SHRI BALAJI NIWAS

by BHOOMI ENTERPRISES · PalgharAlso near Tembhode, Navali, Jawhar

Possession: SHRI BALAJI NIWAS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000015857. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SHRI BALAJI NIWAS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHRI BALAJI NIWAS has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 29 December 2020

    Extended at the builder's request (MahaRERA application EXT99000005014)

    Reason the builder gave MahaRERA: “Beceause of shortage of material like sand ban by maharastra govt,some delay because of ellection in shortage of material,i am requesting to extend my rera possesion date for 1 year,thanks.”
  3. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT99000010803)

    Reason the builder gave MahaRERA:
    “we dont have booked any sale, Because of that we dont have enough funds for complete the construction work, so bcoz of that reason project has affected lots of problems..so it's request to exetend our project completion date to 31st March 2…” Read the full reason“we dont have booked any sale, Because of that we dont have enough funds for complete the construction work, so bcoz of that reason project has affected lots of problems..so it's request to exetend our project completion date to 31st March 2023.”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT99000016497)

    Reason the builder gave MahaRERA:
    “Due to Covid-19, and there after it affected the Cash flow & it is slow and thus there is shortage of materials & Labours. Thus leading to slow down of construction work. We are trying our best to Complete the Project is our new proposed ex…” Read the full reason“Due to Covid-19, and there after it affected the Cash flow & it is slow and thus there is shortage of materials & Labours. Thus leading to slow down of construction work. We are trying our best to Complete the Project is our new proposed extension date.”

Source: SHRI BALAJI NIWAS’s extension records on MahaRERA (P99000015857), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHRI BALAJI NIWAS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000015857
Status
Completed
Builder
BHOOMI ENTERPRISES
Location
Palghar · 401404
Project type
Residential / Group Housing
Registered on
28 Mar 2018
Completion date at registration
December 2019
Latest completion date
December 2024
Delay so far
60 months
Homes
13
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SHRI BALAJI NIWAS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shri Balaji Niwas100%100%100%30%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRI BALAJI NIWAS every month.

SHRI BALAJI NIWAS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHRI BALAJI NIWAS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHRI BALAJI NIWAS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHRI BALAJI NIWAS

What is the possession date of SHRI BALAJI NIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHRI BALAJI NIWAS in Palghar is 31 December 2024 — 60 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHRI BALAJI NIWAS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRI BALAJI NIWAS's builder has filed on MahaRERA, the official one, is 31 December 2024, already 60 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHRI BALAJI NIWAS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI BALAJI NIWAS's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2020, giving the reason "Beceause of shortage of material like sand ban by maharastra govt,some delay because of ellection in shortage of material,i am requesting to extend my rera possesion date for 1 year,thanks."; to 31 March 2023, giving the reason "we dont have booked any sale, Because of that we dont have enough funds for complete the construction work, so bcoz of that reason project has affected lots of problems..so it's request to exetend our project completion date to 31st March 2023."; to 31 December 2024, giving the reason "Due to Covid-19, and there after it affected the Cash flow & it is slow and thus there is shortage of materials & Labours. Thus leading to slow down of construction work. We are trying our best to Complete the Project is our new proposed extension date.".

What is the RERA number of SHRI BALAJI NIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHRI BALAJI NIWAS in Palghar is P99000015857.

Is SHRI BALAJI NIWAS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI BALAJI NIWAS is registered as P99000015857 and its status is "Completed".

What is the construction status of SHRI BALAJI NIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI BALAJI NIWAS's status on MahaRERA is "Completed". As filed by the builder, slab work on Shri Balaji Niwas is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHRI BALAJI NIWAS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHRI BALAJI NIWAS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI BALAJI NIWAS is registered on MahaRERA as P99000015857, its MahaRERA status is "Completed", its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHRI BALAJI NIWAS's possession date changes?

The latest dates are on SHRI BALAJI NIWAS's MahaRERA page (P99000015857). GharKundli's Kundli Watch sends a free WhatsApp update on SHRI BALAJI NIWAS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHRI BALAJI NIWAS have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI BALAJI NIWAS has one building filed: Shri Balaji Niwas with 6 floors.

How big is the land of SHRI BALAJI NIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI BALAJI NIWAS stands on 396 sq m of land (about 0.1 acres), with 474 sq m of sanctioned built-up area.

Where can I read reviews of SHRI BALAJI NIWAS?

Google Maps has reviews of SHRI BALAJI NIWAS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHRI BALAJI NIWAS?

SHRI BALAJI NIWAS by BHOOMI ENTERPRISES is in Palghar (pincode 401404), near Tembhode, Navali, Jawhar, Maharashtra, and is registered on MahaRERA as P99000015857, per GharKundli's check of MahaRERA records.

How many homes are in SHRI BALAJI NIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI BALAJI NIWAS has 13 homes in 1 tower registered on MahaRERA.

When was SHRI BALAJI NIWAS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRI BALAJI NIWAS was registered on MahaRERA on 28 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SHRI BALAJI NIWAS?

No court cases are listed for SHRI BALAJI NIWAS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHRI BALAJI NIWAS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BHOOMI ENTERPRISES, which has 2 other projects registered on MahaRERA.