by SHREE BALAJI ASSOCIATES PUNE LLP (Ganraj) · Kharadi, Pune 411014

What’s in the report? →

Possession date of Ganga Platinum A (MahaRERA P52100031418): 31 October 2026, moved from 31 December 2025 (6 months later), and it has already passed. It has 125 homes, 86% sold or booked. 8 complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100031418, and currently active. Its completion date has moved from December 2025 to October 2026: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100031418, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Ganga Platinum A?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Ganga Platinum A has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA04112518234)

    Reason the builder gave MahaRERA:
    “1. The project is 85% complete. 2. Consent of 99.04% of allottees has been uploaded for extension. 3. The consent is provided in Clause 10 of all the annexures uploaded. 4. Revised Form B has been uploaded. 5. The PERT Chart showing the rem…” Read the full reason“1. The project is 85% complete. 2. Consent of 99.04% of allottees has been uploaded for extension. 3. The consent is provided in Clause 10 of all the annexures uploaded. 4. Revised Form B has been uploaded. 5. The PERT Chart showing the remaining work schedule is uploaded under Other Tab No. 1. 6. Quarterly Progress Reports (QPR) have been updated till the latest period. 7. Due to unavoidable circumstances, the project has been delayed. 8. The revised expected completion date is 30/06/2026. 9. We assure you we will procure Occupancy Certificate within stipulated time.”
  3. 31 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ganga Platinum A’s extension records on MahaRERA (P52100031418), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ganga Platinum A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints and 1 court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100031418
Status
Registered and active
Builder
SHREE BALAJI ASSOCIATES PUNE LLP
Location
Kharadi, Pune · 411014
Project type
Residential / Group Housing
Registered on
23 Oct 2021
Completion date at registration
December 2025
Latest completion date
October 2026
Delay so far
6 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
125
Sold or booked
86%
Towers
1
Complaints on MahaRERA
8
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of Ganga Platinum A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A100%100%99%100%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING A: covers 30 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ganga Platinum A every 1–2 months.

Ganga Platinum A: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING A (36 floors, 125 units)
  • Land: 2,958 sq m (about 0.7 acres) · sanctioned built-up 5,920 sq m · recreational space 296 sq m
  • Land, as filed: 68 NEW H NO 3/3 KHARADI
  • Map: Get directions

The builder’s record and reviews

Shree Balaji Associates Pune (a group of 6 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 20 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 11 months); 10 still being built, 3 past the promised date (typically 10 months late); 2 lapsed. 48 complaints on MahaRERA across 8 projects.

Read Google reviews of Ganga Platinum A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ganga Platinum A: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ganga Platinum A

What is the possession date of Ganga Platinum A?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ganga Platinum A in Kharadi, Pune is 31 October 2026 — 6 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

The date has already moved 6 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Ganga Platinum A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ganga Platinum A's builder has filed on MahaRERA, the official one, is 31 October 2026, already 6 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ganga Platinum A extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Platinum A's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "1. The project is 85% complete. 2. Consent of 99.04% of allottees has been uploaded for extension. 3. The consent is provided in Clause 10 of all the annexures uploaded. 4. Revised Form B has been uploaded. 5. The PERT Chart showing the remaining work schedule is uploaded under Other Tab No. 1. 6. Quarterly Progress Reports (QPR) have been updated till the latest period. 7. Due to unavoidable circumstances, the project has been delayed. 8. The revised expected completion date is 30/06/2026. 9. We assure you we will procure Occupancy Certificate within stipulated time.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ganga Platinum A?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ganga Platinum A in Kharadi, Pune is P52100031418.

Is Ganga Platinum A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Platinum A is registered as P52100031418 and its status is "Registered and active".

What is the current construction status of Ganga Platinum A? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Platinum A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING A is 100% done and internal work 99%. GharKundli's full report compares construction progress with the deadline.

Does Ganga Platinum A have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

8 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →

Is Ganga Platinum A safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Platinum A is registered on MahaRERA as P52100031418, its completion date has moved 6 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ganga Platinum A?

Ganga Platinum A is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ganga Platinum A?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Ganga Platinum A: gharkundli.com/tools/property-cost-calculator

Has Ganga Platinum A received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Platinum A is still under construction, with 31 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Ganga Platinum A uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ganga Platinum A was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Ganga Platinum A have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: GANGA PLATINUM B (P52100054598, possession 30 Apr 2028). Check that your agreement names the registration of your own wing.

How can I get updates if Ganga Platinum A's possession date changes?

The latest dates are on Ganga Platinum A's MahaRERA page (P52100031418). GharKundli's Kundli Watch sends a free WhatsApp update on Ganga Platinum A every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ganga Platinum A have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Platinum A has one building filed: BUILDING A with 36 floors and 125 units.

How big is the land of Ganga Platinum A?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Platinum A stands on 2,958 sq m of land (about 0.7 acres), with 5,920 sq m of sanctioned built-up area and 296 sq m of recreational open space.

What is the track record of Ganga Platinum A's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Balaji Associates Pune (a group of 6 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 20 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 11 months); 10 still being built, 3 past the promised date (typically 10 months late); 2 lapsed. 48 complaints on MahaRERA across 8 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Ganga Platinum A?

Google Maps has reviews of Ganga Platinum A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ganga Platinum A?

Ganga Platinum A by SHREE BALAJI ASSOCIATES PUNE LLP (Ganraj) is in Kharadi, Pune, pincode 411014, Maharashtra, and is registered on MahaRERA as P52100031418, per GharKundli's check of MahaRERA records. Its land is filed as 68 NEW H NO 3/3 KHARADI. GharKundli lists all 323 MahaRERA projects in Kharadi (411014).

How many flats are in Ganga Platinum A, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Platinum A has 125 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.

When was Ganga Platinum A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ganga Platinum A was registered on MahaRERA on 23 October 2021. GharKundli did not find a title report on the land on file there.

Does Ganga Platinum A have any legal issues or court cases?

1 court case is listed for Ganga Platinum A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Ganga Platinum A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE BALAJI ASSOCIATES PUNE LLP, the company Ganraj files this project under, which has 9 other projects registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in Kharadi (411014)

All 323 projects in Kharadi (411014) →

Other projects by SHREE BALAJI ASSOCIATES PUNE LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.