WOLLYWOOD PHASE II

by NIRVANA LIFESTYLE VENTURES · Gates Budruk, Palghar

Possession date of WOLLYWOOD PHASE II: 30 April 2027, moved from 30 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000014632, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about WOLLYWOOD PHASE II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of WOLLYWOOD PHASE II has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT99000012921)

    Reason the builder gave MahaRERA:
    “There has been a severe loss of materials and labour due to the flood in the project land resulting in delay AND due to imposition of GST resulting in a higher tax there has been a shortfall in Sales and customer payments thereby affecting…” Read the full reason“There has been a severe loss of materials and labour due to the flood in the project land resulting in delay AND due to imposition of GST resulting in a higher tax there has been a shortfall in Sales and customer payments thereby affecting the construction schedule”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA02092502492)

    Reason the builder gave MahaRERA:
    “There has been a severe loss of materials and labour due to the flood in the project land resulting in delay AND due to imposition of GST resulting in a higher tax there has been a shortfall in Sales and customer payments thereby affecting…” Read the full reason“There has been a severe loss of materials and labour due to the flood in the project land resulting in delay AND due to imposition of GST resulting in a higher tax there has been a shortfall in Sales and customer payments thereby affecting the construction schedule”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: WOLLYWOOD PHASE II’s extension records on MahaRERA (P99000014632), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on WOLLYWOOD PHASE II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000014632
Status
Registered and active
Builder
NIRVANA LIFESTYLE VENTURES
Location
Gates Budruk, Palghar · 421303
Project type
Residential / Group Housing
Registered on
18 Dec 2017
Completion date at registration
December 2022
Latest completion date
April 2027
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
25
Sold or booked
96%
Towers
25
Complaints on MahaRERA
2
Court cases listed
0
Appeals at the tribunal
3
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of WOLLYWOOD PHASE II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VILLA 1100%100%100%90%
VILLA 20%0%0%0%
VILLA 240%0%0%0%
VILLA 25100%100%50%50%
VILLA 26100%100%100%0%
VILLA 28100%100%100%0%
VILLA 31100%100%100%100%
VILLA 32 A100%100%100%100%
VILLA 32B100%100%100%100%
VILLA 33100%100%100%100%
VILLA 34A100%100%100%100%
VILLA 34B100%100%100%100%
VILLA 35A100%100%100%70%
VILLA 35B100%100%100%70%
VILLA 36100%100%100%100%
VILLA 37100%100%100%100%
VILLA 38100%100%100%80%
VILLA 39100%100%100%50%
VILLA 40100%100%100%100%
VILLA 88A100%100%100%100%
VILLA 88B100%100%100%100%
VILLA 89A100%100%100%100%
VILLA 89B100%100%100%100%
VILLA 870%0%0%0%
VILLA 970%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • VILLA 1: covers 0 floors
  • VILLA 2: covers 0 floors
  • VILLA 24: covers 0 floors
  • VILLA 25: covers 0 floors
  • VILLA 26: covers 0 floors
  • VILLA 28: covers 0 floors
  • VILLA 31: covers 0 floors
  • VILLA 32 A: covers 0 floors
  • VILLA 32B: covers 0 floors
  • VILLA 33: covers 0 floors
  • VILLA 34A: covers 0 floors
  • VILLA 34B: covers 0 floors
  • VILLA 35A: covers 0 floors
  • VILLA 35B: covers 0 floors
  • VILLA 36: covers 0 floors
  • VILLA 37: covers 0 floors
  • VILLA 38: covers 0 floors
  • VILLA 39: covers 0 floors
  • VILLA 40: covers 0 floors
  • VILLA 88A: covers 0 floors
  • VILLA 88B: covers 0 floors
  • VILLA 89A: covers 0 floors
  • VILLA 89B: covers 0 floors
  • VILLA 87: covers 0 floors
  • VILLA 97: covers 0 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on WOLLYWOOD PHASE II every month.

