Sukhwani Coloronic Phase II
by S. S. D. Construction · Ravet, PuneAlso near Dehu Road Cantt
Possession: Sukhwani Coloronic Phase II is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100019968. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Sukhwani Coloronic Phase II?
How the possession date of Sukhwani Coloronic Phase II has moved
30 September 2021
Completion date given when the project was registered
30 September 2022
Extended at the builder's request (MahaRERA application EXT52100010611)
Reason the builder gave MahaRERA:
“We hereby apply for extension of proposed date of completion of the following project Sukhwani Sepia Phase II registered with the regulatory authority vide project registration certificate bearing no. P52100019968 which expires on 30/09/202…” Read the full reason
“We hereby apply for extension of proposed date of completion of the following project Sukhwani Sepia Phase II registered with the regulatory authority vide project registration certificate bearing no. P52100019968 which expires on 30/09/2021. We request you to extend the period of RERA Registration by period of 12 months i.e. upto 30/09/2022. As on date of this application, the major work of one of the building in project is pending to be completed. Due to Covid-19 the project was slowly moving from past 1 year and as on date only a few of the construction activities can be carried out owin…”30 September 2023
Extended at the builder's request (MahaRERA application EXT52100016708)
Reason the builder gave MahaRERA:
“The Project got delayed due to the slow movement of the project as there were labour shortages and low cash flow during the Covid period resulting in a delay of the project. We have applied for completion of the Project and even received a…” Read the full reason
“The Project got delayed due to the slow movement of the project as there were labour shortages and low cash flow during the Covid period resulting in a delay of the project. We have applied for completion of the Project and even received a completion certificate for C Wing and will receive the completion certificate of B building in a month.”
Source: Sukhwani Coloronic Phase II’s extension records on MahaRERA (P52100019968), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sukhwani Coloronic Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Sukhwani Coloronic Phase - IIIP52100032196 · possession 30 Apr 2030
- MahaRERA registration
- P52100019968
- Status
- Completed
- Builder
- S. S. D. Construction
- Location
- Ravet, Pune · 412101
- Project type
- Residential / Group Housing
- Registered on
- 15 Mar 2019
- Completion date at registration
- September 2021
- Latest completion date
- September 2023
- Delay so far
- 24 months
- Homes
- 94
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Sukhwani Coloronic Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING B | 100% | 100% | 100% | 50% |
| BUILDING C | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sukhwani Coloronic Phase II every month.
Sukhwani Coloronic Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING B (13 floors) · BUILDING C (13 floors)
- Land: 2,587 sq m (about 0.6 acres) · sanctioned built-up 5,342 sq m
The builder’s record and reviews
S S D Construction has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.
Read Google reviews of Sukhwani Coloronic Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sukhwani Coloronic Phase II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sukhwani Coloronic Phase II
What is the possession date of Sukhwani Coloronic Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sukhwani Coloronic Phase II in Ravet, Pune is 30 September 2023 — 24 months later than 30 September 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Sukhwani Coloronic Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sukhwani Coloronic Phase II's builder has filed on MahaRERA, the official one, is 30 September 2023, already 24 months later than the 30 September 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sukhwani Coloronic Phase II extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Sukhwani Coloronic Phase II's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2022, giving the reason "We hereby apply for extension of proposed date of completion of the following project Sukhwani Sepia Phase II registered with the regulatory authority vide project registration certificate bearing no. P52100019968 which expires on 30/09/2021. We request you to extend the period of RERA Registration by period of 12 months i.e. upto 30/09/2022. As on date of this application, the major work of one of the building in project is pending to be completed. Due to Covid-19 the project was slowly moving from past 1 year and as on date only a few of the construction activities can be carried out owin…"; to 30 September 2023, giving the reason "The Project got delayed due to the slow movement of the project as there were labour shortages and low cash flow during the Covid period resulting in a delay of the project. We have applied for completion of the Project and even received a completion certificate for C Wing and will receive the completion certificate of B building in a month.".
What is the RERA number of Sukhwani Coloronic Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sukhwani Coloronic Phase II in Ravet, Pune is P52100019968.
Is Sukhwani Coloronic Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sukhwani Coloronic Phase II is registered as P52100019968 and its status is "Completed".
What is the construction status of Sukhwani Coloronic Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Sukhwani Coloronic Phase II's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Sukhwani Coloronic Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Sukhwani Coloronic Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Sukhwani Coloronic Phase II is registered on MahaRERA as P52100019968, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Sukhwani Coloronic Phase II have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Sukhwani Coloronic Phase - III (P52100032196, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.
How can I get updates if Sukhwani Coloronic Phase II's possession date changes?
The latest dates are on Sukhwani Coloronic Phase II's MahaRERA page (P52100019968). GharKundli's Kundli Watch sends a free WhatsApp update on Sukhwani Coloronic Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sukhwani Coloronic Phase II have?
According to GharKundli's check of MahaRERA records (updated November 2026), Sukhwani Coloronic Phase II has 2 buildings filed: BUILDING B with 13 floors; BUILDING C with 13 floors.
How big is the land of Sukhwani Coloronic Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Sukhwani Coloronic Phase II stands on 2,587 sq m of land (about 0.6 acres), with 5,342 sq m of sanctioned built-up area.
What is the track record of Sukhwani Coloronic Phase II's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), S S D Construction has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sukhwani Coloronic Phase II?
Google Maps has reviews of Sukhwani Coloronic Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sukhwani Coloronic Phase II?
Sukhwani Coloronic Phase II by S. S. D. Construction is in Ravet, Pune (pincode 412101), near Dehu Road Cantt, Maharashtra, and is registered on MahaRERA as P52100019968, per GharKundli's check of MahaRERA records.
How many homes are in Sukhwani Coloronic Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Sukhwani Coloronic Phase II has 94 homes in 2 towers registered on MahaRERA.
When was Sukhwani Coloronic Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sukhwani Coloronic Phase II was registered on MahaRERA on 15 March 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Sukhwani Coloronic Phase II?
No court cases are listed for Sukhwani Coloronic Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Sukhwani Coloronic Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is S. S. D. Construction, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sukhwani Coloronic Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 412101
- Kedar Residency
- SHRUTI ANANTA
- SMRUTI GARDEN
- Skyway Elite
- Palm Spring D Wing
- Kesar Kalhaar
- SAI PALLADIUM
- IMPERIAL RESIDENCY
Other projects by S. S. D. Construction
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.