Possession date of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B (MahaRERA P99000015066): 30 December 2021, moved from 31 December 2019 (24 months later), and it has already passed. It has 72 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000015066. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P99000015066, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2021) has passed.

What do you want to know about MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT99000003983)

    Reason the builder gave MahaRERA: “need more time to complete the project in all ascepts, so we are applying for extention of time under rera.”
  3. 30 December 2021

    Revised completion date on MahaRERA

Source: MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B’s extension records on MahaRERA (P99000015066), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000015066
Status
Lapsed (registration period ended)
Builder
Mahadeep Builders and Developers
Location
Umroli Tal. and Dist. Palghar, Palghar · 401404
Project type
Residential / Group Housing
Registered on
23 Jan 2018
Completion date at registration
December 2019
Latest completion date
December 2021
Delay so far
24 months
Homes
72
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Mahadeep Type A Wing A100%100%59%1%
Mahadeep Type A2 Wing B100%100%59%1%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B every 1–2 months.

MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B: buildings, flats and land, as filed on MahaRERA

  • Buildings: Mahadeep Type A Wing A (11 floors) · Mahadeep Type A2 Wing B (11 floors)
  • Land: 2,477 sq m (about 0.6 acres) · sanctioned built-up 2,477 sq m
  • Boundaries filed include: School Bldg No 2, Play Ground
  • Land, as filed: Survey No. 154/A. 185, 187
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B

What is the possession date of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B in Umroli Tal. and Dist. Palghar, Palghar is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration. That date has already passed.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B extended?

According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "need more time to complete the project in all ascepts, so we are applying for extention of time under rera.".

What is the RERA number of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B in Umroli Tal. and Dist. Palghar, Palghar is P99000015066.

Is MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B is registered as P99000015066 and its status is "Lapsed (registration period ended)".

What is the current construction status of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B is registered on MahaRERA as P99000015066, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B: gharkundli.com/tools/property-cost-calculator

Has MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B's possession date changes?

The latest dates are on MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B's MahaRERA page (P99000015066). GharKundli's Kundli Watch sends a free WhatsApp update on MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B have?

According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B has 2 buildings filed: Mahadeep Type A Wing A with 11 floors; Mahadeep Type A2 Wing B with 11 floors.

How big is the land of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B stands on 2,477 sq m of land (about 0.6 acres), with 2,477 sq m of sanctioned built-up area.

What are the reviews of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

Google Maps has reviews of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B by Mahadeep Builders and Developers is in Umroli Tal. and Dist. Palghar, Palghar, pincode 401404, Maharashtra, and is registered on MahaRERA as P99000015066, per GharKundli's check of MahaRERA records. Its boundaries filed there include School Bldg No 2, Play Ground. Its land is filed as Survey No. 154/A. 185, 187. GharKundli lists all 621 MahaRERA projects in Palghar (401404).

How many flats are in MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B has 72 homes in 2 towers registered on MahaRERA.

When was MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B was registered on MahaRERA on 23 January 2018. GharKundli did not find a title report on the land on file there.

Does MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B have any legal issues or court cases?

No court cases are listed for MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of MAHADEEP Building No. 1 Type A and Type A 2 Wing A and Wing B?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Mahadeep Builders and Developers.

Other projects in Palghar (401404)

All 621 projects in Palghar (401404) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.