WOLLYWOOD PHASE II: buildings, flats and land, as filed on MahaRERA

  • Buildings: VILLA 1 (2 floors, 1 units) · VILLA 2 (2 floors, 1 units) · VILLA 24 (2 floors, 1 units) · VILLA 25 (2 floors, 1 units) · VILLA 26 (2 floors, 1 units) · VILLA 28 (2 floors, 1 units) · VILLA 31 (2 floors, 1 units) · VILLA 32 A (2 floors, 1 units) · and 17 more
  • Land: 4,466 sq m (about 1.1 acres) · recreational space 8,800 sq m
  • Boundaries filed include: VAITARNA RIVER

The builder’s record and reviews

Nirvana Leisure Realty (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 7 still being built, 5 past the promised date (typically 30 months late); 1 lapsed. 25 complaints on MahaRERA across 6 projects.

Read Google reviews of WOLLYWOOD PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

WOLLYWOOD PHASE II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about WOLLYWOOD PHASE II

What is the possession date of WOLLYWOOD PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for WOLLYWOOD PHASE II in Gates Budruk, Palghar is 30 April 2027 — 48 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for WOLLYWOOD PHASE II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date WOLLYWOOD PHASE II's builder has filed on MahaRERA, the official one, is 30 April 2027, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of WOLLYWOOD PHASE II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE II's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2023, giving the reason "There has been a severe loss of materials and labour due to the flood in the project land resulting in delay AND due to imposition of GST resulting in a higher tax there has been a shortfall in Sales and customer payments thereby affecting the construction schedule"; to 31 December 2026, giving the reason "There has been a severe loss of materials and labour due to the flood in the project land resulting in delay AND due to imposition of GST resulting in a higher tax there has been a shortfall in Sales and customer payments thereby affecting the construction schedule". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of WOLLYWOOD PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of WOLLYWOOD PHASE II in Gates Budruk, Palghar is P99000014632.

Is WOLLYWOOD PHASE II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE II is registered as P99000014632 and its status is "Registered and active".

What is the construction status of WOLLYWOOD PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 25 towers. GharKundli's full report compares construction progress with the deadline.

Does WOLLYWOOD PHASE II have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is WOLLYWOOD PHASE II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE II is registered on MahaRERA as P99000014632, its completion date has moved 48 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does WOLLYWOOD PHASE II have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: WOLLYWOOD PHASE III (P99000016446, possession 30 Apr 2027); WOLLYWOOD PHASE IV (P99000016676, possession 30 Apr 2027); WOLLYWOOD PHASE V (P99000053858, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.

How can I get updates if WOLLYWOOD PHASE II's possession date changes?

The latest dates are on WOLLYWOOD PHASE II's MahaRERA page (P99000014632). GharKundli's Kundli Watch sends a free WhatsApp update on WOLLYWOOD PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does WOLLYWOOD PHASE II have?

According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE II has 25 buildings filed: VILLA 1 with 2 floors and 1 units; VILLA 2 with 2 floors and 1 units; VILLA 24 with 2 floors and 1 units; VILLA 25 with 2 floors and 1 units; VILLA 26 with 2 floors and 1 units; VILLA 28 with 2 floors and 1 units; and 19 more.

How big is the land of WOLLYWOOD PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE II stands on 4,466 sq m of land (about 1.1 acres) and 8,800 sq m of recreational open space.

What is the track record of WOLLYWOOD PHASE II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Leisure Realty (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 7 still being built, 5 past the promised date (typically 30 months late); 1 lapsed. 25 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of WOLLYWOOD PHASE II?

Google Maps has reviews of WOLLYWOOD PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is WOLLYWOOD PHASE II?

WOLLYWOOD PHASE II by NIRVANA LIFESTYLE VENTURES is in Gates Budruk, Palghar (pincode 421303), Maharashtra, and is registered on MahaRERA as P99000014632, per GharKundli's check of MahaRERA records. Its boundaries filed there include VAITARNA RIVER.

How many homes are in WOLLYWOOD PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE II has 25 homes in 25 towers registered on MahaRERA, and 96% of them are sold or booked.

When was WOLLYWOOD PHASE II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE II was registered on MahaRERA on 18 December 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on WOLLYWOOD PHASE II?

No court cases are listed for WOLLYWOOD PHASE II on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of WOLLYWOOD PHASE II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NIRVANA LIFESTYLE VENTURES, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in Vada

All 20 projects in Wada (421303) →

Other projects by NIRVANA LIFESTYLE VENTURES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.