HARI RESIDENCY PHASE I

by LOTUS LAKSHMINARAYAN HOMES · Kopari, Chandansar, PalgharAlso near Virar East

Possession date of HARI RESIDENCY PHASE I: 30 April 2028, moved from 30 April 2023 (56 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000015966, and currently active. Its completion date has moved from April 2023 to April 2028: 56 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about HARI RESIDENCY PHASE I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HARI RESIDENCY PHASE I has moved

  1. 30 April 2023

    Completion date given when the project was registered

  2. 29 April 2024

    Extended at the builder's request (MahaRERA application EXT99000016519)

    Reason the builder gave MahaRERA:
    “Due to Covid – 19 Pandemic, unable to complete the construction work by us before deadline declared by us and certificate given by you to us. Hence, we are requesting you to extend its deadline date by one more year that’s 30/04/2024. Pleas…” Read the full reason“Due to Covid – 19 Pandemic, unable to complete the construction work by us before deadline declared by us and certificate given by you to us. Hence, we are requesting you to extend its deadline date by one more year that’s 30/04/2024. Please do the needful for the same.”
  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT99000019846)

    Reason the builder gave MahaRERA: “DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON TIME”
  4. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: HARI RESIDENCY PHASE I’s extension records on MahaRERA (P99000015966), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HARI RESIDENCY PHASE I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000015966
Status
Registered and active
Builder
LOTUS LAKSHMINARAYAN HOMES
Location
Kopari, Chandansar, Palghar · 401305
Project type
Residential / Group Housing
Registered on
10 Apr 2018
Completion date at registration
April 2023
Latest completion date
April 2028
Delay so far
56 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
314
Sold or booked
54%
Towers
4
Complaints on MahaRERA
6
Court cases listed
0
Appeals at the tribunal
6
Title report on file
Not found

Construction progress of HARI RESIDENCY PHASE I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HARI RESIDENCY PHASE I BUILDING NO 1 WING A100%100%100%95%
HARI RESIDENCY PHASE I BUILDING NO 1 WING B100%55%0%20%
HARI RESIDENCY PHASE I BUILDING NO 1 WING C100%100%100%100%
HARI RESIDENCY PHASE 1 BUILDING NO 2100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • HARI RESIDENCY PHASE I BUILDING NO 1 WING A: covers 16 floors
  • HARI RESIDENCY PHASE I BUILDING NO 1 WING B: covers 16 floors
  • HARI RESIDENCY PHASE I BUILDING NO 1 WING C: covers 8 floors
  • HARI RESIDENCY PHASE 1 BUILDING NO 2: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HARI RESIDENCY PHASE I every month.

HARI RESIDENCY PHASE I: buildings, flats and land, as filed on MahaRERA

  • Buildings: HARI RESIDENCY PHASE I BUILDING NO 1 WING A (16 floors, 150 units) · HARI RESIDENCY PHASE I BUILDING NO 1 WING B (16 floors, 102 units) · HARI RESIDENCY PHASE I BUILDING NO 1 WING C (8 floors, 67 units) · HARI RESIDENCY PHASE 1 BUILDING NO 2 (7 floors, 42 units)
  • Land: 5,290 sq m (about 1.3 acres) · sanctioned built-up 4,778 sq m · recreational space 711 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of HARI RESIDENCY PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HARI RESIDENCY PHASE I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HARI RESIDENCY PHASE I

What is the possession date of HARI RESIDENCY PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HARI RESIDENCY PHASE I in Kopari, Chandansar, Palghar is 30 April 2028 — 56 months later than 30 April 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for HARI RESIDENCY PHASE I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HARI RESIDENCY PHASE I's builder has filed on MahaRERA, the official one, is 30 April 2028, already 56 months later than the 30 April 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HARI RESIDENCY PHASE I extended?

According to GharKundli's check of MahaRERA records (updated October 2026), HARI RESIDENCY PHASE I's builder applied to MahaRERA to extend the completion date 2 times: to 29 April 2024, giving the reason "Due to Covid – 19 Pandemic, unable to complete the construction work by us before deadline declared by us and certificate given by you to us. Hence, we are requesting you to extend its deadline date by one more year that’s 30/04/2024. Please do the needful for the same."; to 31 December 2027, giving the reason "DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON TIME". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of HARI RESIDENCY PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HARI RESIDENCY PHASE I in Kopari, Chandansar, Palghar is P99000015966.

Is HARI RESIDENCY PHASE I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HARI RESIDENCY PHASE I is registered as P99000015966 and its status is "Registered and active".

What is the construction status of HARI RESIDENCY PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), HARI RESIDENCY PHASE I's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 55% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does HARI RESIDENCY PHASE I have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is HARI RESIDENCY PHASE I safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), HARI RESIDENCY PHASE I is registered on MahaRERA as P99000015966, its completion date has moved 56 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HARI RESIDENCY PHASE I's possession date changes?

The latest dates are on HARI RESIDENCY PHASE I's MahaRERA page (P99000015966). GharKundli's Kundli Watch sends a free WhatsApp update on HARI RESIDENCY PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HARI RESIDENCY PHASE I have?

According to GharKundli's check of MahaRERA records (updated October 2026), HARI RESIDENCY PHASE I has 4 buildings filed: HARI RESIDENCY PHASE I BUILDING NO 1 WING A with 16 floors and 150 units; HARI RESIDENCY PHASE I BUILDING NO 1 WING B with 16 floors and 102 units; HARI RESIDENCY PHASE I BUILDING NO 1 WING C with 8 floors and 67 units; HARI RESIDENCY PHASE 1 BUILDING NO 2 with 7 floors and 42 units.

How big is the land of HARI RESIDENCY PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), HARI RESIDENCY PHASE I stands on 5,290 sq m of land (about 1.3 acres), with 4,778 sq m of sanctioned built-up area and 711 sq m of recreational open space.

Where can I read reviews of HARI RESIDENCY PHASE I?

Google Maps has reviews of HARI RESIDENCY PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HARI RESIDENCY PHASE I?

HARI RESIDENCY PHASE I by LOTUS LAKSHMINARAYAN HOMES is in Kopari, Chandansar, Palghar (pincode 401305), near Virar East, Maharashtra, and is registered on MahaRERA as P99000015966, per GharKundli's check of MahaRERA records.

How many homes are in HARI RESIDENCY PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), HARI RESIDENCY PHASE I has 314 homes in 4 towers registered on MahaRERA, and 54% of them are sold or booked.

When was HARI RESIDENCY PHASE I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HARI RESIDENCY PHASE I was registered on MahaRERA on 10 April 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on HARI RESIDENCY PHASE I?

No court cases are listed for HARI RESIDENCY PHASE I on MahaRERA, and 6 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of HARI RESIDENCY PHASE I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LOTUS LAKSHMINARAYAN HOMES.

All projects with possession due in 2028 in Palghar →

Other projects in Vasai

All 89 projects in Virar East (401305) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.