Mahindra Happinest Tathawade Phase 3
by Mahindra Lifespace Developers limited · Tathawade, PuneAlso near Punawale, Bapu Buwaji Nagar, Ravet
Possession date of Mahindra Happinest Tathawade Phase 3: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100052559, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Mahindra Happinest Tathawade Phase 3?
How the possession date of Mahindra Happinest Tathawade Phase 3 has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Mahindra Happinest Tathawade Phase 3’s extension records on MahaRERA (P52100052559), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mahindra Happinest Tathawade Phase 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Mahindra Happinest Tathawade Phase 2P52100045388 · possession 30 Sep 2027
- MahaRERA registration
- P52100052559
- Status
- Registered and active
- Builder
- Mahindra Lifespace Developers limited
- Location
- Tathawade, Pune · 411033
- Project type
- Others
- Registered on
- 11 Sep 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 438
- Sold or booked
- 96%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 61
Construction progress of Mahindra Happinest Tathawade Phase 3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building A | 100% | 100% | 40% | 0% |
| Building B | 100% | 100% | 37% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Building A: covers 32 floors
- Building B: covers 32 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahindra Happinest Tathawade Phase 3 every month.
Mahindra Happinest Tathawade Phase 3: buildings, flats and land, as filed on MahaRERA
- Buildings: Building A (32 floors, 253 units) · Building B (32 floors, 249 units)
- Land: 8,687 sq m (about 2.1 acres) · sanctioned built-up 31,177 sq m
- Boundaries filed include: 12m wide service road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Mahindra Lifespace Developers (a group of 4 linked companies) has 94 projects on MahaRERA since 2017, this one included. Of the 53 GharKundli has checked: 11 finished, 8 within the promised date and 3 needed more time (typically 6 months); 36 still being built, 12 past the promised date (typically 34 months late); 6 lapsed. 26 complaints on MahaRERA across 10 projects.
Read Google reviews of Mahindra Happinest Tathawade Phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mahindra Happinest Tathawade Phase 3: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mahindra Happinest Tathawade Phase 3
What is the possession date of Mahindra Happinest Tathawade Phase 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mahindra Happinest Tathawade Phase 3 in Tathawade, Pune is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Mahindra Happinest Tathawade Phase 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahindra Happinest Tathawade Phase 3's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Mahindra Happinest Tathawade Phase 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mahindra Happinest Tathawade Phase 3 in Tathawade, Pune is P52100052559.
Is Mahindra Happinest Tathawade Phase 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahindra Happinest Tathawade Phase 3 is registered as P52100052559 and its status is "Registered and active".
What is the construction status of Mahindra Happinest Tathawade Phase 3?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahindra Happinest Tathawade Phase 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Mahindra Happinest Tathawade Phase 3 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of November 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Mahindra Happinest Tathawade Phase 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahindra Happinest Tathawade Phase 3 is registered on MahaRERA as P52100052559, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Mahindra Happinest Tathawade Phase 3 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Mahindra Happinest Tathawade Phase 2 (P52100045388, possession 30 Sep 2027). Check that your agreement names the registration of your own wing.
How can I get updates if Mahindra Happinest Tathawade Phase 3's possession date changes?
The latest dates are on Mahindra Happinest Tathawade Phase 3's MahaRERA page (P52100052559). GharKundli's Kundli Watch sends a free WhatsApp update on Mahindra Happinest Tathawade Phase 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mahindra Happinest Tathawade Phase 3 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahindra Happinest Tathawade Phase 3 has 2 buildings filed: Building A with 32 floors and 253 units; Building B with 32 floors and 249 units.
How big is the land of Mahindra Happinest Tathawade Phase 3?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahindra Happinest Tathawade Phase 3 stands on 8,687 sq m of land (about 2.1 acres), with 31,177 sq m of sanctioned built-up area.
What is the track record of Mahindra Happinest Tathawade Phase 3's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahindra Lifespace Developers (a group of 4 linked companies) has 94 projects on MahaRERA since 2017, this one included. Of the 53 GharKundli has checked: 11 finished, 8 within the promised date and 3 needed more time (typically 6 months); 36 still being built, 12 past the promised date (typically 34 months late); 6 lapsed. 26 complaints on MahaRERA across 10 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Mahindra Happinest Tathawade Phase 3?
Google Maps has reviews of Mahindra Happinest Tathawade Phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mahindra Happinest Tathawade Phase 3?
Mahindra Happinest Tathawade Phase 3 by Mahindra Lifespace Developers limited is in Tathawade, Pune (pincode 411033), near Punawale, Bapu Buwaji Nagar, Ravet, Maharashtra, and is registered on MahaRERA as P52100052559, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12m wide service road.
How many homes are in Mahindra Happinest Tathawade Phase 3?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahindra Happinest Tathawade Phase 3 has 438 homes in 2 towers registered on MahaRERA, and 96% of them are sold or booked.
When was Mahindra Happinest Tathawade Phase 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahindra Happinest Tathawade Phase 3 was registered on MahaRERA on 11 September 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Mahindra Happinest Tathawade Phase 3?
No court cases are listed for Mahindra Happinest Tathawade Phase 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Mahindra Happinest Tathawade Phase 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Mahindra Lifespace Developers limited, which has 61 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mahindra Happinest Tathawade Phase 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in pincode 411033
- GANGA AMBER PH II
- AISHWARYAM INSIGNIA
- RAMAN STELLAR
- Nirman Serenopolis
- ROHAN HARITA PHASE 4
- Millennium Samriddhi
- KOHINOOR UPTOWN AVENUE
- West World
Other projects by Mahindra Lifespace Developers limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.