Skip to content
GharKundli

Samarth Paradise Phase 2

by Samarth Group Builders and Developers · Jalochi Road, PuneAlso near Baramati

Possession date of Samarth Paradise Phase 2: 31 July 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100047609. Status: Lapsed (registration period ended). Its completion date is now July 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about Samarth Paradise Phase 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Samarth Paradise Phase 2 has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 July 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Samarth Paradise Phase 2’s extension records on MahaRERA (P52100047609), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Samarth Paradise Phase 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100047609
Status
Lapsed (registration period ended)
Builder
Samarth Group Builders and Developers
Location
Jalochi Road, Pune · 413102
Project type
Residential / Group Housing
Registered on
14 Nov 2022
Completion date at registration
March 2026
Latest completion date
July 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
29
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Samarth Paradise Phase 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Samarth Paradise Phase 2100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Samarth Paradise Phase 2 every month.

Samarth Paradise Phase 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: Samarth Paradise Phase 2 (6 floors)
  • Land: 622 sq m (about 0.2 acres) · sanctioned built-up 1,743 sq m
  • Boundaries filed include: Layout 9 M Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Samarth Paradise Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Samarth Paradise Phase 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Samarth Paradise Phase 2

What is the possession date of Samarth Paradise Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Samarth Paradise Phase 2 in Jalochi Road, Pune is 31 July 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Samarth Paradise Phase 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Samarth Paradise Phase 2's builder has filed on MahaRERA, the official one, is 31 July 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Samarth Paradise Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Samarth Paradise Phase 2 in Jalochi Road, Pune is P52100047609.

Is Samarth Paradise Phase 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Samarth Paradise Phase 2 is registered as P52100047609 and its status is "Lapsed (registration period ended)".

What is the construction status of Samarth Paradise Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), Samarth Paradise Phase 2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Samarth Paradise Phase 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Samarth Paradise Phase 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Samarth Paradise Phase 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Samarth Paradise Phase 2 is registered on MahaRERA as P52100047609, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Samarth Paradise Phase 2 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Samarth Paradise (P52100030213). Check that your agreement names the registration of your own wing.

How can I get updates if Samarth Paradise Phase 2's possession date changes?

The latest dates are on Samarth Paradise Phase 2's MahaRERA page (P52100047609). GharKundli's Kundli Watch sends a free WhatsApp update on Samarth Paradise Phase 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Samarth Paradise Phase 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Samarth Paradise Phase 2 has one building filed: Samarth Paradise Phase 2 with 6 floors.

How big is the land of Samarth Paradise Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), Samarth Paradise Phase 2 stands on 622 sq m of land (about 0.2 acres), with 1,743 sq m of sanctioned built-up area.

Where can I read reviews of Samarth Paradise Phase 2?

Google Maps has reviews of Samarth Paradise Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Samarth Paradise Phase 2?

Samarth Paradise Phase 2 by Samarth Group Builders and Developers is in Jalochi Road, Pune (pincode 413102), near Baramati, Maharashtra, and is registered on MahaRERA as P52100047609, per GharKundli's check of MahaRERA records. Its boundaries filed there include Layout 9 M Road.

How many homes are in Samarth Paradise Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), Samarth Paradise Phase 2 has 29 homes in 1 tower registered on MahaRERA.

When was Samarth Paradise Phase 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Samarth Paradise Phase 2 was registered on MahaRERA on 14 November 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Samarth Paradise Phase 2?

No court cases are listed for Samarth Paradise Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Samarth Paradise Phase 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Samarth Group Builders and Developers, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in pincode 413102

All 209 projects in Baramati (413102) →

Other projects by Samarth Group Builders and Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.