by SAGAR KALURAM PATOLE · Near Hutatma Rajguru Bridge, Pune

Possession date of 7 SAGAR PLAZA: 31 December 2026. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100050536, and currently active. Its completion date is now December 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about 7 SAGAR PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 7 SAGAR PLAZA has moved

  1. 31 August 2026

    Completion date given when the project was registered

  2. 31 December 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: 7 SAGAR PLAZA’s extension records on MahaRERA (P52100050536), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 7 SAGAR PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100050536
Status
Registered and active
Builder
SAGAR KALURAM PATOLE
Location
Near Hutatma Rajguru Bridge, Pune · 410505
Project type
Others
Registered on
21 Apr 2023
Completion date at registration
August 2026
Latest completion date
December 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
68
Sold or booked
24%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of 7 SAGAR PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING100%100%80%0%
B WING100%100%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • A WING: covers 6 floors
  • B WING: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 7 SAGAR PLAZA every month.

7 SAGAR PLAZA: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING (8 floors, 104 units) · B WING (8 floors, 68 units)
  • Land: 3,224 sq m (about 0.8 acres) · sanctioned built-up 5,178 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of 7 SAGAR PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

7 SAGAR PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 7 SAGAR PLAZA

What is the possession date of 7 SAGAR PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 7 SAGAR PLAZA in Near Hutatma Rajguru Bridge, Pune is 31 December 2026, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for 7 SAGAR PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 7 SAGAR PLAZA's builder has filed on MahaRERA, the official one, is 31 December 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of 7 SAGAR PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 7 SAGAR PLAZA in Near Hutatma Rajguru Bridge, Pune is P52100050536.

Is 7 SAGAR PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 7 SAGAR PLAZA is registered as P52100050536 and its status is "Registered and active".

What is the construction status of 7 SAGAR PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), 7 SAGAR PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does 7 SAGAR PLAZA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is 7 SAGAR PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), 7 SAGAR PLAZA is registered on MahaRERA as P52100050536, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 7 SAGAR PLAZA's possession date changes?

The latest dates are on 7 SAGAR PLAZA's MahaRERA page (P52100050536). GharKundli's Kundli Watch sends a free WhatsApp update on 7 SAGAR PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 7 SAGAR PLAZA have?

According to GharKundli's check of MahaRERA records (updated November 2026), 7 SAGAR PLAZA has 2 buildings filed: A WING with 8 floors and 104 units; B WING with 8 floors and 68 units.

How big is the land of 7 SAGAR PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), 7 SAGAR PLAZA stands on 3,224 sq m of land (about 0.8 acres), with 5,178 sq m of sanctioned built-up area.

Where can I read reviews of 7 SAGAR PLAZA?

Google Maps has reviews of 7 SAGAR PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 7 SAGAR PLAZA?

7 SAGAR PLAZA by SAGAR KALURAM PATOLE is in Near Hutatma Rajguru Bridge, Pune (pincode 410505), Maharashtra, and is registered on MahaRERA as P52100050536, per GharKundli's check of MahaRERA records.

How many homes are in 7 SAGAR PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), 7 SAGAR PLAZA has 68 homes in 2 towers registered on MahaRERA, and 24% of them are sold or booked.

When was 7 SAGAR PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 7 SAGAR PLAZA was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on 7 SAGAR PLAZA?

No court cases are listed for 7 SAGAR PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of 7 SAGAR PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAGAR KALURAM PATOLE, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in Khed

All 41 projects in Rajgurunagar (410505) →

Other projects by SAGAR KALURAM PATOLE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.