Possession date of KALPATARU: 31 December 2025. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100046047. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about KALPATARU?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on KALPATARU

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100046047
Status
Lapsed (registration period ended)
Builder
ISHAN CONSTRUCTION
Location
Chinchwad Pune, Pune · 411033
Project type
Residential / Group Housing
Registered on
15 Jun 2022
Completion date at registration
December 2025
Homes
20
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of KALPATARU, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KALPATARU100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KALPATARU every month.

KALPATARU: buildings, flats and land, as filed on MahaRERA

  • Buildings: KALPATARU (5 floors)
  • Land: 464 sq m (about 0.1 acres) · sanctioned built-up 1,385 sq m
  • Boundaries filed include: ROAD OUT OF LAYOUT

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KALPATARU →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KALPATARU: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KALPATARU

What is the possession date of KALPATARU?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KALPATARU in Chinchwad Pune, Pune is 31 December 2025. That date has already passed.

Is the builder's possession date different from the MahaRERA date for KALPATARU?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KALPATARU's builder has filed on MahaRERA, the official one, is 31 December 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of KALPATARU?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KALPATARU in Chinchwad Pune, Pune is P52100046047.

Is KALPATARU registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KALPATARU is registered as P52100046047 and its status is "Lapsed (registration period ended)".

What is the construction status of KALPATARU?

According to GharKundli's check of MahaRERA records (updated November 2026), KALPATARU's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on KALPATARU is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does KALPATARU have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is KALPATARU safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), KALPATARU is registered on MahaRERA as P52100046047, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KALPATARU's possession date changes?

The latest dates are on KALPATARU's MahaRERA page (P52100046047). GharKundli's Kundli Watch sends a free WhatsApp update on KALPATARU every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KALPATARU have?

According to GharKundli's check of MahaRERA records (updated November 2026), KALPATARU has one building filed: KALPATARU with 5 floors.

How big is the land of KALPATARU?

According to GharKundli's check of MahaRERA records (updated November 2026), KALPATARU stands on 464 sq m of land (about 0.1 acres), with 1,385 sq m of sanctioned built-up area.

Where can I read reviews of KALPATARU?

Google Maps has reviews of KALPATARU written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KALPATARU?

KALPATARU by ISHAN CONSTRUCTION is in Chinchwad Pune, Pune (pincode 411033), near Chinchwadgaon, Maharashtra, and is registered on MahaRERA as P52100046047, per GharKundli's check of MahaRERA records. Its boundaries filed there include ROAD OUT OF LAYOUT.

How many homes are in KALPATARU?

According to GharKundli's check of MahaRERA records (updated November 2026), KALPATARU has 20 homes in 1 tower registered on MahaRERA.

When was KALPATARU registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KALPATARU was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on KALPATARU?

No court cases are listed for KALPATARU on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of KALPATARU?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ISHAN CONSTRUCTION.

Other projects in pincode 411033

All 431 projects in Chinchwadgaon (411033) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.