Skip to content
GharKundli

Bajarang Ganapati Apartment

by Jai Bajarang Construction · Palghar West, Palghar 401402Also near MahimRegistered on MahaRERA as “Ganapati Apartment”

What’s in the report? →

Possession: Bajarang Ganapati Apartment (MahaRERA P99000015531) is marked completed on MahaRERA. It has 19 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000015531. Status: Completed.

Source: MahaRERA website — records for P99000015531, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Bajarang Ganapati Apartment?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Bajarang Ganapati Apartment has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT99000005414)

    Reason the builder gave MahaRERA:
    “Had underestimated completion time while registering for RERA. Also due to market conditions, sale was hampered & hence having financial crunch in between. But now, works are almost 80% completed & will be final within 3-4 months. Also have…” Read the full reason“Had underestimated completion time while registering for RERA. Also due to market conditions, sale was hampered & hence having financial crunch in between. But now, works are almost 80% completed & will be final within 3-4 months. Also have booked only 3 units till date. So request you to grant the said extension.”
  3. 30 December 2021

    Revised completion date on MahaRERA

Source: Bajarang Ganapati Apartment’s extension records on MahaRERA (P99000015531), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Bajarang Ganapati Apartment

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000015531
Status
Completed
Builder
Jai Bajarang Construction
Location
Palghar West, Palghar · 401402
Project type
Residential / Group Housing
Registered on
7 Mar 2018
Completion date at registration
December 2019
Latest completion date
December 2021
Delay so far
24 months
Homes
19
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Bajarang Ganapati Apartment, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Ganapati Apartment100%100%90%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bajarang Ganapati Apartment every 1–2 months.

Bajarang Ganapati Apartment: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Jai Bajarang Construction has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 29 months). No complaints on MahaRERA.

Read Google reviews of Bajarang Ganapati Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Bajarang Ganapati Apartment: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Bajarang Ganapati Apartment

What is the possession date of Bajarang Ganapati Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Bajarang Ganapati Apartment in Palghar West, Palghar is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Bajarang Ganapati Apartment?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Bajarang Ganapati Apartment's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Bajarang Ganapati Apartment extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "Had underestimated completion time while registering for RERA. Also due to market conditions, sale was hampered & hence having financial crunch in between. But now, works are almost 80% completed & will be final within 3-4 months. Also have booked only 3 units till date. So request you to grant the said extension.".

What is the RERA number of Bajarang Ganapati Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Bajarang Ganapati Apartment in Palghar West, Palghar is P99000015531.

Is Bajarang Ganapati Apartment registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment is registered as P99000015531 and its status is "Completed".

What is the current construction status of Bajarang Ganapati Apartment? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment's status on MahaRERA is "Completed". As filed by the builder, slab work on Ganapati Apartment is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Bajarang Ganapati Apartment have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Bajarang Ganapati Apartment safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment is registered on MahaRERA as P99000015531, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Bajarang Ganapati Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Bajarang Ganapati Apartment?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Bajarang Ganapati Apartment: gharkundli.com/tools/property-cost-calculator

Has Bajarang Ganapati Apartment received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Bajarang Ganapati Apartment completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment is marked completed on MahaRERA, and the completion date filed there is 30 December 2021. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Bajarang Ganapati Apartment uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Bajarang Ganapati Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Bajarang Ganapati Apartment's possession date changes?

The latest dates are on Bajarang Ganapati Apartment's MahaRERA page (P99000015531). GharKundli's Kundli Watch sends a free WhatsApp update on Bajarang Ganapati Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Bajarang Ganapati Apartment have?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment has one building filed: Ganapati Apartment with 5 floors.

How big is the land of Bajarang Ganapati Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment stands on 414 sq m of land (about 0.1 acres), with 496 sq m of sanctioned built-up area.

What is the track record of Bajarang Ganapati Apartment's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Jai Bajarang Construction has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 29 months). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Bajarang Ganapati Apartment?

Google Maps has reviews of Bajarang Ganapati Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Bajarang Ganapati Apartment?

Bajarang Ganapati Apartment by Jai Bajarang Construction is in Palghar West, Palghar, pincode 401402 (near Mahim), Maharashtra, and is registered on MahaRERA as P99000015531, per GharKundli's check of MahaRERA records. Its land is filed as Survey No-380, Plot No-87. GharKundli lists all 42 MahaRERA projects in Palghar West (401402).

How many flats are in Bajarang Ganapati Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment has 19 homes in 1 tower registered on MahaRERA.

When was Bajarang Ganapati Apartment registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Bajarang Ganapati Apartment was registered on MahaRERA on 7 March 2018. GharKundli did not find a title report on the land on file there.

Does Bajarang Ganapati Apartment have any legal issues or court cases?

No court cases are listed for Bajarang Ganapati Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Bajarang Ganapati Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Jai Bajarang Construction, which has 1 other project registered on MahaRERA.

Other projects in Palghar West (401402)

All 42 projects in Palghar West (401402) →

Other projects by Jai Bajarang Construction

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.