WOLLYWOOD PHASE III
by NIRVANA LIFESTYLE VENTURES · Gates Budruk, Palghar
Possession date of WOLLYWOOD PHASE III: 30 April 2027, moved from 30 March 2023 (45 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000016446, and currently active. Its completion date has moved from March 2023 to April 2027: 45 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about WOLLYWOOD PHASE III?
How the possession date of WOLLYWOOD PHASE III has moved
30 March 2023
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT99000027106)
Reason the builder gave MahaRERA: “Delay due to flood in the project, lock down the construction work”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: WOLLYWOOD PHASE III’s extension records on MahaRERA (P99000016446), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on WOLLYWOOD PHASE III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- WOLLYWOOD PHASE IIP99000014632 · possession 30 Apr 2027
- WOLLYWOOD PHASE IVP99000016676 · possession 30 Apr 2027
- WOLLYWOOD PHASE VP99000053858 · possession 30 Apr 2027
- MahaRERA registration
- P99000016446
- Status
- Registered and active
- Builder
- NIRVANA LIFESTYLE VENTURES
- Location
- Gates Budruk, Palghar · 421303
- Project type
- Residential / Group Housing
- Registered on
- 11 May 2018
- Completion date at registration
- March 2023
- Latest completion date
- April 2027
- Delay so far
- 45 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 46
- Sold or booked
- 35%
- Towers
- 3
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of WOLLYWOOD PHASE III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A1 - SIMRAN | 0% | 0% | 0% | 0% |
| B-CHANDANI | 0% | 0% | 0% | 0% |
| A2 - QUEEN | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on WOLLYWOOD PHASE III every month.
WOLLYWOOD PHASE III: buildings, flats and land, as filed on MahaRERA
- Buildings: A1 - SIMRAN (6 floors) · B-CHANDANI (7 floors) · A2 - QUEEN (6 floors)
- Car parking: 3 covered, 46 open
- Land: 4,936 sq m (about 1.2 acres) · recreational space 8,800 sq m
- Boundaries filed include: VAITARNA RIVER
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Nirvana Leisure Realty (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 7 still being built, 5 past the promised date (typically 30 months late); 1 lapsed. 25 complaints on MahaRERA across 6 projects.
Read Google reviews of WOLLYWOOD PHASE III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
WOLLYWOOD PHASE III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about WOLLYWOOD PHASE III
What is the possession date of WOLLYWOOD PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for WOLLYWOOD PHASE III in Gates Budruk, Palghar is 30 April 2027 — 45 months later than 30 March 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for WOLLYWOOD PHASE III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date WOLLYWOOD PHASE III's builder has filed on MahaRERA, the official one, is 30 April 2027, already 45 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of WOLLYWOOD PHASE III extended?
According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE III's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Delay due to flood in the project, lock down the construction work". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of WOLLYWOOD PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of WOLLYWOOD PHASE III in Gates Budruk, Palghar is P99000016446.
Is WOLLYWOOD PHASE III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE III is registered as P99000016446 and its status is "Registered and active".
What is the construction status of WOLLYWOOD PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE III's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does WOLLYWOOD PHASE III have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is WOLLYWOOD PHASE III safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE III is registered on MahaRERA as P99000016446, its completion date has moved 45 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does WOLLYWOOD PHASE III have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: WOLLYWOOD PHASE II (P99000014632, possession 30 Apr 2027); WOLLYWOOD PHASE IV (P99000016676, possession 30 Apr 2027); WOLLYWOOD PHASE V (P99000053858, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if WOLLYWOOD PHASE III's possession date changes?
The latest dates are on WOLLYWOOD PHASE III's MahaRERA page (P99000016446). GharKundli's Kundli Watch sends a free WhatsApp update on WOLLYWOOD PHASE III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does WOLLYWOOD PHASE III have?
According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE III has 3 buildings filed: A1 - SIMRAN with 6 floors; B-CHANDANI with 7 floors; A2 - QUEEN with 6 floors.
How much parking does WOLLYWOOD PHASE III have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 3 covered and 46 open car parking spaces for WOLLYWOOD PHASE III.
How big is the land of WOLLYWOOD PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE III stands on 4,936 sq m of land (about 1.2 acres) and 8,800 sq m of recreational open space.
What is the track record of WOLLYWOOD PHASE III's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Leisure Realty (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 7 still being built, 5 past the promised date (typically 30 months late); 1 lapsed. 25 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of WOLLYWOOD PHASE III?
Google Maps has reviews of WOLLYWOOD PHASE III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is WOLLYWOOD PHASE III?
WOLLYWOOD PHASE III by NIRVANA LIFESTYLE VENTURES is in Gates Budruk, Palghar (pincode 421303), Maharashtra, and is registered on MahaRERA as P99000016446, per GharKundli's check of MahaRERA records. Its boundaries filed there include VAITARNA RIVER.
How many homes are in WOLLYWOOD PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE III has 46 homes in 3 towers registered on MahaRERA, and 35% of them are sold or booked.
When was WOLLYWOOD PHASE III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), WOLLYWOOD PHASE III was registered on MahaRERA on 11 May 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on WOLLYWOOD PHASE III?
No court cases are listed for WOLLYWOOD PHASE III on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of WOLLYWOOD PHASE III?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NIRVANA LIFESTYLE VENTURES, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of WOLLYWOOD PHASE III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Vada
- WOLLYWOOD PHASE II
- WOLLYWOOD PHASE IV
- Navkar Hills River Bay View-Part-1
- Status Pride - Phase 1
- Sontakke Arcade
- SWAPNAPURTI COMPLEX
- Parnkuti Row House
- Swastik Heights
Other projects by NIRVANA LIFESTYLE VENTURES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.