by SHREE ADINATH BUILDERS · Boisar, Palghar 401501Registered on MahaRERA as “SYMPHONY”

What’s in the report? →

Possession: Adinath Symphony (MahaRERA P99000016885) is marked completed on MahaRERA. It has 78 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000016885. Status: Completed.

Source: MahaRERA website — records for P99000016885, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Adinath Symphony?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Adinath Symphony

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000016885
Status
Completed
Builder
SHREE ADINATH BUILDERS
Location
Boisar, Palghar · 401501
Project type
Residential / Group Housing
Registered on
20 Jun 2018
Completion date at registration
June 2022
Latest completion date
June 2022
Homes
78
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Adinath Symphony, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SYMPHONY BLDG NO 4 TYPE D WING A100%100%100%100%
SYMPHONY BUILDING NO 4 TYPE E-1 WING B100%100%100%100%
SYMPHONY BLDG NO 4 TYPE E WING C100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Adinath Symphony every 1–2 months.

Adinath Symphony: buildings, flats and land, as filed on MahaRERA

  • Buildings: SYMPHONY BLDG NO 4 TYPE D WING A (6 floors) · SYMPHONY BUILDING NO 4 TYPE E-1 WING B (6 floors) · SYMPHONY BLDG NO 4 TYPE E WING C (6 floors)
  • Land: 3,097 sq m (about 0.8 acres) · sanctioned built-up 6,681 sq m · recreational space 1,450 sq m
  • Boundaries filed include: 9 meter layout road, 12 meter layout road
  • Land, as filed: 61/4/1,61/1/6,61/1/7,61/1/8,61/1/9,61/1/10,63/1,63/3,63/4
  • Map: Get directions

The builder’s record and reviews

Shree Adinath Builders has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA.

Read Google reviews of Adinath Symphony →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Adinath Symphony: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Adinath Symphony

What is the possession date of Adinath Symphony?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Adinath Symphony in Boisar, Palghar is 30 June 2022.

Is the builder's possession date different from the MahaRERA date for Adinath Symphony?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Adinath Symphony's builder has filed on MahaRERA, the official one, is 30 June 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Adinath Symphony?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Adinath Symphony in Boisar, Palghar is P99000016885.

Is Adinath Symphony registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony is registered as P99000016885 and its status is "Completed".

What is the current construction status of Adinath Symphony? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Adinath Symphony have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Adinath Symphony safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony is registered on MahaRERA as P99000016885, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Adinath Symphony?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Adinath Symphony?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Adinath Symphony: gharkundli.com/tools/property-cost-calculator

Has Adinath Symphony received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Adinath Symphony completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony is marked completed on MahaRERA, and the completion date filed there is 30 June 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Adinath Symphony uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Adinath Symphony was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Adinath Symphony's possession date changes?

The latest dates are on Adinath Symphony's MahaRERA page (P99000016885). GharKundli's Kundli Watch sends a free WhatsApp update on Adinath Symphony every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Adinath Symphony have?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony has 3 buildings filed: SYMPHONY BLDG NO 4 TYPE D WING A with 6 floors; SYMPHONY BUILDING NO 4 TYPE E-1 WING B with 6 floors; SYMPHONY BLDG NO 4 TYPE E WING C with 6 floors.

How big is the land of Adinath Symphony?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony stands on 3,097 sq m of land (about 0.8 acres), with 6,681 sq m of sanctioned built-up area and 1,450 sq m of recreational open space.

What is the track record of Adinath Symphony's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Adinath Builders has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 finished, all within the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Adinath Symphony?

Google Maps has reviews of Adinath Symphony written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Adinath Symphony?

Adinath Symphony by SHREE ADINATH BUILDERS is in Boisar, Palghar, pincode 401501, Maharashtra, and is registered on MahaRERA as P99000016885, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 meter layout road, 12 meter layout road. Its land is filed as 61/4/1,61/1/6,61/1/7,61/1/8,61/1/9,61/1/10,63/1,63/3,63/4. GharKundli lists all 180 MahaRERA projects in Boisar (401501).

How many flats are in Adinath Symphony?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony has 78 homes in 3 towers registered on MahaRERA.

When was Adinath Symphony registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Adinath Symphony was registered on MahaRERA on 20 June 2018. GharKundli did not find a title report on the land on file there.

Does Adinath Symphony have any legal issues or court cases?

No court cases are listed for Adinath Symphony on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Adinath Symphony?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE ADINATH BUILDERS, which has 1 other project registered on MahaRERA.

Other projects in Boisar (401501)

All 180 projects in Boisar (401501) →

Other projects by SHREE ADINATH BUILDERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.