PANTAN SYNERGY

by PANTAN INFRAA PRIVATE LIMITED · virar, Palghar

Possession date of PANTAN SYNERGY: 31 December 2025, moved from 31 December 2019 (72 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P99000013139. Status: Lapsed (registration period ended). 9 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about PANTAN SYNERGY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PANTAN SYNERGY has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 June 2021

    Extended at the builder's request (MahaRERA application EXT99000008531)

    Reason the builder gave MahaRERA: “COVID REASONS”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT99000010351)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 57.41% allottees for purpose of extension of RERA registration period of the said project.”

Source: PANTAN SYNERGY’s extension records on MahaRERA (P99000013139), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PANTAN SYNERGY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000013139
Status
Lapsed (registration period ended)
Builder
PANTAN INFRAA PRIVATE LIMITED
Location
virar, Palghar · 401203
Project type
Others
Registered on
14 Sep 2017
Completion date at registration
December 2019
Latest completion date
December 2025
Delay so far
72 months
Homes
58
Sold or booked
100%
Towers
1
Complaints on MahaRERA
9
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of PANTAN SYNERGY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PANTAN SYNERGY100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • PANTAN SYNERGY: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PANTAN SYNERGY every month.

PANTAN SYNERGY: buildings, flats and land, as filed on MahaRERA

  • Buildings: PANTAN SYNERGY (16 floors, 64 units)
  • Land: 474 sq m (about 0.1 acres) · sanctioned built-up 3,067 sq m
  • Boundaries filed include: GARDEN

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PANTAN SYNERGY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PANTAN SYNERGY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PANTAN SYNERGY

What is the possession date of PANTAN SYNERGY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PANTAN SYNERGY in virar, Palghar is 31 December 2025 — 72 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PANTAN SYNERGY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PANTAN SYNERGY's builder has filed on MahaRERA, the official one, is 31 December 2025, already 72 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PANTAN SYNERGY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), PANTAN SYNERGY's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2021, giving the reason "COVID REASONS"; to 31 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 57.41% allottees for purpose of extension of RERA registration period of the said project.".

What is the RERA number of PANTAN SYNERGY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PANTAN SYNERGY in virar, Palghar is P99000013139.

Is PANTAN SYNERGY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PANTAN SYNERGY is registered as P99000013139 and its status is "Lapsed (registration period ended)".

What is the construction status of PANTAN SYNERGY?

According to GharKundli's check of MahaRERA records (updated November 2026), PANTAN SYNERGY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PANTAN SYNERGY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does PANTAN SYNERGY have complaints on MahaRERA?

9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PANTAN SYNERGY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PANTAN SYNERGY is registered on MahaRERA as P99000013139, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 72 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PANTAN SYNERGY's possession date changes?

The latest dates are on PANTAN SYNERGY's MahaRERA page (P99000013139). GharKundli's Kundli Watch sends a free WhatsApp update on PANTAN SYNERGY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PANTAN SYNERGY have?

According to GharKundli's check of MahaRERA records (updated November 2026), PANTAN SYNERGY has one building filed: PANTAN SYNERGY with 16 floors and 64 units.

How big is the land of PANTAN SYNERGY?

According to GharKundli's check of MahaRERA records (updated November 2026), PANTAN SYNERGY stands on 474 sq m of land (about 0.1 acres), with 3,067 sq m of sanctioned built-up area.

Where can I read reviews of PANTAN SYNERGY?

Google Maps has reviews of PANTAN SYNERGY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PANTAN SYNERGY?

PANTAN SYNERGY by PANTAN INFRAA PRIVATE LIMITED is in virar, Palghar (pincode 401203), Maharashtra, and is registered on MahaRERA as P99000013139, per GharKundli's check of MahaRERA records. Its boundaries filed there include GARDEN.

How many homes are in PANTAN SYNERGY?

According to GharKundli's check of MahaRERA records (updated November 2026), PANTAN SYNERGY has 58 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was PANTAN SYNERGY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PANTAN SYNERGY was registered on MahaRERA on 14 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PANTAN SYNERGY?

No court cases are listed for PANTAN SYNERGY on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of PANTAN SYNERGY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PANTAN INFRAA PRIVATE LIMITED.

Other projects in Vasai

All 154 projects in Nallasopara West (401203) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.