so far
36 months
Homes
8
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of silver hills, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Silver Hills100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on silver hills every month.

silver hills: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of silver hills →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

silver hills: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about silver hills

What is the possession date of silver hills?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for silver hills in bhusari colony, Pune is 31 December 2024 — 36 months later than 30 December 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for silver hills?

Builders and listing sites often quote an earlier "target" date for handover. The completion date silver hills's builder has filed on MahaRERA, the official one, is 31 December 2024, already 36 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of silver hills extended?

According to GharKundli's check of MahaRERA records (updated November 2026), silver hills's builder applied to MahaRERA to extend the completion date once: to 31 December 2024, giving the reason "I Promoter of the project "Silver Hills" do hereby declare that we have completed and sold 1st 4 floors of project "Silver hills" before RERA came into force. We received further sanctions for the 5th, 6th, and 7th floors from the concerned municipal corporation on 27.12.2018 vide cc no cc/2991/18. Post which, we registered the project under RERA in the year 2019 for building upper floors (5th, 6th, and 7th). However, we were not able to start the construction in the year 2019 as the Issuance of AVIATION NOC was delayed by the concerned authority and which is mandatory for the project. The…".

What is the RERA number of silver hills?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of silver hills in bhusari colony, Pune is P52100020917.

Is silver hills registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), silver hills is registered as P52100020917 and its status is "Completed".

What is the construction status of silver hills?

According to GharKundli's check of MahaRERA records (updated November 2026), silver hills's status on MahaRERA is "Completed". As filed by the builder, slab work on Silver Hills is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does silver hills have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is silver hills safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), silver hills is registered on MahaRERA as P52100020917, its MahaRERA status is "Completed", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if silver hills's possession date changes?

The latest dates are on silver hills's MahaRERA page (P52100020917). GharKundli's Kundli Watch sends a free WhatsApp update on silver hills every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does silver hills have?

According to GharKundli's check of MahaRERA records (updated November 2026), silver hills has one building filed: Silver Hills with 4 floors.

How big is the land of silver hills?

According to GharKundli's check of MahaRERA records (updated November 2026), silver hills stands on 823 sq m of land (about 0.2 acres), with 1,008 sq m of sanctioned built-up area.

Where can I read reviews of silver hills?

Google Maps has reviews of silver hills written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is silver hills?

silver hills by SHREYA BUILDERS is in bhusari colony, Pune (pincode 411038), near Wakad, Baner, Kiwale, Maharashtra, and is registered on MahaRERA as P52100020917, per GharKundli's check of MahaRERA records.

How many homes are in silver hills?

According to GharKundli's check of MahaRERA records (updated November 2026), silver hills has 8 homes in 1 tower registered on MahaRERA.

When was silver hills registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), silver hills was registered on MahaRERA on 23 May 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on silver hills?

No court cases are listed for silver hills on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of silver hills?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREYA BUILDERS.

Other projects in pincode 411038

All 318 projects in Kothrud (411038) →