Bajarang Riddhivinayak Apartment

by Jai Bajarang Construction · Navali, Palghar 401404Also near Palghar West, Tembhode, Palghar EastRegistered on MahaRERA as “Riddhivinayak Apartment”

What’s in the report? →

Possession: Bajarang Riddhivinayak Apartment (MahaRERA P99000014934) is marked completed on MahaRERA. It has 21 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000014934. Status: Completed.

Source: MahaRERA website — records for P99000014934, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Bajarang Riddhivinayak Apartment?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Bajarang Riddhivinayak Apartment has moved

  1. 30 November 2019

    Completion date given when the project was registered

  2. 29 November 2020

    Extended at the builder's request (MahaRERA application EXT99000003959)

    Reason the builder gave MahaRERA:
    “At the time of Registration, had by mistakenly committed date of completion less than 2 years which is less for the project completion. Sales issue also led to financial crunch. Only 2 units booked till date in the project. Project works al…” Read the full reason“At the time of Registration, had by mistakenly committed date of completion less than 2 years which is less for the project completion. Sales issue also led to financial crunch. Only 2 units booked till date in the project. Project works all going in full swing right now & will be completed within 6-7 Months. I have also obtained the no objection certificate from the only 2 allottees of the project (Attached). So request you to grant me the extension.”
  3. 31 March 2022

    Extended at the builder's request (MahaRERA application EXT99000010158)

    Reason the builder gave MahaRERA: “Last year lockdown & then its effect on sale. Again this year pandemic & restrictions.”
  4. 30 September 2022

    Revised completion date on MahaRERA

Source: Bajarang Riddhivinayak Apartment’s extension records on MahaRERA (P99000014934), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Bajarang Riddhivinayak Apartment

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000014934
Status
Completed
Builder
Jai Bajarang Construction
Location
Navali, Palghar · 401404
Project type
Residential / Group Housing
Registered on
15 Jan 2018
Completion date at registration
November 2019
Latest completion date
September 2022
Delay so far
34 months
Homes
21
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Bajarang Riddhivinayak Apartment, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Riddhivinayak Apartment100%100%100%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bajarang Riddhivinayak Apartment every 1–2 months.

Bajarang Riddhivinayak Apartment: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Jai Bajarang Construction has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 29 months). No complaints on MahaRERA.

Read Google reviews of Bajarang Riddhivinayak Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Bajarang Riddhivinayak Apartment: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Bajarang Riddhivinayak Apartment

What is the possession date of Bajarang Riddhivinayak Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Bajarang Riddhivinayak Apartment in Navali, Palghar is 30 September 2022 — 34 months later than 30 November 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Bajarang Riddhivinayak Apartment?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Bajarang Riddhivinayak Apartment's builder has filed on MahaRERA, the official one, is 30 September 2022, already 34 months later than the 30 November 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Bajarang Riddhivinayak Apartment extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment's builder applied to MahaRERA to extend the completion date 2 times: to 29 November 2020, giving the reason "At the time of Registration, had by mistakenly committed date of completion less than 2 years which is less for the project completion. Sales issue also led to financial crunch. Only 2 units booked till date in the project. Project works all going in full swing right now & will be completed within 6-7 Months. I have also obtained the no objection certificate from the only 2 allottees of the project (Attached). So request you to grant me the extension."; to 31 March 2022, giving the reason "Last year lockdown & then its effect on sale. Again this year pandemic & restrictions.".

What is the RERA number of Bajarang Riddhivinayak Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Bajarang Riddhivinayak Apartment in Navali, Palghar is P99000014934.

Is Bajarang Riddhivinayak Apartment registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment is registered as P99000014934 and its status is "Completed".

What is the current construction status of Bajarang Riddhivinayak Apartment? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment's status on MahaRERA is "Completed". As filed by the builder, slab work on Riddhivinayak Apartment is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Bajarang Riddhivinayak Apartment have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Bajarang Riddhivinayak Apartment safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment is registered on MahaRERA as P99000014934, its MahaRERA status is "Completed", its completion date has moved 34 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Bajarang Riddhivinayak Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Bajarang Riddhivinayak Apartment?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Bajarang Riddhivinayak Apartment: gharkundli.com/tools/property-cost-calculator

Has Bajarang Riddhivinayak Apartment received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Bajarang Riddhivinayak Apartment completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment is marked completed on MahaRERA, and the completion date filed there is 30 September 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Bajarang Riddhivinayak Apartment uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Bajarang Riddhivinayak Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Bajarang Riddhivinayak Apartment's possession date changes?

The latest dates are on Bajarang Riddhivinayak Apartment's MahaRERA page (P99000014934). GharKundli's Kundli Watch sends a free WhatsApp update on Bajarang Riddhivinayak Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Bajarang Riddhivinayak Apartment have?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment has one building filed: Riddhivinayak Apartment with 6 floors.

How big is the land of Bajarang Riddhivinayak Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment stands on 525 sq m of land (about 0.1 acres), with 625 sq m of sanctioned built-up area.

What is the track record of Bajarang Riddhivinayak Apartment's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Jai Bajarang Construction has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 29 months). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Bajarang Riddhivinayak Apartment?

Google Maps has reviews of Bajarang Riddhivinayak Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Bajarang Riddhivinayak Apartment?

Bajarang Riddhivinayak Apartment by Jai Bajarang Construction is in Navali, Palghar, pincode 401404 (near Palghar West, Tembhode, Palghar East), Maharashtra, and is registered on MahaRERA as P99000014934, per GharKundli's check of MahaRERA records. Its land is filed as Gut No-27/2/A, Plot No-24. GharKundli lists all 621 MahaRERA projects in Palghar (401404).

How many flats are in Bajarang Riddhivinayak Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment has 21 homes in 1 tower registered on MahaRERA.

When was Bajarang Riddhivinayak Apartment registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Riddhivinayak Apartment was registered on MahaRERA on 15 January 2018. GharKundli did not find a title report on the land on file there.

Does Bajarang Riddhivinayak Apartment have any legal issues or court cases?

No court cases are listed for Bajarang Riddhivinayak Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Bajarang Riddhivinayak Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Jai Bajarang Construction, which has 1 other project registered on MahaRERA.

Other projects in Palghar (401404)

All 621 projects in Palghar (401404) →

Other projects by Jai Bajarang Construction

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.